Shatrunjay Heights
Deedo IDDP-THN-5RAGCompletion was pushed back 4 months, to Apr 2029; no MahaRERA orders on record; 38% of its units are booked.
Kamatghar, Thane 421302 · by Onyx Buildcon LLP
Buying a flat here?
See every deed registered on it.
Completion was pushed back 4 months, to Apr 2029
- This projectRegistered 29 Sep 2021, completion promised 31 Dec 2028, revised to 30 Apr 2029.
No extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales, rentals and mortgages matched to this project · the free view shows a price band
The building
Open a building to see every flat, floor by floor.
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationP51700030901
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P51700030901 | 29 Sep 2021 | 31 Dec 2028 | 30 Apr 2029 | Onyx Buildcon LLP | Project page |
Documents148
1 document held by Deedo, 147 filings listed on MahaRERA's project page
Finance
- PAN CardPAN.pdf · uploaded 26 Aug 2021Source
Legal
- Declaration Form BForm B Affidavit.pdf · uploaded 25 Aug 2021Source
- Legal Title reportTitle Certificate_Onyx.pdf · uploaded 27 Aug 2021Source
- Legal Title reportSearch Report_Onyx.pdf · uploaded 27 Aug 2021Source
- Legal Title reportTitle Certificate_Kamlesh.pdf · uploaded 27 Aug 2021Source
- Legal Title reportSearch Report_Kamlesh.pdf · uploaded 27 Aug 2021Source
- Legal Title reportFormat-A_Onyx.pdf · uploaded 23 Sep 2021Source
Show all 148 documentsShow fewer documents
Legal
- Legal Title reportFormat-A_Kamlesh.pdf · uploaded 23 Sep 2021Source
Migrated
- 1 Details of encumbrancesNo Encumbrance Certificate.pdf · uploaded 25 Aug 2021Source
- 1 Declaration about Commencement CertificateFORMAT-D.pdf · uploaded 25 Aug 2021Source
- 1 Declaration in FORM BForm B Affidavit.pdf · uploaded 25 Aug 2021Source
- 1 PAN CardPAN.pdf · uploaded 26 Aug 2021Source
- 1 Copy of Layout Approval (in case of layout)Plan-1_page-0001.pdf · uploaded 26 Aug 2021Source
- 1 Building Plan Approval / NA Order for plotted developmentPlan-2_page-0001.pdf · uploaded 26 Aug 2021Source
- 2 Building Plan Approval / NA Order for plotted developmentPlan-3_page-0001.pdf · uploaded 26 Aug 2021Source
- 1 Commencement Certificates / NA Order for plotted developmentApproval.pdf · uploaded 26 Aug 2021Source
- 1 Copy of the legal title reportTitle Certificate_Onyx.pdf · uploaded 27 Aug 2021Source
- 2 Copy of the legal title reportSearch Report_Onyx.pdf · uploaded 27 Aug 2021Source
- 3 Copy of the legal title reportTitle Certificate_Kamlesh.pdf · uploaded 27 Aug 2021Source
- 4 Copy of the legal title reportSearch Report_Kamlesh.pdf · uploaded 27 Aug 2021Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form-3_Shartrunjay.pdf · uploaded 27 Aug 2021Source
- 1 Proforma of Allotment letterDraft Allotment letter.pdf · uploaded 3 Sep 2021Source
- 2 Proforma of Allotment letterDraft Sale Agreement.pdf · uploaded 3 Sep 2021Source
- 5 Copy of the legal title reportFormat-A_Onyx.pdf · uploaded 23 Sep 2021Source
- 6 Copy of the legal title reportFormat-A_Kamlesh.pdf · uploaded 23 Sep 2021Source
- 2 Copy of Layout Approval (in case of layout)Onyx 2C Ground Floor.pdf · uploaded 25 Aug 2022Source
- 3 Copy of Layout Approval (in case of layout)Onyx 1C.pdf · uploaded 25 Aug 2022Source
- 4 Copy of Layout Approval (in case of layout)Onyx 2C Ground Floor.pdf · uploaded 25 Aug 2022Source
- 5 Copy of Layout Approval (in case of layout)Onyx 4C Floor 3.pdf · uploaded 25 Aug 2022Source
- 6 Copy of Layout Approval (in case of layout)Onyx 5C Floor 4 to 6.pdf · uploaded 25 Aug 2022Source
- 7 Copy of Layout Approval (in case of layout)Onyx 6C Floor 7.pdf · uploaded 25 Aug 2022Source
- 3 Building Plan Approval / NA Order for plotted developmentOnyx 9C.pdf · uploaded 25 Aug 2022Source
- 4 Building Plan Approval / NA Order for plotted developmentOnyx 10C.pdf · uploaded 25 Aug 2022Source
- 5 Building Plan Approval / NA Order for plotted developmentOnyx CC Updated.pdf · uploaded 25 Aug 2022Source
- 2 Commencement Certificates / NA Order for plotted developmentOnyx CC Updated.pdf · uploaded 25 Aug 2022Source
- 2 a Details of encumbrances concerned to FinanceNo Encumbrance Certificate - Legal.pdf · uploaded 25 Jan 2023Source
- 1 b Details of encumbrances concerned to LegalNo Encumbrance Certificate - Legal.pdf · uploaded 25 Jan 2023Source
- 1 CERSAI detailsCERSAI_Declaration.pdf · uploaded 25 Jan 2023Source
- 1 Disclosure of Interest in Other Real Estate OrganizationsAnnexure A.pdf · uploaded 25 Jan 2023Source
- 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFormat A.pdf · uploaded 25 Jan 2023Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form-3 - Onyx Buildcon LLP - 31-12-22.pdf · uploaded 27 Jan 2023Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)Form 2A.pdf · uploaded 30 Jan 2023Source
- Form 1Form-1 Onyx Buildcon LLP 31-03-23.pdf · uploaded 21 Jul 2025Source
- Form 2Form-2 Onyx Buildcon LLP 31-03-23.pdf · uploaded 21 Jul 2025Source
- Form 3Form-3 Onyx Buildcon LLP 31-03-2023.pdf · uploaded 21 Jul 2025Source
- Disclosure of Sold and Booked InventoryDISCOLURE OF SOLD AND UNSOLD.pdf · uploaded 21 Jul 2025Source
- Form 1Form-1 Onyx 30-06-23.pdf · uploaded 21 Jul 2025Source
- Form 2Form-2 Onyx 30-06-23.pdf · uploaded 21 Jul 2025Source
- Form 3Form 3 Onyx Buildcon LLP 30-06-2023.pdf · uploaded 21 Jul 2025Source
- Disclosure of Sold and Booked InventoryDISCOLURE OF SOLD AND UNSOLD.pdf · uploaded 21 Jul 2025Source
- Form 1Form-1 Onyx 30-09-23.pdf · uploaded 21 Jul 2025Source
- Form 2Form-2 Onyx 30-09-23.pdf · uploaded 21 Jul 2025Source
- Form 3Form 3 Onyx Buildcon LLP 30-09-2023.pdf · uploaded 21 Jul 2025Source
- Disclosure of Sold and Booked InventoryDISCOLURE OF SOLD AND UNSOLD.pdf · uploaded 21 Jul 2025Source
- Form 1Form-1 Onyx 31-12-23.pdf · uploaded 21 Jul 2025Source
- Form 2Form-2 Onyx 31-12-23.pdf · uploaded 21 Jul 2025Source
- Form 3Form 3 Onyx Buildcon LLP 31-12-2023.pdf · uploaded 21 Jul 2025Source
- Disclosure of Sold and Booked InventoryDISCOLURE OF SOLD AND UNSOLD.pdf · uploaded 21 Jul 2025Source
- Form 1Form-1 Onyx 31-03-24.pdf · uploaded 21 Jul 2025Source
- Form 2Form-2 Onyx 31-03-24.pdf · uploaded 21 Jul 2025Source
- Form 3Form 3 Onyx Buildcon LLP 31-03-2024.pdf · uploaded 21 Jul 2025Source
- Disclosure of Sold and Booked InventoryDISCOLURE OF SOLD AND UNSOLD.pdf · uploaded 21 Jul 2025Source
- Form 1Form-1 Onyx 30-06-24.pdf · uploaded 21 Jul 2025Source
- Form 2Form-2 Onyx 30-06-24.pdf · uploaded 21 Jul 2025Source
- Form 3Form 3 Onyx Buildcon LLP 30-06-2024.pdf · uploaded 21 Jul 2025Source
- Disclosure of Sold and Booked InventoryDISCOLURE OF SOLD AND UNSOLD.pdf · uploaded 21 Jul 2025Source
- Form 1Form-1 Onyx 30-09-24.pdf · uploaded 21 Jul 2025Source
- Form 2Form-2 Onyx 30-09-24.pdf · uploaded 21 Jul 2025Source
- Form 3Form 3 Onyx Buildcon LLP 30-09-2024.pdf · uploaded 21 Jul 2025Source
- Disclosure of Sold and Booked InventoryDISCOLURE OF SOLD AND UNSOLD.pdf · uploaded 21 Jul 2025Source
- Form 1Form-1 Onyx 31-12-24.pdf · uploaded 21 Jul 2025Source
- Form 2Form-2 Onyx 31-12-24.pdf · uploaded 21 Jul 2025Source
- Form 3Form 3 Onyx Buildcon LLP 31-12-2024.pdf · uploaded 21 Jul 2025Source
- Disclosure of Sold and Booked InventoryDISCOLURE OF SOLD AND UNSOLD.pdf · uploaded 21 Jul 2025Source
- Form 1Form-1 Onyx 31-03-25.pdf · uploaded 21 Jul 2025Source
- Form 2Form-2 Onyx 31-03-25.pdf · uploaded 21 Jul 2025Source
- Form 3Form 3 Onyx Buildcon LLP 31-03-2025.pdf · uploaded 21 Jul 2025Source
- Disclosure of Sold and Booked InventoryDISCOLURE OF SOLD AND UNSOLD.pdf · uploaded 21 Jul 2025Source
- Withdrawal Update Form 1Withdrawal Application Form1.pdf · uploaded 12 Aug 2025Source
- Withdrawal Update Form 2Withdrawal Application Form2.pdf · uploaded 12 Aug 2025Source
- Withdrawal Update Form 3Withdrawal Application Form3.pdf · uploaded 12 Aug 2025Source
- Form 1Form-1 - Onyx 30-09-21.pdf · uploaded 31 Oct 2025Source
- Form 2Form-2 Onyx 30-09-21.pdf · uploaded 31 Oct 2025Source
- Form 3Form-3 Onyx Buildcon LLP Q2 30-09-2021.pdf · uploaded 31 Oct 2025Source
- Disclosure of Sold and Booked InventoryDISCOLURE OF SOLD AND UNSOLD.pdf · uploaded 31 Oct 2025Source
- Form 1Form-1 - Onyx 31-12-21.pdf · uploaded 31 Oct 2025Source
- Form 2Form-2 Onyx 31-12-21.pdf · uploaded 31 Oct 2025Source
- Form 3Form-3 Onyx Buildcon LLP Q3 31-12-2021.pdf · uploaded 31 Oct 2025Source
- Disclosure of Sold and Booked InventoryDISCOLURE OF SOLD AND UNSOLD.pdf · uploaded 31 Oct 2025Source
- Disclosure of Sold and Booked InventoryDISCOLURE OF SOLD AND UNSOLD.pdf · uploaded 31 Oct 2025Source
- Form 1Form-1 - Onyx 31-03-22.pdf · uploaded 31 Oct 2025Source
- Form 2Form-2 Onyx 31-03-22.pdf · uploaded 31 Oct 2025Source
- Form 3Form-3 Onyx Buildcon LLP Q4 31-03-2022.pdf · uploaded 31 Oct 2025Source
- Disclosure of Sold and Booked InventoryDISCOLURE OF SOLD AND UNSOLD.pdf · uploaded 31 Oct 2025Source
- Form 2Form-2 Onyx 30-06-22.pdf · uploaded 31 Oct 2025Source
- Form 3Form-3 Onyx Buildcon LLP Q1 30-06-2022.pdf · uploaded 31 Oct 2025Source
- Form 1Form-1 - Onyx 30-06-22.pdf · uploaded 31 Oct 2025Source
- Disclosure of Sold and Booked InventoryDISCOLURE OF SOLD AND UNSOLD.pdf · uploaded 31 Oct 2025Source
- Form 1Form-1 - Onyx 31-12-22.pdf · uploaded 31 Oct 2025Source
- Form 2Form-2 Onyx 31-12-22.pdf · uploaded 31 Oct 2025Source
- Form 3Form-3 Onyx Buildcon LLP Q3 31-12-2022.pdf · uploaded 31 Oct 2025Source
- Form 1Form-1 - Onyx Buildcon LLP 30-09-2022.pdf · uploaded 1 Nov 2025Source
- Form 2Form-2 Onyx 30-09-22.pdf · uploaded 1 Nov 2025Source
- Form 3Form-3 Onyx Buildcon LLP Q2 30-09-2022.pdf · uploaded 1 Nov 2025Source
- Disclosure of Sold and Booked InventoryDISCOLURE OF SOLD AND UNSOLD.pdf · uploaded 1 Nov 2025Source
- Form 5 (FY 2021-2022)Form-5 21-22.pdf · uploaded 29 Nov 2025Source
- Withdrawal Update Form 1Form-1 30-09-25 Onyx.pdf · uploaded 12 Dec 2025Source
- Withdrawal Update Form 2Form-2 Onyx Buildcon LLP 30-09-2025.pdf · uploaded 12 Dec 2025Source
- Withdrawal Update Form 3Form-3 Onyx Buildcon LLP 30-09-2025.pdf · uploaded 12 Dec 2025Source
- Form 5 (FY 2024-2025)Form 5 24-25.pdf · uploaded 5 Jan 2026Source
- Withdrawal Update Form 1Form-1 Onyx Buildcon LLP 31-12-2025.pdf · uploaded 31 Jan 2026Source
- Withdrawal Update Form 2Form-2 Onyx Buildcon LLP 31-12-2025.pdf · uploaded 31 Jan 2026Source
- Withdrawal Update Form 3Form-3 Onyx Buildcon LLP 31-12-2025.pdf · uploaded 31 Jan 2026Source
- Form 2A (FY 2021-2022)Form 2A 21-22.pdf · uploaded 31 Jan 2026Source
- Form 2A (FY 2022-2023)Form 2A 22-23.pdf · uploaded 31 Jan 2026Source
- Form 2A (FY 2023-2024)Form 2A 23-24 .pdf · uploaded 31 Jan 2026Source
- Form 2A (FY 2024-2025)Form 2A 24-25 .pdf · uploaded 31 Jan 2026Source
- Form 5 (FY 2022-2023)Form-5 22-23.pdf · uploaded 31 Jan 2026Source
- Form 5 (FY 2023-2024)Form-5 23-24.pdf · uploaded 31 Jan 2026Source
- Withdrawal Update Form 1Form-1 Onyx Buildcon LLP 31-03-2026.pdf · uploaded 25 Aug 2026Source
- Withdrawal Update Form 1Form-1 Onyx Buildcon LLP 30-06-2026.pdf · uploaded 25 Aug 2026Source
- Withdrawal Update Form 2Form-2 Onyx Buildcon LLP 31-03-2026.pdf · uploaded 25 Aug 2026Source
- Withdrawal Update Form 2Form-2 Onyx Buildcon LLP 30-06-2026.pdf · uploaded 25 Aug 2026Source
- Withdrawal Update Form 3Form-3 Onyx Buildcon LLP 31-03-2026.pdf · uploaded 25 Aug 2026Source
- Withdrawal Update Form 3Form-3 Onyx Buildcon LLP 30-06-2026.pdf · uploaded 25 Aug 2026Source
- Form 2A (FY 2025-2026)Form 2A 25-26.pdf · uploaded 27 Aug 2026Source
Planning Authority
- DocumentyqWRVx6SVvONYX_BLUE_PRINT.pdf · uploaded 19 Sep 2026Source
- DocumentvlFxaa9Z8M2007.pdf · uploaded 19 Sep 2026Source
- DocumentyqWRVx6SVvREVISED_CC.pdf · uploaded 19 Sep 2026Source
- Document1760446928_BNMC-23-ENTRY-43961_R1.pdf_8_76DSE_Sign.pdfSign.pdf · uploaded 19 Sep 2026Source
- Document1760446928_BNMC-23-ENTRY-43961_R1.html · uploaded 19 Sep 2026Source
- DocumentC06bi234Kk7-12.pdf · uploaded 19 Sep 2026Source
- DocumentCert_RB_557676_442tLXwXSign.pdf · uploaded 19 Sep 2026Source
Technical
- DocumentPlan-1_page-0001.pdf · uploaded 26 Aug 2021Source
- DocumentPlan-2_page-0001.pdf · uploaded 26 Aug 2021Source
- DocumentPlan-3_page-0001.pdf · uploaded 26 Aug 2021Source
- DocumentOnyx 2C Ground Floor.pdf · uploaded 25 Aug 2022Source
- DocumentOnyx 1C.pdf · uploaded 25 Aug 2022Source
- DocumentOnyx 2C Ground Floor.pdf · uploaded 25 Aug 2022Source
- DocumentOnyx 4C Floor 3.pdf · uploaded 25 Aug 2022Source
- DocumentOnyx 5C Floor 4 to 6.pdf · uploaded 25 Aug 2022Source
- DocumentOnyx 6C Floor 7.pdf · uploaded 25 Aug 2022Source
- DocumentOnyx 9C.pdf · uploaded 25 Aug 2022Source
- DocumentOnyx 10C.pdf · uploaded 25 Aug 2022Source
- DocumentOnyx CC Updated.pdf · uploaded 25 Aug 2022Source
Technical (Architect)
- DocumentForm-1 Onyx Buildcon LLP 30-06-2026.pdf · uploaded 25 Aug 2026Source
Technical (Engineer)
- DocumentForm-2 Onyx Buildcon LLP 30-06-2026.pdf · uploaded 25 Aug 2026Source
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvalsLand parcel 141/3/1, 141/3/2
As registered with MahaRERA and published on its project page
- Project type
- Residential / Group Housing
- Status on MahaRERA
- Certificate Signed
- Unit types
- 2BHK, 3BHK, 4BHK, Office space, Shop248 units in all
- Address
- 204/A, 203/A, 203/B, 141/3/1, 141/3/2, Agra Road, KamatgharPIN 421302
- Village
- Bhiwandi (M Corp.), Bhiwandi taluka
- Location
- 19.27906, 73.04677
- Land area for this project
- 4,135 sq m (44,509 sq ft)
- Permissible built-up area
- 28,577 sq m (3,07,600 sq ft)
- Sanctioned built-up area
- 3,912 sq m (42,109 sq ft)
- Designated bank account
- 85
- Developed in phases
- No
Survey, CTS, gat or plot numbers
Land as published on MahaRERA's project page
204/A, 203/A, 203/B, 141/3/1, 141/3/2
Boundaries
- North
- 24 Mtr Wide D P Road
- South
- Property Bearing S No 137
- East
- 24 Mtr Wide D P Road
- West
- Property Bearing S No 3
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking248 units
94 of 248 units booked (38%), as the promoter reported to MahaRERA
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 2BHK | 66.93 sq m · 720 sq ft | 40 | 19 |
| 2BHK | 68.32 sq m · 735 sq ft | 17 | 8 |
| 3BHK | 98.17 sq m · 1,057 sq ft | 20 | 10 |
| 4BHK | 79.75 sq m · 858 sq ft | 1 | 0 |
| 4BHK | 144.42 sq m · 1,555 sq ft | 9 | 3 |
| Office space | 13.1 sq m · 141 sq ft | 6 | 1 |
| Office space | 17.48 sq m · 188 sq ft | 2 | 2 |
| Office space | 17.62 sq m · 190 sq ft | 4 | 1 |
Show all 28 unit rowsShow fewer unit rows
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| Office space | 18 sq m · 194 sq ft | 8 | 0 |
| Office space | 18.6 sq m · 200 sq ft | 6 | 2 |
| Office space | 23.58 sq m · 254 sq ft | 6 | 2 |
| Office space | 24.91 sq m · 268 sq ft | 2 | 2 |
| Office space | 26.28 sq m · 283 sq ft | 6 | 0 |
| Office space | 28.03 sq m · 302 sq ft | 12 | 0 |
| Office space | 28.53 sq m · 307 sq ft | 40 | 3 |
| Office space | 31.5 sq m · 339 sq ft | 4 | 0 |
| Office space | 34.56 sq m · 372 sq ft | 6 | 1 |
| Office space | 37.34 sq m · 402 sq ft | 2 | 1 |
| Office space | 38.56 sq m · 415 sq ft | 6 | 0 |
| Office space | 40.72 sq m · 438 sq ft | 2 | 2 |
| Office space | 44.98 sq m · 484 sq ft | 4 | 0 |
| Office space | 48.44 sq m · 521 sq ft | 20 | 16 |
| Office space | 62.21 sq m · 670 sq ft | 4 | 0 |
| Shop | 30.72 sq m · 331 sq ft | 1 | 1 |
| Shop | 35.27 sq m · 380 sq ft | 9 | 9 |
| Shop | 35.38 sq m · 381 sq ft | 9 | 9 |
| Shop | 71.23 sq m · 767 sq ft | 1 | 1 |
| Shop | 77.27 sq m · 832 sq ft | 1 | 1 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Professionals3
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Hk Design Consultants | — |
| Chartered accountant | B M Chauhan & Co | — |
| Engineer | Hk Design Consultants | — |
Source: MahaRERA project page. Contact details are not shown.