Skip to content
Promised date passed8 floorsRERA P51700007310

Miracle, Tharwani Miracle

Deedo IDDP-THN-0QV7-MIRACL

MahaRERA has not published a flat-by-flat record for this tower, and no registered deed names it yet.

Median saleNot on recordneeds 3 or more sales
Booked23%9 of 40 · MahaRERA
Completion31 Dec 2018as registered
Units & parking in Miracle
TypeCarpet areaUnitsBooked
1 BHK32.4 m² (348 sq.ft)70
1 BHK33.2 m² (358 sq.ft)71
1 BHK33.6 m² (361 sq.ft)70
1 BHK35.3 m² (380 sq.ft)70
COMMERCIAL6.6 m² (71 sq.ft)11
COMMERCIAL9.4 m² (101 sq.ft)11
COMMERCIAL10.1 m² (109 sq.ft)11
COMMERCIAL10.5 m² (113 sq.ft)11
COMMERCIAL11.1 m² (119 sq.ft)10
COMMERCIAL11.9 m² (128 sq.ft)22
COMMERCIAL12.3 m² (132 sq.ft)10
COMMERCIAL12.6 m² (136 sq.ft)11
COMMERCIAL16.3 m² (175 sq.ft)10
COMMERCIAL18.3 m² (197 sq.ft)11
COMMERCIAL23.6 m² (253 sq.ft)10
As registered with MahaRERA
RERA registration
P51700007310 · registered 17 Aug 2017
Promised completion
31 Dec 2018
Revised completion
31 Dec 2018
Sanctioned habitable floors
8
Sanctioned floors (incl. basement, stilt, podium)
8
Units declared
0
Homes
0
Shops and offices
0
MahaRERA status
Certificate Signed
Deedo ID
DP-THN-0QV7-MIRACL
Questions about Miracle

When is Miracle due for completion?

The MahaRERA registration promises 31 Dec 2018.

How many floors does Miracle have?

8 sanctioned habitable floors, as registered with MahaRERA.

Data through13 Oct 2026SourcesMahaRERA registration and project page · IGR Maharashtra Index IIFloors and units are as registered; a promoter can revise them in later filings. Party names appear only inside an unlocked Index II.Report a problemMethodology