Residential / Group Housing · 1 building · 270 unitsRERA P51700009127

Skylon

Deedo IDDP-THN-AECW

Its promised completion date, Mar 2026, has passed and MahaRERA does not show it completed; no MahaRERA orders on record; 95% of its units are booked.

Kalyan-Dombivali (M Corp.), Thane 421306 · by Bhagwati Space Conventure

Delivery8 mo past duePromised Mar 2026 · no extension on record · not shown completedRegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales95% booked256 of 270 units · as the promoter reported to MahaRERA

Buying a flat here?

See every deed registered on it.

Its promised completion date, Mar 2026, has passed and MahaRERA does not show it completed

  • This projectRegistered 19 Aug 2017, completion promised 31 Mar 2026, and still not shown completed today.

No extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales first, then rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

The building

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP51700009127
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5170000912719 Aug 201731 Mar 202631 Mar 2026Bhagwati Space ConventureProject page
Documents102

1 document held by Deedo, 101 filings listed on MahaRERA's project page

Registration certificate

Finance

  • PAN Cardbhagwati space conventure pan card.pdf · uploaded 29 Jul 2017Source

Legal

  • Legal Title reporttitel certifiace.pdf · uploaded 29 Jul 2017Source
  • Legal Title reportsearch gandhi.pdf · uploaded 29 Jul 2017Source
  • Declaration Form BAffidavit hemant sir 1.pdf · uploaded 29 Jul 2017Source

Migrated

  • 1 PAN Cardbhagwati space conventure pan card.pdf · uploaded 29 Jul 2017Source
  • 1 Copy of the legal title reporttitel certifiace.pdf · uploaded 29 Jul 2017Source
  • 2 Copy of the legal title reportsearch gandhi.pdf · uploaded 29 Jul 2017Source
Show all 102 documentsShow fewer documents

Migrated

  • 1 Details of encumbrancesencumbrances.pdf · uploaded 29 Jul 2017Source
  • 1 Copy of Layout Approval (in case of layout)MYSCAN_20170428_0001.pdf · uploaded 29 Jul 2017Source
  • 1 Building Plan Approval (IOD)MYSCAN_20170428_0002.pdf · uploaded 29 Jul 2017Source
  • 2 Building Plan Approval (IOD)MYSCAN_20170428_0003.pdf · uploaded 29 Jul 2017Source
  • 3 Building Plan Approval (IOD)MYSCAN_20170428_0004.pdf · uploaded 29 Jul 2017Source
  • 4 Building Plan Approval (IOD)MYSCAN_20170428_0005.pdf · uploaded 29 Jul 2017Source
  • 5 Building Plan Approval (IOD)MYSCAN_20170428_0006.pdf · uploaded 29 Jul 2017Source
  • 6 Building Plan Approval (IOD)MYSCAN_20170428_0007.pdf · uploaded 29 Jul 2017Source
  • 1 Commencement Certificates / NA Order for plotted developmentCC.pdf · uploaded 29 Jul 2017Source
  • 1 Declaration in FORM BAffidavit hemant sir 1.pdf · uploaded 29 Jul 2017Source
  • 1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)architect certificate 12.pdf · uploaded 29 Jul 2017Source
  • 1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)s r consultants 1.pdf · uploaded 29 Jul 2017Source
  • 1 Certificates of CA (Form 3)Form 3 Scan - Signed 1.pdf · uploaded 29 Jul 2017Source
  • 1 Proforma of Allotment letterSkylon final Agreement.pdf · uploaded 29 Jul 2017Source
  • 2 Proforma of Allotment letterfinal BSC allotment letter.pdf · uploaded 29 Jul 2017Source
  • 2 Details of encumbrancesBSC- Mortgage deed reduce size Part 1.pdf · uploaded 31 Jul 2018Source
  • 3 Details of encumbrancesBSC- Mortgage deed reduce size Part 2.pdf · uploaded 31 Jul 2018Source
  • 4 Details of encumbrancesBSC- Mortgage deed reduce size Part 3.pdf · uploaded 31 Jul 2018Source
  • 5 Details of encumbrancesBSC- Mortgage deed reduce size Part 4.pdf · uploaded 31 Jul 2018Source
  • 6 Details of encumbrancesBSC- Mortgage deed reduce size Part 5.pdf · uploaded 31 Jul 2018Source
  • 7 Details of encumbrancesBSC- Mortgage deed reduce size Part 6.pdf · uploaded 31 Jul 2018Source
  • 8 Details of encumbrancesBSC- Mortgage deed reduce size Part 7.pdf · uploaded 31 Jul 2018Source
  • 9 Details of encumbrancesBSC- Mortgage deed reduce size Part 8.pdf · uploaded 31 Jul 2018Source
  • 10 Details of encumbrancesBSC- Mortgage deed reduce size Part 9.pdf · uploaded 31 Jul 2018Source
  • 11 Details of encumbrancesBSC- Mortgage deed reduce size Part 10.pdf · uploaded 31 Jul 2018Source
  • 1 Certificates of CA (Form 5)Bhagwati Space Conventure Form 5.pdf · uploaded 28 Sep 2018Source
  • 2 Certificates of CA (Form 5)Form 5.pdf · uploaded 27 Sep 2019Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)Form 5 BSC.pdf · uploaded 30 Sep 2020Source
  • 1 Declaration about Commencement CertificateDeclaration to CA for RERA.pdf · uploaded 11 Aug 2021Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)Form 5.pdf · uploaded 11 Aug 2021Source
  • 2 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Form 1 Skylon 30 june 2021.pdf · uploaded 13 Aug 2021Source
  • 2 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Form 2 Skylon 30 June 2021.pdf · uploaded 13 Aug 2021Source
  • 1 Disclosure of sold/ booked inventorySold Flat for Rera 1.pdf · uploaded 13 Aug 2021Source
  • 2 Certificates of CA (Form 3)Form 3 Scan 2.pdf · uploaded 13 Aug 2021Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)Form 5 Bhagwati Space Coventure.pdf · uploaded 28 Sep 2021Source
  • 3 Certificates of CA (Form 5)Bhagwati Space Conventure Form 5.pdf · uploaded 29 Sep 2022Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)Bhagwati Space Conventure Form 5.pdf · uploaded 30 Sep 2022Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)Form 5.pdf · uploaded 29 Sep 2023Source
  • 3 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Form 2.pdf · uploaded 1 Jan 2024Source
  • 3 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Form 2.pdf · uploaded 1 Jan 2024Source
  • 4 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Form 2.pdf · uploaded 1 Jan 2024Source
  • 5 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Form 2.pdf · uploaded 1 Jan 2024Source
  • 6 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Form 2.pdf · uploaded 1 Jan 2024Source
  • 2 Disclosure of sold/ booked inventorySold Unsold Letter Mar 22.pdf · uploaded 8 Jan 2024Source
  • 3 Disclosure of sold/ booked inventorySold Unsold Letter June 22.pdf · uploaded 8 Jan 2024Source
  • 4 Disclosure of sold/ booked inventorySold Unsold Letter Sep 22.pdf · uploaded 8 Jan 2024Source
  • 5 Disclosure of sold/ booked inventorySold Unsold Letter Dec 22.pdf · uploaded 8 Jan 2024Source
  • 6 Disclosure of sold/ booked inventorySold Unsold Letter Mar 23.pdf · uploaded 8 Jan 2024Source
  • 7 Disclosure of sold/ booked inventorySold Unsold Letter June 23.pdf · uploaded 8 Jan 2024Source
  • 7 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Form 2.pdf · uploaded 9 Jan 2024Source
  • 3 Certificates of CA (Form 3)Form 3 2.pdf · uploaded 9 Jan 2024Source
  • 4 Certificates of CA (Form 3)Form 3.pdf · uploaded 9 Jan 2024Source
  • 5 Certificates of CA (Form 3)Form 3.pdf · uploaded 9 Jan 2024Source
  • 6 Certificates of CA (Form 3)Form 3.pdf · uploaded 9 Jan 2024Source
  • 7 Certificates of CA (Form 3)Form 3.pdf · uploaded 9 Jan 2024Source
  • 8 Certificates of CA (Form 3)Form 3 1.pdf · uploaded 9 Jan 2024Source
  • 4 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Form 1 Mar 22.pdf · uploaded 1 Mar 2024Source
  • 5 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Form 1 June 22.pdf · uploaded 1 Mar 2024Source
  • 6 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Form 3.pdf · uploaded 1 Mar 2024Source
  • 7 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Form 1 Dec 22.pdf · uploaded 1 Mar 2024Source
  • 8 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Form 1 Mar 23.pdf · uploaded 1 Mar 2024Source
  • 9 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Form 1 June 23.pdf · uploaded 1 Mar 2024Source
  • 10 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Form 1 Sep 23.pdf · uploaded 5 Mar 2024Source
  • 11 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Form 1 Dec 23.pdf · uploaded 5 Mar 2024Source
  • 8 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Form 2 Sep 23.pdf · uploaded 5 Mar 2024Source
  • 9 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Form 2 Dec 23.pdf · uploaded 5 Mar 2024Source
  • 8 Disclosure of sold/ booked inventorySold Unsold 1.pdf · uploaded 5 Mar 2024Source
  • 9 Disclosure of sold/ booked inventorySold Unsold 2.pdf · uploaded 5 Mar 2024Source
  • 9 Certificates of CA (Form 3)Form 3 1.pdf · uploaded 5 Mar 2024Source
  • 10 Certificates of CA (Form 3)Form 3 1.pdf · uploaded 5 Mar 2024Source
  • 2 Copy of Layout Approval (in case of layout)MYSCAN_20220510_0004.PDF · uploaded 16 Aug 2024Source
  • 7 Building Plan Approval (IOD)MYSCAN_20220510_0003.PDF · uploaded 16 Aug 2024Source
  • 8 Building Plan Approval (IOD)MYSCAN_20220510_0004.PDF · uploaded 16 Aug 2024Source
  • 9 Building Plan Approval (IOD)MYSCAN_20220510_0005.PDF · uploaded 16 Aug 2024Source
  • 10 Building Plan Approval (IOD)MYSCAN_20220510_0006.PDF · uploaded 16 Aug 2024Source
  • 11 Building Plan Approval (IOD)MYSCAN_20220510_0007.PDF · uploaded 16 Aug 2024Source
  • 12 Building Plan Approval (IOD)MYSCAN_20220510_0008.PDF · uploaded 16 Aug 2024Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)Form 5.pdf · uploaded 22 Oct 2024Source

Technical

  • DocumentMYSCAN_20170428_0005.pdf · uploaded 29 Jul 2017Source
  • DocumentMYSCAN_20170428_0006.pdf · uploaded 29 Jul 2017Source
  • DocumentMYSCAN_20170428_0007.pdf · uploaded 29 Jul 2017Source
  • DocumentMYSCAN_20170428_0004.pdf · uploaded 29 Jul 2017Source
  • DocumentMYSCAN_20170428_0002.pdf · uploaded 29 Jul 2017Source
  • DocumentMYSCAN_20170428_0003.pdf · uploaded 29 Jul 2017Source
  • DocumentMYSCAN_20170428_0001.pdf · uploaded 29 Jul 2017Source
  • DocumentMYSCAN_20220510_0003.PDF · uploaded 16 Aug 2024Source
  • DocumentMYSCAN_20220510_0004.PDF · uploaded 16 Aug 2024Source
  • DocumentMYSCAN_20220510_0005.PDF · uploaded 16 Aug 2024Source
  • DocumentMYSCAN_20220510_0006.PDF · uploaded 16 Aug 2024Source
  • DocumentMYSCAN_20220510_0007.PDF · uploaded 16 Aug 2024Source
  • DocumentMYSCAN_20220510_0008.PDF · uploaded 16 Aug 2024Source
  • DocumentMYSCAN_20220510_0004.PDF · uploaded 16 Aug 2024Source

Technical (Architect)

  • DocumentForm 1 Dec 23.pdf · uploaded 5 Mar 2024Source

Technical (Engineer)

  • DocumentForm 2 Dec 23.pdf · uploaded 5 Mar 2024Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsLand parcel CTC 691 To 715 S N 5A H No 8

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
Unit types
1BHK, 2BHK, 3BHK, Office space, Shop270 units in all
Address
CTC 691 To 715 S N 5A H No 8, Netivali, Chakki NakaPIN 421306
Village
Kalyan-Dombivali (M Corp.), Kalyan taluka
Land area for this project
5,794 sq m (62,366 sq ft)
Permissible built-up area
11,140 sq m (1,19,910 sq ft)
Sanctioned built-up area
11,140 sq m (1,19,910 sq ft)
Recreational open space
732 sq m (7,878 sq ft)
Designated bank account
171
Developed in phases
No

Survey, CTS, gat or plot numbers

CTC 691 To 715 S N 5A H No 8

Land as published on MahaRERA's project page

CTC 691 To 715 S N 5A H No 8

Boundaries

North
Fulware and Other Chawl
South
Ulhasnagar Puna Link Road
East
Mauje Tisgaon Shiv
West
6 Mtr wide Road

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking270 units

256 of 270 units booked (95%), as the promoter reported to MahaRERA

1BHK · 124 units2BHK · 93 units3BHK · 12 unitsOffice space · 31 unitsShop · 10 units
TypeCarpet areaUnitsBooked
1BHK29.07 sq m · 313 sq ft7372
1BHK30.07 sq m · 324 sq ft1919
1BHK31.21 sq m · 336 sq ft3230
2BHK41.28 sq m · 444 sq ft4040
2BHK43.07 sq m · 464 sq ft21
2BHK44.44 sq m · 478 sq ft1919
2BHK45.81 sq m · 493 sq ft3231
3BHK57.46 sq m · 618 sq ft21
Show all 38 unit rowsShow fewer unit rows
TypeCarpet areaUnitsBooked
3BHK58.82 sq m · 633 sq ft108
Office space8.09 sq m · 87 sq ft10
Office space25.48 sq m · 274 sq ft21
Office space28.27 sq m · 304 sq ft11
Office space28.56 sq m · 307 sq ft11
Office space32.27 sq m · 347 sq ft11
Office space32.37 sq m · 348 sq ft22
Office space34.27 sq m · 369 sq ft55
Office space34.41 sq m · 370 sq ft21
Office space34.64 sq m · 373 sq ft22
Office space40.64 sq m · 437 sq ft11
Office space43.67 sq m · 470 sq ft21
Office space46.54 sq m · 501 sq ft22
Office space50.69 sq m · 546 sq ft11
Office space51.51 sq m · 554 sq ft11
Office space80.53 sq m · 867 sq ft11
Office space80.94 sq m · 871 sq ft11
Office space86.39 sq m · 930 sq ft11
Office space99.96 sq m · 1,076 sq ft11
Office space121.01 sq m · 1,303 sq ft11
Office space130.58 sq m · 1,406 sq ft10
Office space167.98 sq m · 1,808 sq ft10
Shop28.56 sq m · 307 sq ft11
Shop34.27 sq m · 369 sq ft11
Shop44.15 sq m · 475 sq ft11
Shop45.52 sq m · 490 sq ft11
Shop49.77 sq m · 536 sq ft11
Shop49.92 sq m · 537 sq ft22
Shop50.69 sq m · 546 sq ft11
Shop52.85 sq m · 569 sq ft22

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Other projects in Kalyan-Dombivali (M Corp.)

All 60 projects in Kalyan-Dombivali (M Corp.) · Compare Skylon with another project

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Report a problemMethodology