Completion was pushed back 4 months, to Apr 2029; no MahaRERA orders on record; 18% of its units are booked.

Juinagar, Thane 400705 · by Raheja Universal (Pvt.) Ltd

DeliveryExtended 4 moPromised Dec 2028 · now due Apr 2029RegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales18% booked5 of 28 units · as the promoter reported to MahaRERA

Buying a flat here?

See every deed registered on it.

Completion was pushed back 4 months, to Apr 2029

  • This projectRegistered 6 Aug 2025, completion promised 31 Dec 2028, revised to 30 Apr 2029.

No extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales first, then rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

2 buildings

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationPM1330002500505
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
PM13300025005056 Aug 202531 Dec 202830 Apr 2029Raheja Universal (Pvt.) Ltd.Project page
Documents48

1 document held by Deedo, 47 filings listed on MahaRERA's project page

Registration certificate

Finance

  • PAN CardPAN card.PDF · uploaded 16 Jul 2025Source

Legal

  • Declaration Form BTitle certificate (Synova).pdf · uploaded 16 Jul 2025Source
  • Declaration Form BSynova Form B.pdf · uploaded 16 Jul 2025Source
  • Declaration Form BDOA 05102006.pdf · uploaded 16 Jul 2025Source
  • OthersDisclosure of Interest (RSR).pdf · uploaded 28 Jul 2025Source
  • OthersDisclosure of Interest (ASR).pdf · uploaded 28 Jul 2025Source
  • OthersDisclosure of Interest (SLR).pdf · uploaded 28 Jul 2025Source
Show all 48 documentsShow fewer documents

Legal

  • OthersClarification .pdf · uploaded 28 Jul 2025Source
  • OthersIndenture of Lease bearing doc no 2867_1966.pdf · uploaded 28 Jul 2025Source
  • OthersSupplementarl Lease deed 134_1971.pdf · uploaded 28 Jul 2025Source
  • OthersK Raheja to RUPL name change.pdf · uploaded 28 Jul 2025Source
  • OthersDevelopment Agreement bearing doc no 8822_2004.pdf · uploaded 28 Jul 2025Source
  • OthersDeed of confiramtion doc no 2870_1996.pdf · uploaded 28 Jul 2025Source
  • OthersLetter dated 11112022_compressed.pdf · uploaded 28 Jul 2025Source
  • OthersDeed of Assignment bearing doc no 1731_23 part 1.pdf · uploaded 28 Jul 2025Source
  • OthersDeed of Assignment bearing doc no 1731_23 part 2.pdf · uploaded 28 Jul 2025Source
  • OthersATSL_Synova (Tesla-3)_Ms Raheja Universal (Pvt) Limited_25052026.pdf · uploaded 26 May 2026Source
  • OthersDeviation Report - Synova.pdf · uploaded 26 May 2026Source

Migrated

  • Withdrawal Update Form 1Form 1 Synova 30092025.pdf · uploaded 27 Nov 2025Source
  • Withdrawal Update Form 1Form 1 Synova 30092025.pdf · uploaded 27 Nov 2025Source
  • Withdrawal Update Form 2Form 2 Synova 30092025.pdf · uploaded 27 Nov 2025Source
  • Withdrawal Update Form 2Form 2 Synova 30092025.pdf · uploaded 27 Nov 2025Source
  • Withdrawal Update Form 3Synova Form 3.pdf · uploaded 27 Nov 2025Source
  • Withdrawal Update Form 3Form 3 Synova 300925.pdf · uploaded 27 Nov 2025Source
  • Withdrawal Update Form 1Form 1 Tesla 3 Synova 30 12 2025.pdf · uploaded 9 Feb 2026Source
  • Withdrawal Update Form 1Form 1 Tesla 3 Synova 30 12 2025.pdf · uploaded 9 Feb 2026Source
  • Withdrawal Update Form 2Form 2 Tesla 3 Synova 31122025 04022026.pdf · uploaded 9 Feb 2026Source
  • Withdrawal Update Form 2Form 2 Tesla 3 Synova 31122025 04022026.pdf · uploaded 9 Feb 2026Source
  • Withdrawal Update Form 3Form 3 Synova 300925.pdf · uploaded 9 Feb 2026Source
  • Withdrawal Update Form 3Form 3 Tesla 3 Synova 09022026.pdf · uploaded 9 Feb 2026Source
  • Withdrawal Update Form 1Form 1 - Tesla 3 (Synova).pdf · uploaded 15 May 2026Source
  • Withdrawal Update Form 1Form 1 - Tesla 3 (Synova).pdf · uploaded 15 May 2026Source
  • Withdrawal Update Form 2Tesla - III.pdf · uploaded 15 May 2026Source
  • Withdrawal Update Form 2Tesla - III.pdf · uploaded 15 May 2026Source
  • Withdrawal Update Form 3Form 3_Synova Tesla 3_31 03 2026.pdf · uploaded 15 May 2026Source
  • Withdrawal Update Form 3Form 3_Synova Tesla 3_31 03 2026.pdf · uploaded 15 May 2026Source
  • Form 2A (FY 2025-2026)Tesla Building 3.pdf · uploaded 18 Jun 2026Source
  • Withdrawal Update Form 1Form 1 Tesla 3 (Synova) dt 30 06 2026.pdf · uploaded 15 Jul 2026Source
  • Withdrawal Update Form 2Tesla 3 Synova 30 06 2026.pdf · uploaded 15 Jul 2026Source
  • Withdrawal Update Form 3Form 3_Synova Tesla 3_31 03 2026.pdf · uploaded 15 Jul 2026Source

Technical

  • DocumentSynova Building Plan.pdf · uploaded 16 Jul 2025Source
  • DocumentPlot area declaration Synova.pdf · uploaded 16 Jul 2025Source
  • DocumentSYNOVA LAYOUT PLAN (2).pdf · uploaded 16 Jul 2025Source
  • OthersEmail from SPA.pdf · uploaded 16 Jul 2025Source
  • OthersSynova CC Declaration.pdf · uploaded 16 Jul 2025Source

Technical (Architect)

  • DocumentForm 1 - Tesla 3 (Synova).pdf · uploaded 7 Oct 2026Source

Technical (Engineer)

  • DocumentForm 2 - Tesla 3.pdf · uploaded 9 Oct 2026Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsLand parcel Gen-2/1/C (Part-B)

As registered with MahaRERA and published on its project page

Project type
Mixed
Status on MahaRERA
Certificate Signed
Unit types
—28 units in all
Address
Gen-2/1/C (Part-B), JuinagarPIN 400705
Village
Navi Mumbai (M Corp.), Thane taluka
Land area for this project
1,100 sq m (11,840 sq ft)
Approved layout area
44,124 sq m (4,74,947 sq ft)
Permissible built-up area
1,46,628 sq m (15,78,291 sq ft)
Sanctioned built-up area
5,004 sq m (53,863 sq ft)
Recreational open space
0 sq m (0 sq ft)
Designated bank account
76
Developed in phases
No

Survey, CTS, gat or plot numbers

Gen-2/1/C (Part-B)

Land as published on MahaRERA's project page

Gen-2/1/C (Part-B)

Boundaries

North
Internal Road of Larger Layout
South
Internal Road of Larger Layout
East
Internal Road of Larger Layout
West
Internal Road of Larger Layout

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking28 units

28 units registered

— · 28 units
TypeCarpet areaUnits
——28

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals4

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectKamal Khemani—
Chartered accountantVinit Shah—
EngineerAvinash Shinde—
EngineerMahesh Lalla—

Source: MahaRERA project page. Contact details are not shown.

Other projects in Juinagar

All 4 projects in Juinagar · Compare Raheja Tesla-3 (Synova) with another project

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Report a problemMethodology