Ramdev Ritu Heights
Deedo IDDP-THN-PTRDIts promised completion date, Dec 2025, has passed and MahaRERA does not show it completed; no MahaRERA orders on record; 87% of its units are booked.
Ghodbunder, Thane 401107 · by Shree Ramdev Ritu Developers
Buying a flat here?
See every deed registered on it.
Its promised completion date, Dec 2025, has passed and MahaRERA does not show it completed
- This projectRegistered 15 Mar 2019, completion promised 30 Dec 2025, and still not shown completed today.
No extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales, rentals and mortgages matched to this project · the free view shows a price band
3 buildings
Open a building to see every flat, floor by floor.
- Building (P51700019982)Size not on record74% booked
- CommercialSize not on record0% booked
- Main building3 floors · 239 units87% booked
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationP51700019982
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P51700019982 | 15 Mar 2019 | 30 Dec 2025 | 30 Dec 2025 | M/s Shree Ramdev Ritu Developers | Project page |
Documents100
2 documents held by Deedo, 98 filings listed on MahaRERA's project page
Other
- OtherDate not statedView
Finance
Show all 100 documentsShow fewer documents
Migrated
- 1 PAN CardShree Ramdev Ritu Developers.pdf · uploaded 8 Mar 2019Source
- 2 PAN CardManoj Purohit.pdf · uploaded 8 Mar 2019Source
- 3 PAN CardRaju Bhati.pdf · uploaded 8 Mar 2019Source
- 1 Copy of the legal title reportTitle S No110.pdf · uploaded 8 Mar 2019Source
- 1 Details of encumbrancesNo Encumbrance Certificate.pdf · uploaded 8 Mar 2019Source
- 1 Copy of Layout Approval (in case of layout)LAYOUT PLAN.pdf · uploaded 8 Mar 2019Source
- 1 Building Plan Approval (IOD)1ST FLOOR BUILDING PLAN.pdf · uploaded 8 Mar 2019Source
- 2 Building Plan Approval (IOD)2ND FLOOR BUILDING PLAN.pdf · uploaded 8 Mar 2019Source
- 3 Building Plan Approval (IOD)5 AND 9 FLOOR BUILDING PLAN.pdf · uploaded 8 Mar 2019Source
- 4 Building Plan Approval (IOD)11TH FLOOR BUILDING PLAN.pdf · uploaded 8 Mar 2019Source
- 5 Building Plan Approval (IOD)GROUND FLOOR BUILDING PLAN.pdf · uploaded 8 Mar 2019Source
- 1 Commencement Certificates / NA Order for plotted developmentCommencement Certificate.pdf · uploaded 8 Mar 2019Source
- 1 Declaration in FORM BAffidavit - Form B.pdf · uploaded 8 Mar 2019Source
- 1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Architect Certificate Form 1.pdf · uploaded 8 Mar 2019Source
- 1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Engineer certificate Form 2.pdf · uploaded 8 Mar 2019Source
- 1 Certificates of CA (Form 3)CA Certificate.pdf · uploaded 8 Mar 2019Source
- 2 Certificates of CA (Form 3)Annexure A.pdf · uploaded 8 Mar 2019Source
- 1 Proforma of Allotment letterAllotment Letter.pdf · uploaded 8 Mar 2019Source
- 2 Commencement Certificates / NA Order for plotted developmentNew CC.pdf · uploaded 31 Dec 2019Source
- 2 Certificates of Architect (Form 1)(Mandatory for only ongoing project)FORM 1 Architect Certificate AS PER NEW CC.pdf · uploaded 28 Dec 2020Source
- 2 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Form 2 Engineer Certificate as per new CC.pdf · uploaded 28 Dec 2020Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)Form 2A.pdf · uploaded 28 Dec 2020Source
- 3 Certificates of CA (Form 3)FORM 3 ANNEXURE-A.pdf · uploaded 30 Dec 2020Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)form 5.pdf · uploaded 30 Dec 2020Source
- 6 Building Plan Approval (IOD)BLDG NO1 FLOOR GR and TERRACE 1 2.pdf · uploaded 28 Jan 2021Source
- 7 Building Plan Approval (IOD)BLDG NO2 FLOOR GR AND 1.pdf · uploaded 28 Jan 2021Source
- 8 Building Plan Approval (IOD)BLDG NO 2 FLOOR 2 AND 3.pdf · uploaded 28 Jan 2021Source
- 9 Building Plan Approval (IOD)BLDG NO 2 FLOOR 4 TO 6 AND 8 TO 10 TO 11 AND 13.pdf · uploaded 28 Jan 2021Source
- 10 Building Plan Approval (IOD)BLDG NO 2 FLOOR 7 AND 12 AND 14.pdf · uploaded 28 Jan 2021Source
- 11 Building Plan Approval (IOD)BLDG NO3 FLOOR GR TERRACE 1 AND 2.pdf · uploaded 28 Jan 2021Source
- 4 Certificates of CA (Form 3)Quarterly Form 3.pdf · uploaded 9 Oct 2021Source
- 3 Commencement Certificates / NA Order for plotted developmentNEW CC - 25112021_compressed.pdf · uploaded 2 Feb 2022Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)Form-5.pdf · uploaded 7 Feb 2022Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)17042023164556.pdf · uploaded 29 Apr 2023Source
- 3 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Form 1 Bldg 1 2 3 4 30062023.pdf · uploaded 4 Aug 2023Source
- 4 Certificates of Architect (Form 1)(Mandatory for only ongoing project)SHREE RAMDEV RITU DEV-fORM 3_compressed.pdf · uploaded 4 Aug 2023Source
- 5 Certificates of Architect (Form 1)(Mandatory for only ongoing project)MANOJ M PUROHIT-fORM 1_compressed.pdf · uploaded 4 Aug 2023Source
- 3 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Form 2 Bldg 1 2 3 4 30062023.pdf · uploaded 4 Aug 2023Source
- 5 Certificates of CA (Form 3)SHREE RAMDEV RITU DEV-fORM 3_compressed.pdf · uploaded 4 Aug 2023Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)2020-2021 Enginner certificate_0001.pdf · uploaded 21 Aug 2023Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)2021-2022 Enginner certificate_0001.pdf · uploaded 21 Aug 2023Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)2022-2023 Enginner certificate_0001.pdf · uploaded 21 Aug 2023Source
- 6 Certificates of CA (Form 3)SHREE RAMDEV RITU DEV -FORM 3-1 TO 4.pdf · uploaded 21 Aug 2023Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)SHREE RAMDEV RITU DEV FROM NO 5-BLDG 1 TO 4-22-23.pdf · uploaded 21 Aug 2023Source
- 6 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Form 1.pdf · uploaded 16 Oct 2023Source
- 4 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Form 2 Bldg 1234 30092023.pdf · uploaded 16 Oct 2023Source
- 7 Certificates of CA (Form 3)Form-3 9982 (16-10-2023).pdf · uploaded 16 Oct 2023Source
- 7 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Ritu Heights-1-4-form 1.pdf · uploaded 19 Jan 2024Source
- 5 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Ritu Heights-1-4-form 2.pdf · uploaded 19 Jan 2024Source
- 8 Certificates of CA (Form 3)Form 3 Bldg.pdf · uploaded 19 Jan 2024Source
- 8 Certificates of Architect (Form 1)(Mandatory for only ongoing project)FORM 1-1-4.pdf · uploaded 29 Apr 2024Source
- 6 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)FORM 2-1-4.pdf · uploaded 29 Apr 2024Source
- 9 Certificates of CA (Form 3)FORM 3-1-4_compressed.pdf · uploaded 29 Apr 2024Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)FORM 5.pdf · uploaded 2 May 2024Source
- 2 Declaration in FORM BHdfc Rera Acc Confirmation.pdf · uploaded 16 Jul 2024Source
- 9 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Form 1_0001.pdf · uploaded 16 Jul 2024Source
- 10 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Form 1_0001.pdf · uploaded 16 Jul 2024Source
- 7 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Form 2_0001.pdf · uploaded 16 Jul 2024Source
- 8 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Form 2_0001.pdf · uploaded 16 Jul 2024Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)QA.pdf · uploaded 16 Jul 2024Source
- 2 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)QA certificate_0001.pdf · uploaded 16 Jul 2024Source
- 10 Certificates of CA (Form 3)form3.pdf · uploaded 16 Jul 2024Source
- 11 Certificates of CA (Form 3)Form 3_compressed (1).pdf · uploaded 16 Jul 2024Source
- 1 Declaration about all RERA Designated Bank Accounts (Format A)Builder Rera Acc Confirmation.pdf · uploaded 16 Jul 2024Source
- 2 Declaration about all RERA Designated Bank Accounts (Format A)Builder Rera Acc Confirmation.pdf · uploaded 16 Jul 2024Source
- 1 Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)IndusInd Rera Acc Confirmation.pdf · uploaded 16 Jul 2024Source
- 2 Certificates of Architect (Form 1)(Mandatory for only ongoing project)FORM 1_0001.pdf · uploaded 11 Nov 2024Source
- 3 Certificates of CA (Form 3)FORM 3_0001_compressed.pdf · uploaded 11 Nov 2024Source
- 2 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)FORM 2_0001.pdf · uploaded 11 Nov 2024Source
- 1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)FORM 1_0001.pdf · uploaded 21 Jan 2025Source
- 1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)FORM 2_0001.pdf · uploaded 21 Jan 2025Source
- 1 Disclosure of sold/ booked inventorySOLD UNSOLD_0001.pdf · uploaded 21 Jan 2025View
- 1 Certificates of CA (Form 3)FORM 3_0001-1.pdf · uploaded 23 Jan 2025Source
- 2 Certificates of CA (Form 3)FORM 3_0001_compressed.pdf · uploaded 23 Jan 2025Source
Technical
- Document1ST FLOOR BUILDING PLAN.pdf · uploaded 8 Mar 2019Source
- Document2ND FLOOR BUILDING PLAN.pdf · uploaded 8 Mar 2019Source
- Document5 AND 9 FLOOR BUILDING PLAN.pdf · uploaded 8 Mar 2019Source
- Document11TH FLOOR BUILDING PLAN.pdf · uploaded 8 Mar 2019Source
- DocumentGROUND FLOOR BUILDING PLAN.pdf · uploaded 8 Mar 2019Source
- DocumentLAYOUT PLAN.pdf · uploaded 8 Mar 2019Source
- DocumentBLDG NO2 FLOOR GR AND 1.pdf · uploaded 28 Jan 2021Source
- DocumentBLDG NO 2 FLOOR 2 AND 3.pdf · uploaded 28 Jan 2021Source
- DocumentBLDG NO 2 FLOOR 4 TO 6 AND 8 TO 10 TO 11 AND 13.pdf · uploaded 28 Jan 2021Source
- DocumentBLDG NO 2 FLOOR 7 AND 12 AND 14.pdf · uploaded 28 Jan 2021Source
- DocumentBLDG NO3 FLOOR GR TERRACE 1 AND 2.pdf · uploaded 28 Jan 2021Source
- DocumentBLDG NO1 FLOOR GR and TERRACE 1 2.pdf · uploaded 28 Jan 2021Source
Technical (Architect)
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvalsLand parcel 110/2
As registered with MahaRERA and published on its project page
- Project type
- Others
- Status on MahaRERA
- Certificate Signed
- Unit types
- 1BHK, 1 shop, 1st floor commercial, 2BHK, 2nd commercialunit 1, 3rd commercial unit1, 3rd floor commercial, 4 office, Ground floor commerc, Office, Office space, Shop239 units in all
- Address
- 110/2, 60 Feet Road, Behind Western Hotel, GhodbundarPIN 401107
- Village
- Mira-Bhayandar (M Corp.), Thane taluka
- Land area for this project
- 3,374 sq m (36,317 sq ft)
- Permissible built-up area
- 7,147 sq m (76,933 sq ft)
- Sanctioned built-up area
- 5,739 sq m (61,777 sq ft)
- Recreational open space
- 676 sq m (7,273 sq ft)
- Designated bank account
- 88
- Developed in phases
- Yes
Survey, CTS, gat or plot numbers
Land as published on MahaRERA's project page
110/2
Boundaries
- North
- Survey No 25 and 18 mtr DP Road
- South
- Survey No 109
- East
- Survey No 111 and 18 mtr DP Road
- West
- Survey No 224 and 18 mtr DP Road
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking239 units
207 of 239 units booked (87%), as the promoter reported to MahaRERA
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 1BHK | 32.89 sq m · 354 sq ft | 60 | 58 |
| 1BHK | 34.72 sq m · 374 sq ft | 26 | 24 |
| 1BHK | 37.33 sq m · 402 sq ft | 63 | 62 |
| 1 shop | 131.54 sq m · 1,416 sq ft | 1 | 0 |
| 1st floor commercial | 99.72 sq m · 1,073 sq ft | 1 | 0 |
| 2BHK | 49.15 sq m · 529 sq ft | 24 | 24 |
| 2BHK | 52.36 sq m · 564 sq ft | 18 | 18 |
| 2nd commercialunit 1 | 194.13 sq m · 2,090 sq ft | 1 | 0 |
Show all 34 unit rowsShow fewer unit rows
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 3rd commercial unit1 | 194.13 sq m · 2,090 sq ft | 1 | 0 |
| 3rd floor commercial | 139.41 sq m · 1,501 sq ft | 1 | 0 |
| 4 office | 254.32 sq m · 2,737 sq ft | 4 | 0 |
| Ground floor commerc | 178.54 sq m · 1,922 sq ft | 1 | 0 |
| Office | 225.18 sq m · 2,424 sq ft | 4 | 0 |
| Office | 349.1 sq m · 3,758 sq ft | 4 | 0 |
| Office space | 13.55 sq m · 146 sq ft | 1 | 1 |
| Office space | 18.95 sq m · 204 sq ft | 1 | 1 |
| Office space | 23.04 sq m · 248 sq ft | 1 | 0 |
| Office space | 23.05 sq m · 248 sq ft | 1 | 0 |
| Office space | 28.95 sq m · 312 sq ft | 1 | 1 |
| Office space | 30.15 sq m · 325 sq ft | 2 | 0 |
| Office space | 30.64 sq m · 330 sq ft | 1 | 1 |
| Office space | 31.9 sq m · 343 sq ft | 1 | 1 |
| Office space | 40.85 sq m · 440 sq ft | 1 | 0 |
| Shop | 14.55 sq m · 157 sq ft | 3 | 1 |
| Shop | 14.68 sq m · 158 sq ft | 2 | 2 |
| Shop | 14.75 sq m · 159 sq ft | 1 | 1 |
| Shop | 15.91 sq m · 171 sq ft | 2 | 2 |
| Shop | 18.04 sq m · 194 sq ft | 3 | 3 |
| Shop | 18.04 sq m · 194 sq ft | 3 | 3 |
| Shop | 18.45 sq m · 199 sq ft | 1 | 1 |
| Shop | 18.79 sq m · 202 sq ft | 1 | 1 |
| Shop | 19.82 sq m · 213 sq ft | 2 | 2 |
| Shop | 149.27 sq m · 1,607 sq ft | 1 | 0 |
| Shop | 178.55 sq m · 1,922 sq ft | 1 | 0 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Professionals1
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Tej's' Consultants | — |
Source: MahaRERA project page. Contact details are not shown.