Promised date passed16 floorsRERA P51700007988

Building B, Apna Ghar

Deedo IDDP-THN-MC8E-B

MahaRERA has not published a flat-by-flat record for this tower, and no registered deed names it yet.

All of Apna Ghar
Median saleNot on recordneeds 3 or more sales
Booked89%209 of 236 · MahaRERA
Completion30 Jun 2022as registered
Units & parking in Building B
TypeCarpet areaUnitsBooked
1 BHK6,350.8 m² (68,359 sq.ft)236209
As registered with MahaRERA
RERA registration
P51700007988 · registered 18 Aug 2017
Promised completion
30 Jun 2022
Revised completion
30 Jun 2022
Sanctioned habitable floors
16
Sanctioned floors (incl. basement, stilt, podium)
16
Units declared
0
Homes
0
Shops and offices
0
MahaRERA status
Certificate Signed
Deedo ID
DP-THN-MC8E-B
Questions about Building B

When is Building B due for completion?

The MahaRERA registration promises 30 Jun 2022.

How many floors does Building B have?

16 sanctioned habitable floors, as registered with MahaRERA.