Sai Amrut
Deedo IDDP-THN-7CT8It is due for completion in Oct 2027, with no extension on record; no MahaRERA orders on record; 0% of its units are booked.
Done, Thane 421503 · by Pravin Suresh Bamne
Buying a flat here?
See every deed registered on it.
It is due for completion in Oct 2027, with no extension on record
- This projectRegistered 1 Jun 2023, completion promised 31 Oct 2027.
No extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales, rentals and mortgages matched to this project · the free view shows a price band
The building
Open a building to see every flat, floor by floor.
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationP51700051157
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P51700051157 | 1 Jun 2023 | 31 Oct 2027 | 31 Oct 2027 | Pravin Suresh Bamne | Project page |
Documents51
1 document held by Deedo, 50 filings listed on MahaRERA's project page
Finance
- PAN CardPan Card Praveen Bamne.pdf · uploaded 22 Apr 2023Source
Legal
- Other – LegalPurchase deed 1to30.pdf · uploaded 22 Apr 2023Source
- Other – LegalPurchase deed 31to60.pdf · uploaded 22 Apr 2023Source
- Other – LegalPurchase deed 61to90.pdf · uploaded 22 Apr 2023Source
- Other – LegalPurchase deed 91to122.pdf · uploaded 22 Apr 2023Source
- Legal Title reportLegal Tital Report.pdf · uploaded 22 Apr 2023Source
- Declaration Form BForm B.pdf · uploaded 22 Apr 2023Source
Show all 51 documentsShow fewer documents
Migrated
- 1 PAN CardPan Card Praveen Bamne.pdf · uploaded 22 Apr 2023Source
- 1 Copy of the legal title reportLegal Tital Report.pdf · uploaded 22 Apr 2023Source
- 1 a Details of encumbrances concerned to FinanceNo Encumbrance.pdf · uploaded 22 Apr 2023Source
- 1 b Details of encumbrances concerned to LegalNo Encumbrance.pdf · uploaded 22 Apr 2023Source
- 1 Copy of Layout Approval (in case of layout)Layout Plans 1.pdf · uploaded 22 Apr 2023Source
- 1 Building Plan Approval / NA Order for plotted developmentLayout Plans.pdf · uploaded 22 Apr 2023Source
- 1 Commencement Certificates / NA Order for plotted developmentCC.pdf · uploaded 22 Apr 2023Source
- 1 Declaration about Commencement CertificateCC Formet D.pdf · uploaded 22 Apr 2023Source
- 1 Declaration in FORM BForm B.pdf · uploaded 22 Apr 2023Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 Architech.pdf · uploaded 22 Apr 2023Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Engineer.pdf · uploaded 22 Apr 2023Source
- 1 CERSAI detailsCERSAI Certificate.pdf · uploaded 22 Apr 2023Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 CA.pdf · uploaded 22 Apr 2023Source
- 1 Proforma of Agreement for saleProforma Agreement for sale .pdf · uploaded 22 Apr 2023Source
- 1 Proforma of Allotment letterProforma Allotmenet letter.pdf · uploaded 22 Apr 2023Source
- 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameBank account declaration.pdf · uploaded 22 Apr 2023Source
- 1 Deviation Report with respect to Allotment letterDeviation Report Allotment Letter.pdf · uploaded 22 Apr 2023Source
- 1 Deviation Report with respect to model copy of AgreementDeviation Report Agreement Sale.pdf · uploaded 22 Apr 2023Source
- 1 Other – LegalPurchase deed 1to30.pdf · uploaded 22 Apr 2023Source
- 2 Other – LegalPurchase deed 31to60.pdf · uploaded 22 Apr 2023Source
- 3 Other – LegalPurchase deed 61to90.pdf · uploaded 22 Apr 2023Source
- 4 Other – LegalPurchase deed 91to122.pdf · uploaded 22 Apr 2023Source
- 1 Disclosure of Interest in Other Real Estate OrganizationsDisclosure of Interest in Other Real Estate Organizations.pdf · uploaded 24 Apr 2023Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 Architect.pdf · uploaded 27 Oct 2023Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2.pdf · uploaded 27 Oct 2023Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form-3 CA Om sai enterprises.pdf · uploaded 27 Oct 2023Source
- Withdrawal Update Form 1Form 1 Pravin June 25.pdf · uploaded 21 Mar 2026Source
- Withdrawal Update Form 1Form 1 Pravin Sep 25.pdf · uploaded 21 Mar 2026Source
- Withdrawal Update Form 1Form 1 Pravin Dec 25.pdf · uploaded 21 Mar 2026Source
- Withdrawal Update Form 2Form 2 PRavin June 25.pdf · uploaded 21 Mar 2026Source
- Withdrawal Update Form 2Form 2 Pravin Sep 25.pdf · uploaded 21 Mar 2026Source
- Withdrawal Update Form 2Form 2 Pravin Dec 25.pdf · uploaded 21 Mar 2026Source
- Withdrawal Update Form 3Form 3 Pravin June 25.pdf · uploaded 21 Mar 2026Source
- Withdrawal Update Form 3Form 3 Pravin Sep 25.pdf · uploaded 21 Mar 2026Source
- Withdrawal Update Form 3Form 3 Pravin Dec 25.pdf · uploaded 21 Mar 2026Source
- Form 2A (FY 2023-2024)Form 2a 2.pdf · uploaded 8 Apr 2026Source
- Form 2A (FY 2024-2025)Form 2a 3.pdf · uploaded 8 Apr 2026Source
- Form 5 (FY 2023-2024)Form 5 2024 -sa.pdf · uploaded 8 Apr 2026Source
- Form 5 (FY 2024-2025)Form 5 2025 -sa.pdf · uploaded 8 Apr 2026Source
Technical
Technical (Architect)
- DocumentForm 1 Pravin Dec 25.pdf · uploaded 21 Mar 2026Source
Technical (Engineer)
- DocumentForm 2 Pravin Dec 25.pdf · uploaded 21 Mar 2026Source
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvalsLand parcel S NO 2 HISSA NO 5 E PLOT NO 3
As registered with MahaRERA and published on its project page
- Project type
- Residential / Group Housing
- Status on MahaRERA
- Certificate Signed
- Unit types
- 1BHK, 1RK, 2BHK12 units in all
- Address
- S No 2 Hissa No 5 E Plot No 3, Village Done, VanganiPIN 421503
- Village
- Done, Ambarnath taluka
- Location
- 19.08688, 73.31513
- Land area for this project
- 279 sq m (3,003 sq ft)
- Permissible built-up area
- 547 sq m (5,886 sq ft)
- Sanctioned built-up area
- 547 sq m (5,886 sq ft)
- Designated bank account
- 203
- Developed in phases
- No
Survey, CTS, gat or plot numbers
Land as published on MahaRERA's project page
S NO 2 HISSA NO 5 E PLOT NO 3
Boundaries
- North
- Twelve Meter Road
- South
- S No 2 Hissa No 5 E Plot No 2
- East
- S No 2 Hissa No 5 E Plot No 6
- West
- S No 2 Hissa No 5
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking12 units
0 of 12 units booked (0%), as the promoter reported to MahaRERA
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 1BHK | 33 sq m · 355 sq ft | 6 | 0 |
| 1BHK | 36.78 sq m · 396 sq ft | 4 | 0 |
| 1RK | 24.05 sq m · 259 sq ft | 1 | 0 |
| 2BHK | 48.67 sq m · 524 sq ft | 1 | 0 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Professionals5
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | M SQUARE ARCHITECTS Mukesh More | — |
| Chartered accountant | Chandrant Valku Bhoir | — |
| Chartered accountant | Kranti Chandrakant Bhoir | — |
| Chartered accountant | Kritarth R Patel And Associates | — |
| Engineer | ATULKUDTARKAR AND ASSOCIATES PVT LTD Atul Kudtarkar | — |
Source: MahaRERA project page. Contact details are not shown.