Skip to content
Others · 1 building · 53 unitsRERA P51700077696

Vivaan Heights

Deedo IDDP-THN-XQSX

Completion was pushed back 4 months, to Apr 2030; no MahaRERA orders on record; 9% of its units are booked.

Dombivli, Thane 421201 · by Shree Enterprises

DeliveryExtended 4 moPromised Dec 2029 · now due Apr 2030RegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales9% booked5 of 53 units · as the promoter reported to MahaRERA

Buying a flat here?

See every deed registered on it.

Completion was pushed back 4 months, to Apr 2030

  • This projectRegistered 21 Oct 2024, completion promised 31 Dec 2029, revised to 30 Apr 2030.

No extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales, rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

The building

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP51700077696
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5170007769621 Oct 202431 Dec 202930 Apr 2030Shree EnterprisesProject page
Documents83

1 document held by Deedo, 82 filings listed on MahaRERA's project page

Registration certificate

Finance

  • Other – FinanceAuthorized signatory letter.pdf · uploaded 6 Oct 2024Source
  • Other – FinanceDeclaration Rearding not selling.pdf · uploaded 6 Oct 2024Source
  • PAN CardCompany Pancard.pdf · uploaded 6 Oct 2024Source

Legal

  • Other – Legalकांचनगाव_84_14_Satbara.pdf · uploaded 6 Oct 2024Source
  • Other – Legalshree enterprise partnership deed Latest_11zon.pdf · uploaded 6 Oct 2024Source
  • Other – LegalAuthorized signatory letter.pdf · uploaded 6 Oct 2024Source
  • Legal Title reportTitle Report 16-10-2024.pdf · uploaded 6 Oct 2024Source
Show all 83 documentsShow fewer documents

Legal

  • Declaration Form BForm B Developer Shree Enterprises.pdf · uploaded 6 Oct 2024Source

Migrated

  • 1 PAN CardCompany Pancard.pdf · uploaded 6 Oct 2024Source
  • 1 Copy of the legal title reportTitle Report 16-10-2024.pdf · uploaded 6 Oct 2024Source
  • 1 a Details of encumbrances concerned to FinanceEncumbrance Finance.pdf · uploaded 6 Oct 2024Source
  • 2 a Details of encumbrances concerned to FinanceEncumbrance legal.pdf · uploaded 6 Oct 2024Source
  • 1 Copy of Layout Approval (in case of layout)Plan 1 Layout.pdf · uploaded 6 Oct 2024Source
  • 1 Proforma of Allotment letterAllotment Letter for Vivaan Heights.pdf · uploaded 6 Oct 2024Source
  • 1 Declaration in FORM BForm B Developer Shree Enterprises.pdf · uploaded 6 Oct 2024Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.pdf · uploaded 6 Oct 2024Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2.pdf · uploaded 6 Oct 2024Source
  • 1 Commencement Certificates / NA Order for plotted developmentKanchangaon CC 2462024.pdf · uploaded 6 Oct 2024Source
  • 1 Building Plan Approval / NA Order for plotted developmentPlan 1 Layout.pdf · uploaded 6 Oct 2024Source
  • 2 Building Plan Approval / NA Order for plotted developmentPlan 2 Building Plan.pdf · uploaded 6 Oct 2024Source
  • 3 Building Plan Approval / NA Order for plotted developmentPlan 3 Building plan.pdf · uploaded 6 Oct 2024Source
  • 1 Other – LegalAuthorized signatory letter.pdf · uploaded 6 Oct 2024Source
  • 2 Other – Legalshree enterprise partnership deed Latest_11zon.pdf · uploaded 6 Oct 2024Source
  • 3 Other – Legalकांचनगाव_84_14_Satbara.pdf · uploaded 6 Oct 2024Source
  • 1 Declaration about Commencement CertificateFormat D.pdf · uploaded 6 Oct 2024Source
  • 1 CERSAI detailsCERSAI.pdf · uploaded 6 Oct 2024Source
  • 1 Declaration about all RERA Designated Bank Accounts (Format A)Format A latest.pdf · uploaded 6 Oct 2024Source
  • 1 Deviation Report with respect to Allotment letterDeviation Allotment.pdf · uploaded 6 Oct 2024Source
  • 1 b Details of encumbrances concerned to LegalEncumbrance Finance.pdf · uploaded 6 Oct 2024Source
  • 2 b Details of encumbrances concerned to LegalEncumbrance legal.pdf · uploaded 6 Oct 2024Source
  • 1 Other – FinanceDeclaration Rearding not selling.pdf · uploaded 6 Oct 2024Source
  • 2 Other – FinanceAuthorized signatory letter.pdf · uploaded 6 Oct 2024Source
  • 1 Other – TechnicalAnnexure A Order 50.pdf · uploaded 6 Oct 2024Source
  • 2 Other – TechnicalAuthorized signatory letter.pdf · uploaded 6 Oct 2024Source
  • 1 Deviation Report with respect to model copy of AgreementDeviation AFS.pdf · uploaded 6 Oct 2024Source
  • 1 Proforma of Agreement for saleAgreement for Sale Vivaan Heights.pdf · uploaded 6 Oct 2024Source
  • 1 Disclosure of Interest in Other Real Estate OrganizationsDIN Anil.pdf · uploaded 6 Oct 2024Source
  • 9 Disclosure of Interest in Other Real Estate OrganizationsDIN Vinit.pdf · uploaded 6 Oct 2024Source
  • 8 Disclosure of Interest in Other Real Estate OrganizationsDIN Vaish.pdf · uploaded 6 Oct 2024Source
  • 7 Disclosure of Interest in Other Real Estate OrganizationsDIN Sushant.pdf · uploaded 6 Oct 2024Source
  • 6 Disclosure of Interest in Other Real Estate OrganizationsDIN Siddesh.pdf · uploaded 6 Oct 2024Source
  • 5 Disclosure of Interest in Other Real Estate OrganizationsDIN Kavita.pdf · uploaded 6 Oct 2024Source
  • 4 Disclosure of Interest in Other Real Estate OrganizationsDIN Jaya.pdf · uploaded 6 Oct 2024Source
  • 3 Disclosure of Interest in Other Real Estate OrganizationsDIN Avinash.pdf · uploaded 6 Oct 2024Source
  • 2 Disclosure of Interest in Other Real Estate OrganizationsDIN Ankesh.pdf · uploaded 6 Oct 2024Source
  • 1 Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)Format B Latest 1.pdf · uploaded 6 Oct 2024Source
  • 1 Disclosure for secured/unsecured finance availed for the projectDisclosure of Secrured and unsecured.pdf · uploaded 6 Oct 2024Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 Final organized.pdf · uploaded 7 Oct 2024Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 SHREE ENTERPRISES REVISED.pdf · uploaded 6 Mar 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3 SHREE ENTERPRISES.pdf · uploaded 6 Mar 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 SHREE ENTERPRISES.pdf · uploaded 13 Mar 2025Source
  • Form 1FORM 1 SHREE ENTERPRISES MARCH 2025.pdf · uploaded 22 Jul 2025Source
  • Form 2FORM 2 SHREE ENTERPRISES MARCH 2025.pdf · uploaded 22 Jul 2025Source
  • Form 3FORM 3 SHREE ENTERPRISES MARCH 2025.pdf · uploaded 22 Jul 2025Source
  • Disclosure of Sold and Booked InventoryDisclosure of Sold Booked Inventory - March 2025.pdf · uploaded 22 Jul 2025Source
  • Form 1Form 01.pdf · uploaded 22 Jul 2025Source
  • Form 2Form 02.pdf · uploaded 22 Jul 2025Source
  • Form 3Form 03.pdf · uploaded 22 Jul 2025Source
  • Disclosure of Sold and Booked InventoryDisclosure of Sold Booked Inventory.pdf · uploaded 22 Jul 2025Source
  • Withdrawal Update Form 1FORM 1 SHREE ENTERPRISES JUNE 25.pdf · uploaded 22 Jul 2025Source
  • Withdrawal Update Form 2FORM 2 SHREE ENTERPRISES JUNE 25.pdf · uploaded 22 Jul 2025Source
  • Withdrawal Update Form 3FORM 3 SHREE ENTERPRISES JUNE 25.pdf · uploaded 22 Jul 2025Source
  • Withdrawal Update Form 1Form-1.pdf · uploaded 25 Oct 2025Source
  • Withdrawal Update Form 2Form-2.pdf · uploaded 25 Oct 2025Source
  • Withdrawal Update Form 3Form 3_Sep 25.pdf · uploaded 25 Oct 2025Source
  • Withdrawal Update Form 1Form 1 Dec 25.pdf · uploaded 20 Jan 2026Source
  • Withdrawal Update Form 2Form 2 Dec 25.pdf · uploaded 20 Jan 2026Source
  • Withdrawal Update Form 3Form-3 Dec 25.pdf · uploaded 20 Jan 2026Source
  • Withdrawal Update Form 1Form 1_March 26.pdf · uploaded 25 Apr 2026Source
  • Withdrawal Update Form 2Form 2_March 26.pdf · uploaded 25 Apr 2026Source
  • Withdrawal Update Form 3Form 3_March 26.pdf · uploaded 25 Apr 2026Source
  • Withdrawal Update Form 1Form 1_Jun 26.pdf · uploaded 23 Jul 2026Source
  • Withdrawal Update Form 2Form 2_Jun 26.pdf · uploaded 23 Jul 2026Source
  • Withdrawal Update Form 3Form 3_Jun 26.pdf · uploaded 23 Jul 2026Source

Technical

  • DocumentPlan 3 Building plan.pdf · uploaded 6 Oct 2024Source
  • DocumentPlan 2 Building Plan.pdf · uploaded 6 Oct 2024Source
  • DocumentPlan 1 Layout.pdf · uploaded 6 Oct 2024Source
  • DocumentPlan 1 Layout.pdf · uploaded 6 Oct 2024Source
  • Other – TechnicalAuthorized signatory letter.pdf · uploaded 6 Oct 2024Source
  • Other – TechnicalAnnexure A Order 50.pdf · uploaded 6 Oct 2024Source

Technical (Architect)

  • DocumentFORM 1 SHREE ENTERPRISES REVISED.pdf · uploaded 6 Mar 2025Source
  • DocumentForm 1_Jun 26.pdf · uploaded 23 Jul 2026Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsLand parcel Hissa No 14, Survey No 84

As registered with MahaRERA and published on its project page

Project type
Others
Status on MahaRERA
Certificate Signed
Unit types
—53 units in all
Address
Survey No 84, Hissa No 14, Kalyan Road, Kanchangaon, Dombivali EastPIN 421201
Village
Dombivli, Kalyan taluka
Land area for this project
1,400 sq m (15,069 sq ft)
Permissible built-up area
2,545 sq m (27,394 sq ft)
Sanctioned built-up area
2,545 sq m (27,394 sq ft)
Recreational open space
0 sq m (0 sq ft)
Developed in phases
No

Survey, CTS, gat or plot numbers

Hissa No 14Survey No 84

Land as published on MahaRERA's project page

Survey No 84, Hissa No 14

Boundaries

North
Plot
South
15 Wide KDMC DP Road
East
Plot
West
24 Wide KDMC DP Road

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking53 units

53 units registered

— · 53 units
TypeCarpet areaUnits
——53

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals5

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectDilip Deshmukh and Associates—
Chartered accountantDhiraj Sudhir Waghmare & CO—
Chartered accountantPooja Prasad Sawant And Company—
Chartered accountantSiddhi Sanjay Mane—
EngineerShravani Consultants—

Source: MahaRERA project page. Contact details are not shown.

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Report a problemMethodology