Deedo IDDP-THN-GPG7MahaRERA shows it completed; no MahaRERA orders on record; 91% of its units are booked.
Dombivli, Thane 421202 · by Aditya Buildcon · 67% of its projects kept the RERA date
Buying a flat here?
See every deed registered on it.
MahaRERA shows it completed
- This projectRegistered 14 Jan 2022, completion promised 31 Dec 2024.
No extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales, rentals and mortgages matched to this project · the free view shows a price band
The building
Open a building to see every flat, floor by floor.
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationP51700032599
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P51700032599 | 14 Jan 2022 | 31 Dec 2024 | 31 Dec 2024 | Aditya Buildcon | Project page |
Documents55
1 document held by Deedo, 54 filings listed on MahaRERA's project page
Legal
Migrated
- 1 Declaration in FORM BForm B declaration -1.pdf · uploaded 24 Nov 2021Source
- 1 Proforma of Allotment letterSamruddhi Society-Rera Flat.pdf · uploaded 24 Nov 2021Source
- 1 Copy of Layout Approval (in case of layout)Layout.pdf · uploaded 8 Dec 2021Source
- 1 Commencement Certificates / NA Order for plotted developmentCOMMENCEMENT CERTIFICATE.pdf · uploaded 8 Dec 2021Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)ARCHITECT CERTIFICATE OF SAMRUDHI chs.pdf · uploaded 8 Dec 2021Source
Show all 55 documentsShow fewer documents
Migrated
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)ENGINEER'S CERTIFICATE OF SAMRUDHI chs.pdf · uploaded 8 Dec 2021Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA Certificate.pdf · uploaded 8 Dec 2021Source
- 1 PAN CardPAN.pdf · uploaded 9 Dec 2021Source
- 1 Building Plan Approval / NA Order for plotted developmentPlan Layout_.pdf · uploaded 9 Dec 2021Source
- 1 Details of encumbrancesLETTER.pdf · uploaded 27 Dec 2021Source
- 1 Copy of the legal title reportTitle certificate of Samrudhi chs.pdf · uploaded 8 Jan 2022Source
- 1 Declaration about Commencement CertificateForm D Commencement Declaration of Aditya Buidcon.pdf · uploaded 8 Jan 2022Source
- 1 CERSAI detailsCersai Details.pdf · uploaded 8 Jan 2022Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect certificate of Kaustubh March 28-03-22_compressed.pdf · uploaded 8 Jun 2022Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineers Certificate - 31-03-22_compressed.pdf · uploaded 8 Jun 2022Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Samrudhi CA Certificate_compressed.pdf · uploaded 8 Jun 2022Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)Annual report Aditya Buildcon_Final.pdf · uploaded 14 Oct 2022Source
- 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect certf of Samrudhi.pdf · uploaded 15 Nov 2022Source
- 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect certificate of Samrudhi 1.pdf · uploaded 15 Nov 2022Source
- 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)ENGr CERTE of kaustubh (1)_compressed.pdf · uploaded 15 Nov 2022Source
- 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)NJ 608 3RD RERA CERTIFICATE _compressed.pdf · uploaded 15 Nov 2022Source
- 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer's Certificate Samrudhi New.pdf · uploaded 15 Nov 2022Source
- 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architech certf of Samrudhi.pdf · uploaded 30 Jan 2023Source
- 6 Engineer’s Certificate on Cost Incurred on Project (Form 2)Samrudhi chs Engr Certificate.pdf · uploaded 30 Jan 2023Source
- 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA Certificate Final.pdf · uploaded 30 Jan 2023Source
- 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA certificate sep 30 Samrudhi.pdf · uploaded 30 Jan 2023Source
- 5 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA CERTIFICATE FINAL.pdf · uploaded 30 Jan 2023Source
- 6 Architect’s Certificate of Percentage of Completion of Work (Form 1)architect certificate of samrudhi 01-04-2023.pdf · uploaded 5 May 2023Source
- 7 Engineer’s Certificate on Cost Incurred on Project (Form 2)engineers certificate samrudhi 01-04-2023.pdf · uploaded 5 May 2023Source
- 6 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA Certificate.pdf · uploaded 5 May 2023Source
- 7 Architect’s Certificate of Percentage of Completion of Work (Form 1)architect certificate of samrudhi.pdf · uploaded 18 May 2023Source
- 8 Engineer’s Certificate on Cost Incurred on Project (Form 2)engineers certificate samrudhi.pdf · uploaded 18 May 2023Source
- 7 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA Certificate.pdf · uploaded 18 May 2023Source
- 8 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect certifiate of Samrudhi June 30.pdf · uploaded 8 Aug 2023Source
- 9 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer chertf of samrudhi.pdf · uploaded 8 Aug 2023Source
- 8 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA Certificate of Samrudhi.pdf · uploaded 8 Aug 2023Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)Form 5 Aditya Buildcon Samruddhi Signed.pdf · uploaded 7 Oct 2023Source
- 9 Architect’s Certificate of Percentage of Completion of Work (Form 1)Samruddhi Architect Certificate.pdf · uploaded 31 Oct 2023Source
- 10 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineers Certificate-Samrudhi chs.pdf · uploaded 31 Oct 2023Source
- 9 CA Certificate on Project Cost & Fund withdrawal (Form 3)Samrudhi CA Certificate.pdf · uploaded 4 Jan 2024Source
- 1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentOc of Ground to First floor Samrudhi chs.pdf · uploaded 4 Jan 2024Source
- 2 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentOC of 2nd flr to 7th SAMRUDHI CHS.pdf · uploaded 4 Jan 2024Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)FORM 5.pdf · uploaded 7 Oct 2024Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)FORM 5.pdf · uploaded 7 Oct 2024Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Archhitect certf upto OC dt of Samrudhi.pdf · uploaded 4 Feb 2025Source
- 1 Architect’s Certificate on Completion of Project (Form 4)Form 4 - Final.pdf · uploaded 4 Feb 2025Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA Certificate -Samrudhi CHS.pdf · uploaded 4 Feb 2025Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer Certificate - Completion.pdf · uploaded 4 Feb 2025Source
Technical
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvalsLand parcel 8361 TO 8367
As registered with MahaRERA and published on its project page
- Project type
- Others
- Status on MahaRERA
- Certificate Signed
- Unit types
- 2BHK, 3BHK, Office space, Shop22 units in all
- Address
- 8361 To 8367, Mouje Dombivli, DombivaliPIN 421202
- Village
- Dombivli, Kalyan taluka
- Land area for this project
- 673 sq m (7,244 sq ft)
- Permissible built-up area
- 2,207 sq m (23,754 sq ft)
- Sanctioned built-up area
- 2,207 sq m (23,754 sq ft)
- Designated bank account
- 203
- Developed in phases
- No
Survey, CTS, gat or plot numbers
Land as published on MahaRERA's project page
8361 TO 8367
Boundaries
- North
- Cts 8368 8348
- South
- Chiplunkar Road And Partly By Cts No 8321
- East
- Cts No 8348 8321
- West
- Cts No 8368 Partly By Chiplunkar Road
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking22 units
20 of 22 units booked (91%), as the promoter reported to MahaRERA
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 2BHK | 56.32 sq m · 606 sq ft | 12 | 12 |
| 3BHK | 71.62 sq m · 771 sq ft | 6 | 4 |
| Office space | 127.66 sq m · 1,374 sq ft | 1 | 1 |
| Shop | 37.1 sq m · 399 sq ft | 1 | 1 |
| Shop | 39.27 sq m · 423 sq ft | 1 | 1 |
| Shop | 66.71 sq m · 718 sq ft | 1 | 1 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.