Skip to content
Residential / Group Housing · 1 buildingRERA P51700008571

Rambhuvan Residency

Deedo IDDP-THN-0JXW

MahaRERA shows it completed, after its date was pushed back 1 year; no MahaRERA orders on record.

Dombivli, Thane 421201 · by Abhay Anant Kamat

DeliveryCompletedAs MahaRERA shows · after a 1 yr extensionRegulatoryNo ordersNot in any MahaRERA list or order Deedo has read

Buying a flat here?

See every deed registered on it.

MahaRERA shows it completed, after its date was pushed back 1 year

  • This projectRegistered 19 Aug 2017, completion promised 31 Dec 2017, revised to 31 Dec 2018.

1 extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales, rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

The building

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page. Construction % is the average of the developer's own declared activity progress to MahaRERA, not an inspection.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP51700008571
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5170000857119 Aug 201731 Dec 201731 Dec 2018Abhay Anant KamatProject page
Documents32

15 documents held by Deedo, 17 filings listed on MahaRERA's project page

Title report

Encumbrance details

Form B

Form 1 (2)

Form 2 (2)

Registration certificate

Show all 32 documentsShow fewer documents

Extension certificate

Form 4

Other (3)

Layout plan

Allotment letter

Document library

  • Details of encumbrancesCertificate Impressions prop 001.pdf · uploaded 31 Jul 2017View
  • Declaration in FORM BNotarised Form B 3 001 (2 files merged).pdf · uploaded 31 Jul 2017View
  • Certificates of Architect (Form 1)(Mandatory for only ongoing project)ARCHITECT FORM 1 PROP.pdf · uploaded 31 Jul 2017View
  • Certificates of Engineer (Form 2)(Mandatory for only ongoing project)FORM 2 PROPRIETOR.pdf · uploaded 31 Jul 2017View
  • Copy of Layout Approval (in case of layout)PROP PLAN.pdf · uploaded 31 Jul 2017View
  • Proforma of Allotment letterSELF DECLARATION CERTIFICATE REGAGREEMENT FOR SALE (PROP) 001.pdf · uploaded 31 Jul 2017View
  • Building Plan Approval (IOD)PROP PLAN.pdf · uploaded 31 Jul 2017View
  • Copy of the legal title reportTITLE CERTIFICATE PROP.pdf · uploaded 31 Jul 2017View
  • Certificates of Engineer (Form 2)(Mandatory for only ongoing project)IMPRESSIONS RAMBHUVAN ENGG CERTIFICATE.pdf · uploaded 24 Nov 2017View
  • Certificates of Architect (Form 1)(Mandatory for only ongoing project)IMPRESSIONS RAMBHUVAN ARCHITECT CERTIFICATE.pdf · uploaded 24 Nov 2017View
  • Architect’s Certificate on Completion of Project (Form 4)RAMBHUVAN FORM 4.pdf · uploaded 2 Jan 2020View
  • Status of Formation of Legal Entity (Society/Co Op etc.)RAMBHUVAN RESIDENCY SOCIETY REGISTRACTION CERTI.pdf · uploaded 29 Jun 2021View

Promoter documents

  • Declaration Form BNotarised Form B 3 001 (2 files merged).pdf · uploaded 31 Jul 2017View
  • Legal Title reportTITLE CERTIFICATE PROP.pdf · uploaded 31 Jul 2017View

Technical documents

  • Layout ApprovalPROP PLAN.pdfView
  • Building Plan ApprovalPROP PLAN.pdfView

Proforma allotment letter

  • Proforma allotment letterSELF DECLARATION CERTIFICATE REGAGREEMENT FOR SALE (PROP) 001.pdfView

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsPlot 42, 91B / C T S NO 8388 TO 8393

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Completed
Address
Plot No 42, Survey No 91a/1/1 And 91b / C T S No 8388 To 8393PIN 421201
Village
Dombivli, Kalyan taluka
Land area for this project
479 sq m (5,151 sq ft)
Permissible built-up area
792 sq m (8,522 sq ft)
Sanctioned built-up area
792 sq m (8,522 sq ft)
Designated bank account
Idbi Bank
Litigation declared by promoter
None declared
Financial encumbrance declared
None declared

Survey, CTS, gat or plot numbers

4291B / C T S NO 8388 TO 8393PLOT NO 42SURVEY NO 91A/1/1

Land as published on MahaRERA's project page

PLOT NO 42, SURVEY NO 91A/1/1 AND 91B / C T S NO 8388 TO 8393

Boundaries

North
Sangam Chs
South
Chiplunkar Road
East
Vakratund Chs
West
Rajaji Road

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking6 parking spaces

0 units registered

Parking

TypeTwo-wheelerFour-wheelerBusVisitorTotal
Closed/Covered00000
Open Space00006

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Construction progress2 buildings and areas

Work completed, as the promoter reported it to MahaRERA (Form 1)

Rambhuvan Residency

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor0%
  • Slabs of Super Structure100%
Show all 11 activitiesShow fewer activities
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
  • Sanitary Fittings within the flats / premises100%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.99%

Common areas and amenities

  • Internal Roads & FootpathsNot applicable
  • Water SupplyWATER SUPPLY ON THE RECEIPT OF OC0%
  • Sewerage (Chamber, Lines, Septic Tank , STP)WORK COMPLETED100%
  • Storm Water DrainsNot applicable
  • Landscaping & Tree PlantingWORK COMPLETED100%
  • Street LightingNot applicable
Show all 15 activitiesShow fewer activities
  • Community BuildingsNot applicable
  • Treatment And Disposal Of Sewage And Sullage WaterNot applicable
  • Solid Waste Management And DisposalNot applicable
  • Water conservation /Rain water harvestingWORK COMPLETED100%
  • Energy managemcntWORK COMPLETED100%
  • Fire protection and fire safety requirementsWORK COMPLETD100%
  • Electrical meter room, sub-station, receiving stationWORK COMPLETED100%
  • Aggregate area of recreational Open SpaceNot applicable
  • Open ParkingWORK COMPLETED100%

Source: MahaRERA project page. Percentages are the promoter's own declaration, not an inspection.

Professionals3

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectGaurav V Likhite—
EngineerRajesh A Thakare—
OtherSunil Dattatray Rane—

Source: MahaRERA project page. Contact details are not shown.

Data through11 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Report a problemMethodology