Deedo IDDP-THN-R10MCompletion was pushed back 4 months, to Apr 2028; no MahaRERA orders on record; 60% of its units are booked.
Dombivli, Thane 421201 · by Vinayak Deoram Patil
Buying a flat here?
See every deed registered on it.
Completion was pushed back 4 months, to Apr 2028
- This projectRegistered 24 Feb 2023, completion promised 31 Dec 2027, revised to 30 Apr 2028.
No extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales, rentals and mortgages matched to this project · the free view shows a price band
The building
Open a building to see every flat, floor by floor.
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationP51700049777
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P51700049777 | 24 Feb 2023 | 31 Dec 2027 | 30 Apr 2028 | Vinayak Deoram Patil | Project page |
Documents120
1 document held by Deedo, 119 filings listed on MahaRERA's project page
Finance
- PAN CardVinayak Patil (New pan card).pdf · uploaded 23 Dec 2022Source
Legal
Migrated
- 1 PAN CardVinayak Patil (New pan card).pdf · uploaded 23 Dec 2022Source
- 1 a Details of encumbrances concerned to FinanceEncumbrance -Fianance -Creekedge.pdf · uploaded 23 Dec 2022Source
- 2 a Details of encumbrances concerned to FinanceEncumbrance -Legal -Creekedge.pdf · uploaded 23 Dec 2022Source
- 1 b Details of encumbrances concerned to LegalEncumbrance -Fianance -Creekedge.pdf · uploaded 23 Dec 2022Source
Show all 120 documentsShow fewer documents
Migrated
- 2 b Details of encumbrances concerned to LegalEncumbrance -Legal -Creekedge.pdf · uploaded 23 Dec 2022Source
- 1 Declaration about Commencement CertificateFormat D -Creekedge.pdf · uploaded 23 Dec 2022Source
- 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFormat A -Creekedge.pdf · uploaded 23 Dec 2022Source
- 1 Proforma of Allotment letterAllotment Letter_Creek Edge_Rudra Construction_26122022.pdf · uploaded 25 Jan 2023Source
- 1 CERSAI detailsCERSAI_Search_Report_200258809898_For_Asset_Based_Search_27_01_2023_18_45_25_668.pdf · uploaded 27 Jan 2023Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)First Form 3 - Creek Edge - Rudra Construction - Revised.pdf · uploaded 27 Jan 2023Source
- 1 Deviation Report with respect to Allotment letter20230127000751_2-4.pdf · uploaded 27 Jan 2023Source
- 1 Deviation Report with respect to model copy of AgreementDeviation Agreement Creek edge.pdf · uploaded 27 Jan 2023Source
- 1 Copy of Layout Approval (in case of layout)MYSCAN_20230113_0001_rotated_11zon.pdf · uploaded 28 Jan 2023Source
- 1 Building Plan Approval / NA Order for plotted developmentMYSCAN_20230113_0001_rotated_11zon.pdf · uploaded 28 Jan 2023Source
- 2 Building Plan Approval / NA Order for plotted developmentMYSCAN_20230113_0002_11zon_rotated.pdf · uploaded 28 Jan 2023Source
- 3 Building Plan Approval / NA Order for plotted developmentMYSCAN_20230113_0003_11zon_rotated.pdf · uploaded 28 Jan 2023Source
- 1 Commencement Certificates / NA Order for plotted developmentAppendix D.pdf · uploaded 28 Jan 2023Source
- 1 Disclosure of Interest in Other Real Estate OrganizationsAnnuxure A.pdf · uploaded 28 Jan 2023Source
- 1 Declaration in FORM BAffidavit cum Declaration.pdf · uploaded 6 Feb 2023Source
- 1 Proforma of Agreement for saleAFS_Creek Edge_Rudra Construction_19012023.pdf · uploaded 6 Feb 2023Source
- 1 Copy of the legal title reportLegal Title Report (2).pdf · uploaded 14 Feb 2023Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2- Creek Edge as on March 2023.pdf · uploaded 24 Jul 2023Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2- Creek Edge as on June 2023.pdf · uploaded 24 Jul 2023Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3- Creek Edge as on 31-03-2023.pdf · uploaded 24 Jul 2023Source
- 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3- Creek Edge as on 30-06-2023.pdf · uploaded 24 Jul 2023Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)Form 5- Creek Edge as on 2022-23.pdf · uploaded 27 Sep 2023Source
- 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 - Creek Edge as on Sep 2023.pdf · uploaded 16 Oct 2023Source
- 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 of Creek Edge as on Sep 2023.pdf · uploaded 16 Oct 2023Source
- 5 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 Sept 2023.pdf · uploaded 25 Oct 2023Source
- 4 Building Plan Approval / NA Order for plotted developmentPage 1_compressed.pdf · uploaded 27 Oct 2023Source
- 5 Building Plan Approval / NA Order for plotted developmentPage 2_compressed.pdf · uploaded 27 Oct 2023Source
- 6 Building Plan Approval / NA Order for plotted developmentPage 3_compressed.pdf · uploaded 27 Oct 2023Source
- 7 Building Plan Approval / NA Order for plotted developmentPage 4_compressed.pdf · uploaded 27 Oct 2023Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)ARCHITECT CERTIFICATE Oct 2023.pdf · uploaded 3 Nov 2023Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)Form 2A (FY 2022-23).pdf · uploaded 18 Nov 2023Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 - Creek edge as on Sept 2023.pdf · uploaded 14 Dec 2023Source
- 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 - Creek edge as on March 2023.pdf · uploaded 14 Dec 2023Source
- 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 - Creek edge as on June 2023.pdf · uploaded 14 Dec 2023Source
- 6 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 - Creek edge as on Sept 2023.pdf · uploaded 14 Dec 2023Source
- 6 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 - Creek edge as on March 2023.pdf · uploaded 14 Dec 2023Source
- 7 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 - Creek edge as on June 2023.pdf · uploaded 14 Dec 2023Source
- 8 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 - Creek edge as on Sept 2023.pdf · uploaded 14 Dec 2023Source
- 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 - Creek Edge as on Dec 2023.pdf · uploaded 19 Jan 2024Source
- 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 - Creek Edge as on March 2024.pdf · uploaded 15 Apr 2024Source
- 7 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 - Creek Edge as on Sep 2023.pdf · uploaded 7 Jun 2024Source
- 9 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 of Creek Edge as on 31-03-2024.pdf · uploaded 7 Jun 2024Source
- 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 - Creek Edge as on June 2024.pdf · uploaded 20 Jul 2024Source
- 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 of Creek Edge as on 30-06-2024 New.pdf · uploaded 18 Oct 2024Source
- 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 of Creek Edge as on 30-09-2024.pdf · uploaded 18 Oct 2024Source
- 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 - Creek Edge as on 30-09-2024.pdf · uploaded 18 Oct 2024Source
- 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 - Creek Edge as on June 2024.pdf · uploaded 18 Oct 2024Source
- 1 Copy of Layout Approval (in case of layout)1_11zon.pdf · uploaded 11 Nov 2024Source
- 1 Commencement Certificates / NA Order for plotted developmentCC.pdf · uploaded 11 Nov 2024Source
- 1 Building Plan Approval / NA Order for plotted development2_11zon.pdf · uploaded 11 Nov 2024Source
- 2 Building Plan Approval / NA Order for plotted development3_11zon.pdf · uploaded 11 Nov 2024Source
- 3 Building Plan Approval / NA Order for plotted development4_11zon.pdf · uploaded 11 Nov 2024Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 of Creek Edge as on 31-12-2024.pdf · uploaded 16 Jan 2025Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 - Creek Edge as on 31-12-2024.pdf · uploaded 16 Jan 2025Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 - Sept 2024.pdf · uploaded 30 Jan 2025Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 - Dec 2024.pdf · uploaded 30 Jan 2025Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 (Dec 2024)_compressed.pdf · uploaded 30 Jan 2025Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 (Dec 2024)_compressed.pdf · uploaded 30 Jan 2025Source
- 1 Disclosure of sold/ booked inventoryCircular 29 (Dec 2024)_compressed.pdf · uploaded 30 Jan 2025Source
- 1 Declaration about Commencement CertificateFormat D.pdf · uploaded 31 Jan 2025Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)Form 2A FY 2023-24.pdf · uploaded 5 Feb 2025Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)Form 5 - Creek Edge FY 2023-24.pdf · uploaded 14 Feb 2025Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)form 5_compressed.pdf · uploaded 15 Feb 2025Source
- 2 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)Form 5 Creek Edge FY 2023-24.pdf · uploaded 15 Feb 2025Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 - Creek Edge as on March 2025.pdf · uploaded 12 Apr 2025Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 of Creek Edge as on 31-03-2025.pdf · uploaded 20 Apr 2025Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 - Creek Edge as on March 2025.pdf · uploaded 20 Apr 2025Source
- Form 1Form 1 - Creek Edge as on June 2025.pdf · uploaded 29 Jul 2025Source
- Form 2Form 2 - Creek Edge as on June 2025.pdf · uploaded 29 Jul 2025Source
- Form 3Form 3 - Creek Edge as on June 2025.pdf · uploaded 29 Jul 2025Source
- Disclosure of Sold and Booked InventoryCircular 29 - Creek Edge as on June 2025.pdf · uploaded 29 Jul 2025Source
- Form 1Form 1 - Creek Edge as on Sep 2025.pdf · uploaded 20 Oct 2025Source
- Form 2Form 2 - Creek Edge as on Sept 2025.pdf · uploaded 20 Oct 2025Source
- Form 3Form 3 of Creek Edge as on 30-09-2025.pdf · uploaded 20 Oct 2025Source
- Disclosure of Sold and Booked InventoryCircular 29 - Creek Edge as on Sept 2025.pdf · uploaded 20 Oct 2025Source
- Form 1Form 1 - Creek Edge as on March 2026.pdf · uploaded 24 Apr 2026Source
- Form 2Form 2 - Creek Edge as on March 2026.pdf · uploaded 24 Apr 2026Source
- Form 3Form 3 - Creek Edge as on March 2026.pdf · uploaded 24 Apr 2026Source
- Disclosure of Sold and Booked InventoryCircular 29 - Creek Edge as on March 2026.pdf · uploaded 24 Apr 2026Source
- Form 1Form 1 - Creek Edge as on Dec 2025.pdf · uploaded 24 Apr 2026Source
- Form 2Form 2 - Creek Edge as on March 2026.pdf · uploaded 24 Apr 2026Source
- Form 3Form 3 - Creek Edge as on Dec 2025.pdf · uploaded 24 Apr 2026Source
- Disclosure of Sold and Booked InventoryCircular 29 - Creek Edge as on Dec 2025.pdf · uploaded 24 Apr 2026Source
- Form 2A (FY 2024-2025)Form 2A Creek Egde FY 2024-25_compressed.pdf · uploaded 1 Jul 2026Source
- Form 2A (FY 2025-2026)Form 2A Creek Egde FY 2025-26_compressed.pdf · uploaded 1 Jul 2026Source
- Form 1Form 1 - Creek Edge June 2026.pdf · uploaded 21 Jul 2026Source
- Form 2Form 2 - Creek Edge June 2026.pdf · uploaded 21 Jul 2026Source
- Form 3Form 3 - Creek Edge June 2026.pdf · uploaded 21 Jul 2026Source
- Disclosure of Sold and Booked InventoryCircular 29 - Creek Edge June 2026.pdf · uploaded 21 Jul 2026Source
- Form 5 (FY 2025-2026)Form-5 Creek Edge For FY 2025-26.pdf · uploaded 30 Sep 2026Source
Technical
- DocumentMYSCAN_20230113_0001_rotated_11zon.pdf · uploaded 28 Jan 2023Source
- DocumentMYSCAN_20230113_0001_rotated_11zon.pdf · uploaded 28 Jan 2023Source
- DocumentMYSCAN_20230113_0002_11zon_rotated.pdf · uploaded 28 Jan 2023Source
- DocumentMYSCAN_20230113_0003_11zon_rotated.pdf · uploaded 28 Jan 2023Source
- DocumentPage 1_compressed.pdf · uploaded 27 Oct 2023Source
- DocumentPage 2_compressed.pdf · uploaded 27 Oct 2023Source
- DocumentPage 3_compressed.pdf · uploaded 27 Oct 2023Source
- DocumentPage 4_compressed.pdf · uploaded 27 Oct 2023Source
- Document1_11zon.pdf · uploaded 11 Nov 2024Source
- Document2_11zon.pdf · uploaded 11 Nov 2024Source
- Document3_11zon.pdf · uploaded 11 Nov 2024Source
- Document4_11zon.pdf · uploaded 11 Nov 2024Source
Technical (Architect)
Technical (Engineer)
- DocumentForm 2 - Creek Edge as on Sep 2023.pdf · uploaded 7 Jun 2024Source
- DocumentForm 2 - Creek Edge as on June 2024.pdf · uploaded 18 Oct 2024Source
- DocumentForm 2 - Creek Edge as on 30-09-2024.pdf · uploaded 18 Oct 2024Source
- DocumentForm 2 - Creek Edge as on 31-12-2024.pdf · uploaded 16 Jan 2025Source
- DocumentForm 2 (Dec 2024)_compressed.pdf · uploaded 30 Jan 2025Source
- DocumentForm 2 - Creek Edge as on March 2025.pdf · uploaded 20 Apr 2025Source
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvalsLand parcel 139(NEW), 140 (NEW)
As registered with MahaRERA and published on its project page
- Project type
- Others
- Status on MahaRERA
- Certificate Signed
- Unit types
- 1.5BHK, 1BHK, 1RK, 2BHK, 3BHK, 4BHK, Office space, Shop175 units in all
- Address
- S.NO.68(OLD), 139(NEW), HISSA NO.1, S.NO.229(OLD), 140 (NEW), HISSA NO.1 & 3, S.NO. 244(OLD), 141(NEW), HISSA NO. 1 & 2, S.NO.221(OLD), 142(NEW), HISSA NO.2 & 4, Kanchangaon, Kanchangaon, Dombivli EastPIN 421201
- Village
- Dombivli, Kalyan taluka
- Location
- 19.22786, 73.10577
- Land area for this project
- 3,454 sq m (37,176 sq ft)
- Permissible built-up area
- 12,642 sq m (1,36,080 sq ft)
- Sanctioned built-up area
- 12,642 sq m (1,36,080 sq ft)
- Designated bank account
- 105
- Developed in phases
- No
Survey, CTS, gat or plot numbers
Land as published on MahaRERA's project page
S.NO.68(OLD), 139(NEW), HISSA NO.1, S.NO.229(OLD), 140 (NEW), HISSA NO.1 & 3, S.NO. 244(OLD), 141(NEW), HISSA NO. 1 & 2, S.NO.221(OLD), 142(NEW), HISSA NO.2 & 4
Boundaries
- North
- 24M Wide DP Road
- South
- Vithal Plaza CHS
- East
- Garden Plot
- West
- Plot
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking175 units
105 of 175 units booked (60%), as the promoter reported to MahaRERA
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 1.5BHK | 38.79 sq m · 418 sq ft | 10 | 6 |
| 1.5BHK | 38.96 sq m · 419 sq ft | 1 | 1 |
| 1.5BHK | 43.75 sq m · 471 sq ft | 16 | 13 |
| 1BHK | 35.37 sq m · 381 sq ft | 26 | 5 |
| 1BHK | 36.36 sq m · 391 sq ft | 4 | 4 |
| 1BHK | 36.4 sq m · 392 sq ft | 3 | 3 |
| 1BHK | 36.42 sq m · 392 sq ft | 10 | 10 |
| 1RK | 28.97 sq m · 312 sq ft | 1 | 0 |
Show all 33 unit rowsShow fewer unit rows
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 1RK | 28.98 sq m · 312 sq ft | 1 | 1 |
| 2BHK | 49.18 sq m · 529 sq ft | 19 | 14 |
| 2BHK | 49.71 sq m · 535 sq ft | 6 | 6 |
| 2BHK | 51.35 sq m · 553 sq ft | 7 | 6 |
| 2BHK | 51.69 sq m · 556 sq ft | 16 | 12 |
| 2BHK | 53.67 sq m · 578 sq ft | 1 | 1 |
| 2BHK | 58.07 sq m · 625 sq ft | 5 | 3 |
| 2BHK | 58.43 sq m · 629 sq ft | 7 | 6 |
| 2BHK | 58.75 sq m · 632 sq ft | 4 | 3 |
| 2BHK | 58.77 sq m · 633 sq ft | 3 | 3 |
| 3BHK | 62.94 sq m · 677 sq ft | 6 | 6 |
| 3BHK | 63.41 sq m · 683 sq ft | 2 | 1 |
| 4BHK | 126.11 sq m · 1,357 sq ft | 1 | 0 |
| Office space | 24.46 sq m · 263 sq ft | 3 | 0 |
| Office space | 26.74 sq m · 288 sq ft | 3 | 0 |
| Office space | 28.49 sq m · 307 sq ft | 3 | 0 |
| Office space | 35.97 sq m · 387 sq ft | 3 | 0 |
| Office space | 40.88 sq m · 440 sq ft | 3 | 0 |
| Office space | 58.32 sq m · 628 sq ft | 3 | 0 |
| Office space | 109.42 sq m · 1,178 sq ft | 3 | 0 |
| Shop | 22.4 sq m · 241 sq ft | 1 | 0 |
| Shop | 31.82 sq m · 343 sq ft | 1 | 1 |
| Shop | 37.54 sq m · 404 sq ft | 1 | 0 |
| Shop | 57.11 sq m · 615 sq ft | 1 | 0 |
| Shop | 108.24 sq m · 1,165 sq ft | 1 | 0 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Professionals2
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Chartered accountant | Parth Gada | — |
| Engineer | Ashokan | — |
Source: MahaRERA project page. Contact details are not shown.