Residential / Group Housing · 2 buildings · 282 unitsRERA P51700050483

Arista Skyline

Deedo IDDP-THN-KPTY

Completion was pushed back 4 months, to Apr 2029; no MahaRERA orders on record; 32% of its units are booked.

Dombivli, Thane 421204 · by Glen Square

DeliveryExtended 4 moPromised Dec 2028 · now due Apr 2029RegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales32% booked89 of 282 units · as the promoter reported to MahaRERA

Buying a flat here?

See every deed registered on it.

Completion was pushed back 4 months, to Apr 2029

  • This projectRegistered 17 Apr 2023, completion promised 31 Dec 2028, revised to 30 Apr 2029.

No extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales, rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

2 buildings

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP51700050483
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5170005048317 Apr 202331 Dec 202830 Apr 2029Glen SquareProject page
Documents156

1 document held by Deedo, 155 filings listed on MahaRERA's project page

Registration certificate

Finance

  • PAN CardGlen Square pancard (2).pdf · uploaded 7 Mar 2023Source

Legal

  • Legal Title reportGlen Square legal title RERA 37-2_0001.pdf · uploaded 7 Mar 2023Source
  • Legal Title reportGlen Square legal title RERA 38-1-F_0001.pdf · uploaded 7 Mar 2023Source
  • Legal Title reportGlen Square legal title RERA 38-1-A_0001.pdf · uploaded 7 Mar 2023Source
  • Legal Title reportGlen Square legal title RERA 38-1-E_0001.pdf · uploaded 7 Mar 2023Source
  • Legal Title reportGlen Square legal title RERA 38-1-B_0001.pdf · uploaded 7 Mar 2023Source
  • Legal Title reportGlen Square legal title RERA 38-1-J_0001.pdf · uploaded 7 Mar 2023Source
Show all 156 documentsShow fewer documents

Legal

  • Legal Title reportGlen Square legal title RERA 58-2-2_0001.pdf · uploaded 7 Mar 2023Source
  • Legal Title reportGlen Square legal title RERA 58-2-1-1_0001.pdf · uploaded 7 Mar 2023Source
  • Declaration Form BGlen Square Form B Declaration Ramesh Patel _0001.pdf · uploaded 7 Mar 2023Source
  • Other – LegalRERA Title Report (1).pdf · uploaded 28 Mar 2023Source
  • Other – LegalRERA HDFC Bank Letter.pdf · uploaded 6 Jan 2025Source
  • Other – LegalNotary.pdf · uploaded 6 Jan 2025Source
  • Other – LegalAnnexure A.pdf · uploaded 18 Jan 2025Source
  • Other – LegalFormat A.pdf · uploaded 18 Jan 2025Source

Migrated

  • 1 PAN CardGlen Square pancard (2).pdf · uploaded 7 Mar 2023Source
  • 1 Copy of the legal title reportGlen Square legal title RERA 37-2_0001.pdf · uploaded 7 Mar 2023Source
  • 2 Copy of the legal title reportGlen Square legal title RERA 38-1-F_0001.pdf · uploaded 7 Mar 2023Source
  • 3 Copy of the legal title reportGlen Square legal title RERA 38-1-A_0001.pdf · uploaded 7 Mar 2023Source
  • 4 Copy of the legal title reportGlen Square legal title RERA 38-1-E_0001.pdf · uploaded 7 Mar 2023Source
  • 5 Copy of the legal title reportGlen Square legal title RERA 38-1-B_0001.pdf · uploaded 7 Mar 2023Source
  • 6 Copy of the legal title reportGlen Square legal title RERA 38-1-J_0001.pdf · uploaded 7 Mar 2023Source
  • 7 Copy of the legal title reportGlen Square legal title RERA 58-2-2_0001.pdf · uploaded 7 Mar 2023Source
  • 8 Copy of the legal title reportGlen Square legal title RERA 58-2-1-1_0001.pdf · uploaded 7 Mar 2023Source
  • 1 a Details of encumbrances concerned to FinanceGlen Square Legal litigation encumbrance_0001.pdf · uploaded 7 Mar 2023Source
  • 1 b Details of encumbrances concerned to LegalGlen Square Legal litigation encumbrance_0001.pdf · uploaded 7 Mar 2023Source
  • 1 Declaration about Commencement CertificateGlen Square declaration about commencement certification _0001.pdf · uploaded 7 Mar 2023Source
  • 1 Declaration in FORM BGlen Square Form B Declaration Ramesh Patel _0001.pdf · uploaded 7 Mar 2023Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Glen Square Architect Certificate (1).pdf · uploaded 7 Mar 2023Source
  • 1 Proforma of Agreement for saleDRAFT1.pdf · uploaded 7 Mar 2023Source
  • 1 Proforma of Allotment letterGlen Square Allotment Letter _0001 (1).pdf · uploaded 7 Mar 2023Source
  • 2 a Details of encumbrances concerned to Finance1 a Details of encumbrances concerned to Finance (1) (2 files merged).pdf · uploaded 28 Mar 2023Source
  • 2 b Details of encumbrances concerned to Legal1 a Details of encumbrances concerned to Finance (1) (2 files merged).pdf · uploaded 28 Mar 2023Source
  • 1 Deviation Report with respect to Allotment letter1 Deviation Report with respect to model copy of Agreement (5).pdf · uploaded 28 Mar 2023Source
  • 1 Other – LegalRERA Title Report (1).pdf · uploaded 28 Mar 2023Source
  • 1 Copy of Layout Approval (in case of layout)4 plan copy (2)_1.pdf · uploaded 30 Mar 2023Source
  • 2 Copy of Layout Approval (in case of layout)4 plan copy (2)_2.pdf · uploaded 30 Mar 2023Source
  • 3 Copy of Layout Approval (in case of layout)4 plan copy (2)_3.pdf · uploaded 30 Mar 2023Source
  • 4 Copy of Layout Approval (in case of layout)4 plan copy (2)_4.pdf · uploaded 30 Mar 2023Source
  • 5 Copy of Layout Approval (in case of layout)1.pdf · uploaded 30 Mar 2023Source
  • 6 Copy of Layout Approval (in case of layout)2.pdf · uploaded 30 Mar 2023Source
  • 7 Copy of Layout Approval (in case of layout)3.pdf · uploaded 30 Mar 2023Source
  • 1 Building Plan Approval / NA Order for plotted development4 plan copy (2)_1.pdf · uploaded 30 Mar 2023Source
  • 2 Building Plan Approval / NA Order for plotted development4 plan copy (2)_2.pdf · uploaded 30 Mar 2023Source
  • 3 Building Plan Approval / NA Order for plotted development4 plan copy (2)_3.pdf · uploaded 30 Mar 2023Source
  • 4 Building Plan Approval / NA Order for plotted development4 plan copy (2)_4.pdf · uploaded 30 Mar 2023Source
  • 5 Building Plan Approval / NA Order for plotted development1.pdf · uploaded 30 Mar 2023Source
  • 6 Building Plan Approval / NA Order for plotted development2.pdf · uploaded 30 Mar 2023Source
  • 7 Building Plan Approval / NA Order for plotted development3.pdf · uploaded 30 Mar 2023Source
  • 1 Commencement Certificates / NA Order for plotted developmentGlen Square Adesh patr_0001 (11) (1).pdf · uploaded 30 Mar 2023Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 (2).pdf · uploaded 30 Mar 2023Source
  • 1 CERSAI detailsGlen squareersai Report_0001.pdf · uploaded 30 Mar 2023Source
  • 1 Disclosure of Interest in Other Real Estate OrganizationsASHOK BHAI.pdf · uploaded 30 Mar 2023Source
  • 2 Disclosure of Interest in Other Real Estate OrganizationsAVINASH JAIN.pdf · uploaded 30 Mar 2023Source
  • 3 Disclosure of Interest in Other Real Estate OrganizationsDEVJI RAVARIYA.pdf · uploaded 30 Mar 2023Source
  • 4 Disclosure of Interest in Other Real Estate OrganizationsGAURAV MHATRE.pdf · uploaded 30 Mar 2023Source
  • 5 Disclosure of Interest in Other Real Estate Organizationsprashant shukla.pdf · uploaded 30 Mar 2023Source
  • 6 Disclosure of Interest in Other Real Estate OrganizationsRAMESH PATEL.pdf · uploaded 30 Mar 2023Source
  • 7 Disclosure of Interest in Other Real Estate OrganizationsSANKET RAVAT.pdf · uploaded 30 Mar 2023Source
  • 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameGLEN SQUARE DECLARATION SAPERATE BANK ACCOUNT _0001.pdf · uploaded 30 Mar 2023Source
  • 1 Deviation Report with respect to model copy of AgreementGlen square Deviation model copy of Agreement _0001.pdf · uploaded 30 Mar 2023Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Glen Square CA form 3_0001.pdf · uploaded 10 Apr 2023Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)Adobe Scan Nov 22, 2023.pdf · uploaded 24 Nov 2023Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Glen Square Arista Skyline Architect certificate form 1.pdf · uploaded 19 Jan 2024Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)GLEN SQUARE FORM 3 CA Q3 F Y 23-24_0001 (1).pdf · uploaded 19 Jan 2024Source
  • 1 Disclosure of sold/ booked inventoryScan (2).pdf · uploaded 29 Mar 2024Source
  • 2 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)form 5 glen square.pdf · uploaded 29 Mar 2024Source
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)Glen square Arista Skyline Form 1 Architect Certificate_0001 (1).pdf · uploaded 10 May 2024Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Glen square form No 2 quarter 4_0001.pdf · uploaded 10 May 2024Source
  • 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)Glen square form No 3 quarter 4_0001 - converted.pdf · uploaded 10 May 2024Source
  • 3 a Details of encumbrances concerned to FinanceRERA Encumbrance Bajaj.pdf · uploaded 25 Jul 2024Source
  • 3 b Details of encumbrances concerned to LegalRERA Encumbrance Bajaj.pdf · uploaded 25 Jul 2024Source
  • 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)Glen Square Form 1 architect certificate _0001.pdf · uploaded 7 Aug 2024Source
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)Glen Square Form 2 Engineers certificate _0001.pdf · uploaded 7 Aug 2024Source
  • 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)Glen Square Form 3 CA certificate _0001 - converted.pdf · uploaded 7 Aug 2024Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Glen Square Architect certificate Form 1_0001.pdf · uploaded 4 Nov 2024Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)H R Jain Associates Form 3 - converted.pdf · uploaded 4 Nov 2024Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Glen Square Engineers certificate Form 2_0001.pdf · uploaded 4 Nov 2024Source
  • 1 Other – LegalRERA HDFC Bank Letter.pdf · uploaded 6 Jan 2025Source
  • 2 Other – LegalNotary.pdf · uploaded 6 Jan 2025Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)Glen Square Form 5 (1).pdf · uploaded 8 Jan 2025Source
  • 1 Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)2 Other – Legal.pdf · uploaded 8 Jan 2025Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Glen Square Arcchitect certificatte _0001.pdf · uploaded 11 Jan 2025Source
  • 3 Other – LegalAnnexure A.pdf · uploaded 18 Jan 2025Source
  • 4 Other – LegalFormat A.pdf · uploaded 18 Jan 2025Source
  • 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameAnnexure A.pdf · uploaded 18 Jan 2025Source
  • 2 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFormat A.pdf · uploaded 18 Jan 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Glen Square Form 3 22-01-25 (1).pdf · uploaded 22 Mar 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)ASC Form 2.pdf · uploaded 22 Mar 2025Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)1 Declaration-cum-undertaking for change of bank account (Annexure A).pdf · uploaded 19 Apr 2025Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)UC Associates (2).pdf · uploaded 19 Apr 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)ASC (1).pdf · uploaded 19 Apr 2025Source
  • 1 Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)Glen Square RERA Bank letter (3).pdf · uploaded 19 Apr 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)GLEN SQUARE- FORM 3.pdf · uploaded 24 Apr 2025Source
  • 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameGlen Square declaration about separate bank account_0001.pdf · uploaded 24 Apr 2025Source
  • 1 Other – TechnicalGlen Square Format A declaration about rera designated bank acco_0001.pdf · uploaded 24 Apr 2025Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)Glen Square Engineers Certificate 23-24.pdf · uploaded 24 Apr 2025Source
  • 1 Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)Glen Square Annexure A declaration cum undertaking_0001.pdf · uploaded 24 Apr 2025Source
  • 1 Disclosure of sold/ booked inventorySOLD INVETORY LETTER.pdf · uploaded 27 May 2025Source
  • 1 Disclosure for secured/unsecured finance availed for the projectGlen Square Disclosure of Finance.pdf · uploaded 28 May 2025Source
  • 1 Copy of Layout Approval (in case of layout)REVISED SANCTION PLAN - 11-07-2025 - converted.pdf · uploaded 14 Jul 2025Source
  • 1 Commencement Certificates / NA Order for plotted developmentGLEN REVISED CC 11-07-2025 - converted.pdf · uploaded 14 Jul 2025Source
  • 1 Building Plan Approval / NA Order for plotted developmentREVISED SANCTION PLAN - 11-07-2025 - converted.pdf · uploaded 14 Jul 2025Source
  • 1 Declaration about Commencement CertificateGLEN REVISED CC 11-07-2025 - converted.pdf · uploaded 14 Jul 2025Source
  • 2 Declaration about Commencement Certificatedeclaration.pdf · uploaded 14 Jul 2025Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 - Glen Square.pdf · uploaded 18 Jul 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 - Glen Square.pdf · uploaded 18 Jul 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 - Glen Square.pdf · uploaded 18 Jul 2025Source
  • 1 Disclosure of sold/ booked inventoryGLEN - Disclosure of Sold and Unsold - Adhara.pdf · uploaded 18 Jul 2025Source
  • 2 Disclosure of sold/ booked inventoryGLEN - Disclosure of Sold and Unsold Ascella_30-06-2025.pdf · uploaded 18 Jul 2025Source
  • Form 1Form - 1 - Mar - 26.pdf · uploaded 30 Jun 2026Source
  • Form 2Form -2 Mar- 26.pdf · uploaded 30 Jun 2026Source
  • Form 3CA Certificate (2).pdf · uploaded 30 Jun 2026Source
  • Disclosure of Sold and Booked InventoryDisclosure Mar- 26.pdf · uploaded 30 Jun 2026Source
  • Withdrawal Update Form 1Glen Square - Form - 1 Q1-2026-27.pdf · uploaded 17 Sep 2026Source
  • Withdrawal Update Form 1Form 1 - Glen Square Sept 25.pdf · uploaded 17 Sep 2026Source
  • Withdrawal Update Form 1Glen Form1 - 2025-26 - Q3.pdf · uploaded 17 Sep 2026Source
  • Withdrawal Update Form 1Glen Square - Form - 1 Q1-2026-27.pdf · uploaded 17 Sep 2026Source
  • Withdrawal Update Form 2Form 2 - Glen Square.pdf · uploaded 17 Sep 2026Source
  • Withdrawal Update Form 2Form 2 - Glen Square Sept 25.pdf · uploaded 17 Sep 2026Source
  • Withdrawal Update Form 2form 2 - 2025-26 - Q3.pdf · uploaded 17 Sep 2026Source
  • Withdrawal Update Form 2Glen Square - Form 2 Q1-2026-27.pdf · uploaded 17 Sep 2026Source
  • Withdrawal Update Form 3Form 3 - Glen Square.pdf · uploaded 17 Sep 2026Source
  • Withdrawal Update Form 3Form 3 - Glen Square.pdf · uploaded 17 Sep 2026Source
  • Withdrawal Update Form 3Glen Form 3 - 2025-26 - Q3.pdf · uploaded 17 Sep 2026Source
  • Withdrawal Update Form 3Glen Square - Form - 3 Q1-2026-27.pdf · uploaded 17 Sep 2026Source
  • Form 2A (FY 2025-2026)Glen Sqaure Form 2A - 2025-2026-1.pdf · uploaded 17 Sep 2026Source

Technical

  • Document4 plan copy (2)_1.pdf · uploaded 30 Mar 2023Source
  • Document4 plan copy (2)_2.pdf · uploaded 30 Mar 2023Source
  • Document4 plan copy (2)_3.pdf · uploaded 30 Mar 2023Source
  • Document4 plan copy (2)_4.pdf · uploaded 30 Mar 2023Source
  • Document1.pdf · uploaded 30 Mar 2023Source
  • Document2.pdf · uploaded 30 Mar 2023Source
  • Document3.pdf · uploaded 30 Mar 2023Source
  • Document4 plan copy (2)_1.pdf · uploaded 30 Mar 2023Source
  • Document4 plan copy (2)_2.pdf · uploaded 30 Mar 2023Source
  • Document4 plan copy (2)_3.pdf · uploaded 30 Mar 2023Source
  • Document4 plan copy (2)_4.pdf · uploaded 30 Mar 2023Source
  • Document1.pdf · uploaded 30 Mar 2023Source
  • Document2.pdf · uploaded 30 Mar 2023Source
  • Document3.pdf · uploaded 30 Mar 2023Source
  • Other – TechnicalGlen Square Format A declaration about rera designated bank acco_0001.pdf · uploaded 24 Apr 2025Source
  • DocumentREVISED SANCTION PLAN - 11-07-2025 - converted.pdf · uploaded 14 Jul 2025Source
  • DocumentREVISED SANCTION PLAN - 11-07-2025 - converted.pdf · uploaded 14 Jul 2025Source

Technical (Architect)

  • DocumentGlen Square Architect certificate Form 1_0001.pdf · uploaded 4 Nov 2024Source
  • DocumentGlen Square Arcchitect certificatte _0001.pdf · uploaded 11 Jan 2025Source
  • Document1 Declaration-cum-undertaking for change of bank account (Annexure A).pdf · uploaded 19 Apr 2025Source
  • DocumentUC Associates (2).pdf · uploaded 19 Apr 2025Source
  • DocumentForm 1 - Glen Square.pdf · uploaded 18 Jul 2025Source
  • DocumentGlen Square - Form - 1 Q1-2026-27.pdf · uploaded 17 Sep 2026Source

Technical (Engineer)

  • DocumentGlen Square Engineers certificate Form 2_0001.pdf · uploaded 4 Nov 2024Source
  • DocumentASC Form 2.pdf · uploaded 22 Mar 2025Source
  • DocumentASC (1).pdf · uploaded 19 Apr 2025Source
  • DocumentForm 2 - Glen Square.pdf · uploaded 18 Jul 2025Source
  • DocumentGlen Square - Form 2 Q1-2026-27.pdf · uploaded 17 Sep 2026Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsLand parcel 01/B, 01/E

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
Unit types
1BHK, 2BHK, Alloted to mahada282 units in all
Address
Survey No 38 Hissa No 01/A, 01/B, 01/E, 01/F, 01/J, Survey No 58 Hissa No 2/2, 2/B Survey No 37 Hissa No 02 And Survey No 58 Hissa No 2/1/2 Village Nandivali Tarfe Panchanand Dombivli East 421204, Village Nandivali Targe Panchnand, P And T ColonyPIN 421204
Village
Dombivli, Kalyan taluka
Land area for this project
11,289 sq m (1,21,514 sq ft)
Permissible built-up area
27,750 sq m (2,98,698 sq ft)
Sanctioned built-up area
13,876 sq m (1,49,359 sq ft)
Recreational open space
804 sq m (8,657 sq ft)
Designated bank account
159
Developed in phases
Yes

Survey, CTS, gat or plot numbers

01/B01/E01/F01/J2/B SURVEY NO 37 HISSA NO 02SURVEY NO 38 HISSA NO 01/ASURVEY NO 58 HISSA NO 2/1/2SURVEY NO 58 HISSA NO 2/2

Land as published on MahaRERA's project page

SURVEY NO 38 HISSA NO 01/A, 01/B, 01/E, 01/F, 01/J, SURVEY NO 58 HISSA NO 2/2, 2/B SURVEY NO 37 HISSA NO 02 AND SURVEY NO 58 HISSA NO 2/1/2 VILLAGE NANDIVALI TARFE PANCHANAND DOMBIVLI EAST 421204

Boundaries

North
Road
South
58-2-3 Property
East
Janardan Palace
West
Road

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking282 units

89 of 282 units booked (32%), as the promoter reported to MahaRERA

1BHK · 186 units2BHK · 64 unitsAlloted to mahada · 32 units
BuildingTypeCarpet areaUnitsBooked
Adhara1BHK31.46 sq m · 339 sq ft162
Adhara1BHK37.63 sq m · 405 sq ft295
Adhara1BHK40.85 sq m · 440 sq ft162
Adhara1BHK40.95 sq m · 441 sq ft166
Adhara1BHK42.28 sq m · 455 sq ft162
Adhara2BHK54.43 sq m · 586 sq ft3214
AdharaAlloted to mahada31.46 sq m · 339 sq ft22
AdharaAlloted to mahada37.63 sq m · 405 sq ft44
Show all 24 unit rowsShow fewer unit rows
BuildingTypeCarpet areaUnitsBooked
AdharaAlloted to mahada40.85 sq m · 440 sq ft22
AdharaAlloted to mahada40.95 sq m · 441 sq ft22
AdharaAlloted to mahada42.28 sq m · 455 sq ft22
AdharaAlloted to mahada54.43 sq m · 586 sq ft44
Ascella1BHK31.46 sq m · 339 sq ft164
Ascella1BHK37.63 sq m · 405 sq ft295
Ascella1BHK40.85 sq m · 440 sq ft163
Ascella1BHK40.95 sq m · 441 sq ft162
Ascella1BHK42.28 sq m · 455 sq ft163
Ascella2BHK54.43 sq m · 586 sq ft329
AscellaAlloted to mahada31.46 sq m · 339 sq ft22
AscellaAlloted to mahada37.63 sq m · 405 sq ft44
AscellaAlloted to mahada40.85 sq m · 440 sq ft22
AscellaAlloted to mahada40.95 sq m · 441 sq ft22
AscellaAlloted to mahada42.28 sq m · 455 sq ft22
AscellaAlloted to mahada54.43 sq m · 586 sq ft44

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals5

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectUc Associates—
Chartered accountantH R Jain And Associates—
EngineerAssociated Structural Engioneers LLP—
EngineerDevendra Bharode—
Registered real estate agentAnil Puthran—

Source: MahaRERA project page. Contact details are not shown.

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Report a problemMethodology