Completion was pushed back 4 months, to Apr 2027; no MahaRERA orders on record; 67% of its units are booked.

Dahisar, Thane 400612 · by I G Builders

DeliveryExtended 4 moPromised Dec 2026 · now due Apr 2027RegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales67% booked91 of 136 units · as the promoter reported to MahaRERA

Buying a flat here?

See every deed registered on it.

Completion was pushed back 4 months, to Apr 2027

  • This projectRegistered 5 Aug 2017, completion promised 31 Dec 2026, revised to 30 Apr 2027.

No extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales first, then rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

6 buildings

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP51700003547
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P517000035475 Aug 201731 Dec 202630 Apr 2027I G BuildersProject page
Documents114

1 document held by Deedo, 113 filings listed on MahaRERA's project page

Registration certificate

Finance

  • PAN CardNew Doc 35_4.pdf · uploaded 28 Jul 2017Source

Legal

  • Legal Title reportNew Doc 2017-07-28.pdf · uploaded 28 Jul 2017Source
  • Declaration Form BNew Doc 35.pdf · uploaded 28 Jul 2017Source

Migrated

  • 1 PAN CardNew Doc 35_4.pdf · uploaded 28 Jul 2017Source
  • 1 Copy of the legal title reportNew Doc 2017-07-28.pdf · uploaded 28 Jul 2017Source
  • 1 Details of encumbrancesig encumbrance.pdf · uploaded 28 Jul 2017Source
  • 1 Copy of Layout Approval (in case of layout)compressed_compressed_HPSC3248 (2).pdf · uploaded 28 Jul 2017Source
Show all 114 documentsShow fewer documents

Migrated

  • 2 Copy of Layout Approval (in case of layout)HPSC3249.pdf · uploaded 28 Jul 2017Source
  • 3 Copy of Layout Approval (in case of layout)HPSC3251.pdf · uploaded 28 Jul 2017Source
  • 4 Copy of Layout Approval (in case of layout)HPSC3252.pdf · uploaded 28 Jul 2017Source
  • 5 Copy of Layout Approval (in case of layout)HPSC3253.pdf · uploaded 28 Jul 2017Source
  • 1 Building Plan Approval (IOD)ig cc.pdf · uploaded 28 Jul 2017Source
  • 1 Commencement Certificates / NA Order for plotted developmentig cc.pdf · uploaded 28 Jul 2017Source
  • 1 Declaration in FORM BNew Doc 35.pdf · uploaded 28 Jul 2017Source
  • 1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)RERA Low res.pdf · uploaded 28 Jul 2017Source
  • 1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)ig engineer 01.pdf · uploaded 28 Jul 2017Source
  • 1 Certificates of CA (Form 3)0488_001 (1).pdf · uploaded 28 Jul 2017Source
  • 1 Proforma of Allotment letterIG ALLOTMENT.pdf · uploaded 28 Jul 2017Source
  • 2 Proforma of Allotment letterDRAFT AGREEMENT.pdf · uploaded 28 Jul 2017Source
  • 1 Certificates of CA (Form 5)I G BUILDERS FORM 5.pdf · uploaded 29 Sep 2018Source
  • 2 Certificates of CA (Form 5)i g builders rera audit form 5.pdf · uploaded 28 Sep 2019Source
  • 2 Commencement Certificates / NA Order for plotted developmentAmended Cc.pdf · uploaded 20 Jun 2022Source
  • 1 Declaration about Commencement CertificateFORMAT D IG.pdf · uploaded 20 Jun 2022Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)2A 19-20.pdf · uploaded 20 Jun 2022Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)2A 20-21.pdf · uploaded 20 Jun 2022Source
  • 1 CERSAI detailsPlanet Homes.pdf · uploaded 20 Jun 2022Source
  • 1 Disclosure of sold/ booked inventory29 IG.pdf · uploaded 20 Jun 2022Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)Form 5 18-19 Planet.pdf · uploaded 20 Jun 2022Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)Form 5 Planet Homes FY 2019-20.pdf · uploaded 20 Jun 2022Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)Form 5 Planet Homes FY 2020-21.pdf · uploaded 20 Jun 2022Source
  • 6 Copy of Layout Approval (in case of layout)Plan 1.pdf · uploaded 19 Aug 2022Source
  • 7 Copy of Layout Approval (in case of layout)Plan 2.pdf · uploaded 19 Aug 2022Source
  • 8 Copy of Layout Approval (in case of layout)Plan 3.pdf · uploaded 19 Aug 2022Source
  • 9 Copy of Layout Approval (in case of layout)Plan 4.pdf · uploaded 19 Aug 2022Source
  • 2 Disclosure of sold/ booked inventory29 Planet Homes.pdf · uploaded 19 Aug 2022Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)Form 5_Planet Homes_FY 2021-22.pdf · uploaded 30 Sep 2022Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)IG FORM 5.pdf · uploaded 28 Sep 2023Source
  • 10 Copy of Layout Approval (in case of layout)B WING 5TH FLOOR REVISED CC plan 1_compressed.pdf · uploaded 7 Dec 2023Source
  • 11 Copy of Layout Approval (in case of layout)B WING 5TH FLOOR REVISED CC PLAN 2_compressed.pdf · uploaded 7 Dec 2023Source
  • 12 Copy of Layout Approval (in case of layout)B WING 5TH FLOOR REVISED CC PLAN 3_compressed.pdf · uploaded 7 Dec 2023Source
  • 3 Commencement Certificates / NA Order for plotted developmentB WING 5TH FLOOR REVISED CC.PDF · uploaded 7 Dec 2023Source
  • 2 Declaration about Commencement CertificateIG RERA DECLARATION.pdf · uploaded 7 Dec 2023Source
  • 2 Certificates of Architect (Form 1)(Mandatory for only ongoing project)IG ARCHITECT CERT.pdf · uploaded 24 Jan 2024Source
  • 2 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)IG BUILDER ENGINEER CERTIFICATE.pdf · uploaded 24 Jan 2024Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)IG FORM 2A.pdf · uploaded 24 Jan 2024Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)IG FORM 2A.pdf · uploaded 24 Jan 2024Source
  • 3 Disclosure of sold/ booked inventoryDISCLOSURE OF SOLD FLATS IG.pdf · uploaded 24 Jan 2024Source
  • 2 Certificates of CA (Form 3)IG FORM 3 DEC 23.pdf · uploaded 25 Jan 2024Source
  • 1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Q4Form1.pdf · uploaded 14 Apr 2025Source
  • 2 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Q1Form1.pdf · uploaded 14 Apr 2025Source
  • 3 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Q1Form1.pdf · uploaded 14 Apr 2025Source
  • 4 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Q3Form1.pdf · uploaded 14 Apr 2025Source
  • 1 Certificates of CA (Form 3)Q4Form3.pdf · uploaded 14 Apr 2025Source
  • 2 Certificates of CA (Form 3)Q1Form3.pdf · uploaded 14 Apr 2025Source
  • 3 Certificates of CA (Form 3)Q2Form3.pdf · uploaded 14 Apr 2025Source
  • 4 Certificates of CA (Form 3)Q3Form3.pdf · uploaded 14 Apr 2025Source
  • 1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Q4Form2.pdf · uploaded 14 Apr 2025Source
  • 2 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Q1Form2.pdf · uploaded 14 Apr 2025Source
  • 3 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Q2Form2.pdf · uploaded 14 Apr 2025Source
  • 4 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Q3Form2.pdf · uploaded 14 Apr 2025Source
  • 1 Disclosure of sold/ booked inventoryQ4Sold-Unsold.pdf · uploaded 14 Apr 2025Source
  • 2 Disclosure of sold/ booked inventoryQ3SoldUnsold.pdf · uploaded 14 Apr 2025Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)Form2A.pdf · uploaded 23 Apr 2025Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)Form5.pdf · uploaded 23 Apr 2025Source
  • Form 1Q4Form1.pdf · uploaded 21 Jun 2025Source
  • Form 2Q4Form2.pdf · uploaded 21 Jun 2025Source
  • Form 3Q4Form3.pdf · uploaded 21 Jun 2025Source
  • Disclosure of Sold and Booked InventorySoldUnsold.pdf · uploaded 21 Jun 2025Source
  • Form 1Q4Form1.pdf · uploaded 14 Aug 2025Source
  • Form 2Q4Form2.pdf · uploaded 14 Aug 2025Source
  • Form 3Q4Form3.pdf · uploaded 14 Aug 2025Source
  • Disclosure of Sold and Booked InventoryQ4Sold-Unsold.pdf · uploaded 14 Aug 2025Source
  • Form 1Q3Form1.pdf · uploaded 14 Aug 2025Source
  • Form 2Q3Form2.pdf · uploaded 14 Aug 2025Source
  • Form 3Q3Form3.pdf · uploaded 14 Aug 2025Source
  • Disclosure of Sold and Booked InventoryQ3SoldUnsold.pdf · uploaded 14 Aug 2025Source
  • Form 1Q2Form1.pdf · uploaded 14 Aug 2025Source
  • Form 2Q2Form2.pdf · uploaded 14 Aug 2025Source
  • Form 3Q2Form3.pdf · uploaded 14 Aug 2025Source
  • Disclosure of Sold and Booked InventorySoldUnsold.pdf · uploaded 14 Aug 2025Source
  • Form 1Q1Form1.pdf · uploaded 14 Aug 2025Source
  • Form 2Q1Form2.pdf · uploaded 14 Aug 2025Source
  • Form 3Q1Form3.pdf · uploaded 14 Aug 2025Source
  • Disclosure of Sold and Booked InventorySoldUnsold.pdf · uploaded 14 Aug 2025Source
  • Withdrawal Update Form 1FORM 1 30-06-2025 - converted.pdf · uploaded 27 Sep 2025Source
  • Withdrawal Update Form 2form 2 30-06-2025.pdf · uploaded 27 Sep 2025Source
  • Withdrawal Update Form 3FORM 3 IG 30-06-2025 - converted.pdf · uploaded 27 Sep 2025Source
  • Form 2A (FY 2023-2024)Form 2A 23-24.pdf · uploaded 11 Oct 2025Source
  • Form 2A (FY 2024-2025)Form 2A 24-25.pdf · uploaded 11 Oct 2025Source
  • Form 5 (FY 2023-2024)Form 5 23-24.pdf · uploaded 11 Oct 2025Source

Technical

  • Documentcompressed_compressed_HPSC3248 (2).pdf · uploaded 28 Jul 2017Source
  • DocumentHPSC3249.pdf · uploaded 28 Jul 2017Source
  • DocumentHPSC3251.pdf · uploaded 28 Jul 2017Source
  • DocumentHPSC3252.pdf · uploaded 28 Jul 2017Source
  • DocumentHPSC3253.pdf · uploaded 28 Jul 2017Source
  • Documentig cc.pdf · uploaded 28 Jul 2017Source
  • DocumentPlan 1.pdf · uploaded 19 Aug 2022Source
  • DocumentPlan 2.pdf · uploaded 19 Aug 2022Source
  • DocumentPlan 3.pdf · uploaded 19 Aug 2022Source
  • DocumentPlan 4.pdf · uploaded 19 Aug 2022Source
  • DocumentB WING 5TH FLOOR REVISED CC plan 1_compressed.pdf · uploaded 7 Dec 2023Source
  • DocumentB WING 5TH FLOOR REVISED CC PLAN 2_compressed.pdf · uploaded 7 Dec 2023Source
  • DocumentB WING 5TH FLOOR REVISED CC PLAN 3_compressed.pdf · uploaded 7 Dec 2023Source

Technical (Architect)

  • DocumentQ4Form1.pdf · uploaded 14 Apr 2025Source
  • DocumentQ1Form1.pdf · uploaded 14 Apr 2025Source
  • DocumentQ1Form1.pdf · uploaded 14 Apr 2025Source
  • DocumentQ3Form1.pdf · uploaded 14 Apr 2025Source
  • DocumentFORM 1 30-06-2025 - converted.pdf · uploaded 27 Sep 2025Source

Technical (Engineer)

  • DocumentQ4Form2.pdf · uploaded 14 Apr 2025Source
  • DocumentQ1Form2.pdf · uploaded 14 Apr 2025Source
  • DocumentQ2Form2.pdf · uploaded 14 Apr 2025Source
  • DocumentQ3Form2.pdf · uploaded 14 Apr 2025Source
  • Documentform 2 30-06-2025.pdf · uploaded 27 Sep 2025Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsLand parcel SURVEY NO 79 HISSA NO 1B

As registered with MahaRERA and published on its project page

Project type
Others
Status on MahaRERA
Certificate Signed
Unit types
—136 units in all
Address
SURVEY NO 79 HISSA NO 1B, Dahisar, DahisarPIN 400612
Village
Dahisar, Thane taluka
Land area for this project
3,000 sq m (32,296 sq ft)
Permissible built-up area
5,161 sq m (55,548 sq ft)
Sanctioned built-up area
4,661 sq m (50,166 sq ft)
Recreational open space
301 sq m (3,244 sq ft)
Designated bank account
98
Developed in phases
Yes

Survey, CTS, gat or plot numbers

SURVEY NO 79 HISSA NO 1B

Land as published on MahaRERA's project page

SURVEY NO 79 HISSA NO 1B

Boundaries

North
Old Survey No 351
South
Survey No 79 Hissa No 2
East
Existing 6 Meter Proposed 12 Meter Road
West
Survey No 79 Hissa No 1a

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking136 units

136 units registered

— · 136 units
BuildingTypeCarpet areaUnits
Planet Homes Building No 1 A Wing——32
Planet Homes Building No 1 B Wing——38
Planet Homes B Wing——30
Planet Homes C Wing——12
Planet Homes D Wing——12
Planet Homes E Wing——12

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.