Ritzenia

Completion due Dec 2031

Chikanghar, Thane 421301 |Promoter: Vikas Developer

18 Jun 2026Registered with MahaRERAFirst of 3 registrations
31 Dec 2031Promised completionLatest across registrations
3Buildings3 phases
531Units registered
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA

RERA registrations
3
Phases
3
Buildings
3

Location

Coordinates as published by MahaRERA

View on OpenStreetMap 19.24674, 73.15193
Ritzenia is at latitude 19.24674, longitude 73.15193.

Also registered as

Ritzenia Tower CRitzenia Tower ARitzenia Tower B
MahaRERA's project page hasn't been imported for this project yet.

Unit mix, parking, construction progress and the project's professionals come from that page. You can open it on MahaRERA (it asks for a CAPTCHA).

Latest registered deals

No registered transactions matched to this project yetSales, resales and rentals appear here once registered documents from authorised IGR feeds are matched to this project.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion promised for 31 Dec 2029

PC1331012600853
Registered
18 Jun 2026
Promised
31 Dec 2029

Completion promised for 31 Dec 2030

PM1331012601103
Registered
8 Jul 2026
Promised
31 Dec 2030

Completion promised for 31 Dec 2031

PM1332022602016
Registered
23 Sep 2026
Promised
31 Dec 2031

3 RERA registrations

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
PC133101260085318 Jun 202631 Dec 2029—Vikas DeveloperProject page
PM13310126011038 Jul 202631 Dec 2030—Vikas DeveloperProject page
PM133202260201623 Sep 202631 Dec 2031—Vikas DeveloperProject page

3 buildings

Buildings and wings named in the registration

BuildingSanctioned floorsFloors with CCUnits
Bldg Type A1212253
Bldg Type B1313217
Bldg Type - C5561

Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.

Documents

3 documents held by Deedo

Registration certificates

  • Registration certificatePC1331012600853 · 18 Jun 2026ViewSource
  • Registration certificatePM1331012601103 · 8 Jul 2026ViewSource
  • Registration certificatePM1332022602016 · 23 Sep 2026ViewSource

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Chikanghar

Survey, CTS, gat or plot numbers

31/3 NewSurvey No. 31(Pt) Old

Source: registration certificates, as stated there.