Tanisha
Its promised completion date, Sep 2024, has passed and MahaRERA does not show it completed; no MahaRERA orders on record; 65% of its units are booked.
Badlapur (M Cl), Thane 421503 · Promoter: Tanisha Enterprises
Its promised completion date, Sep 2024, has passed and MahaRERA does not show it completed
- This projectRegistered 29 Jan 2022, completion promised 30 Sep 2024, and still not shown completed today.
No extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales, rentals and mortgages matched to this project · the free view shows a price band
4 buildings
Open a building to see every flat, floor by floor.
- Tanisha Wing A6 floors · 32 units63% booked
- Tanisha Wing B6 floors · 18 units72% booked
- Tanisha Wing C6 floors · 18 units72% booked
- Tanisha Wing D6 floors · 14 units50% booked
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationP51700032792
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P51700032792 | 29 Jan 2022 | 30 Sep 2024 | 30 Sep 2024 | Tanisha Enterprises | Project page |
Documents43
1 document held by Deedo, 42 filings listed on MahaRERA's project page
Finance
- PAN CardTanisha PAN.pdf · uploaded 20 Dec 2021Source
Legal
- Legal Title reportTanisha Title.pdf · uploaded 12 Dec 2021Source
- Declaration Form BForm B Affidavit cum Declearation.pdf · uploaded 17 Dec 2021Source
- Legal Title reportTanisha Title.pdf · uploaded 27 Dec 2021Source
- Legal Title reportTanisha Legal Title Report.pdf · uploaded 3 Jan 2022Source
- Legal Title reportLegal Title Report_Upload_Final.pdf · uploaded 17 Jan 2022Source
Migrated
- 1 Copy of the legal title reportTanisha Title.pdf · uploaded 12 Dec 2021Source
Show all 43 documentsShow fewer documents
Migrated
- 1 Details of encumbrancesLetter No Encumbrance.pdf · uploaded 12 Dec 2021Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architechts Certificate compressed.pdf · uploaded 12 Dec 2021Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineers Certificate compressed.pdf · uploaded 12 Dec 2021Source
- 1 Proforma of Allotment letterAgreement for Sale.pdf · uploaded 12 Dec 2021Source
- 1 Declaration about Commencement CertificateCommencement Declaration.pdf · uploaded 17 Dec 2021Source
- 1 Declaration in FORM BForm B Affidavit cum Declearation.pdf · uploaded 17 Dec 2021Source
- 1 CERSAI detailsDeclaration regarding CERSAI.pdf · uploaded 17 Dec 2021Source
- 1 PAN CardTanisha PAN.pdf · uploaded 20 Dec 2021Source
- 1 Copy of Layout Approval (in case of layout)Tanisha Plan compressed.pdf · uploaded 20 Dec 2021Source
- 1 Building Plan Approval / NA Order for plotted developmentTanisha Plan compressed.pdf · uploaded 20 Dec 2021Source
- 1 Commencement Certificates / NA Order for plotted developmentCommencement Certificate compressed.pdf · uploaded 20 Dec 2021Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3.pdf · uploaded 20 Dec 2021Source
- 2 Copy of the legal title reportTanisha Title.pdf · uploaded 27 Dec 2021Source
- 2 Copy of Layout Approval (in case of layout)Tanisha Plan 2.pdf · uploaded 27 Dec 2021Source
- 2 CERSAI details1 CERSAI details.pdf · uploaded 27 Dec 2021Source
- 2 Proforma of Allotment letterAllotment Letter.pdf · uploaded 27 Dec 2021Source
- 3 Copy of the legal title reportTanisha Legal Title Report.pdf · uploaded 3 Jan 2022Source
- 3 Copy of Layout Approval (in case of layout)Tanisha Plan 2.pdf · uploaded 3 Jan 2022Source
- 3 CERSAI details1 CERSAI details.pdf · uploaded 3 Jan 2022Source
- 3 Proforma of Allotment letterAgreement for Sale.pdf · uploaded 3 Jan 2022Source
- 4 Proforma of Allotment letterAllotment Letter.pdf · uploaded 3 Jan 2022Source
- 4 Copy of the legal title reportLegal Title Report_Upload_Final.pdf · uploaded 17 Jan 2022Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)FORM 5.pdf · uploaded 3 Feb 2023Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)New Engineer's Certificate.pdf · uploaded 10 Aug 2023Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3_310323.pdf · uploaded 10 Aug 2023Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect certificate.pdf · uploaded 25 Aug 2023Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)Form 5 CA certificate.pdf · uploaded 25 Aug 2023Source
- 1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted development13023_signed Shreedhar Patil - OC.pdf · uploaded 25 Aug 2023Source
- 1 Architect’s Certificate on Completion of Project (Form 4)Form 4 (2).pdf · uploaded 25 Aug 2023Source
Technical
Technical (Architect)
- DocumentArchitect certificate.pdf · uploaded 25 Aug 2023Source
Technical (Engineer)
- DocumentNew Engineer's Certificate.pdf · uploaded 10 Aug 2023Source
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvalsGut No 29 Hissa No 2
As registered with MahaRERA and published on its project page
- Project type
- Residential / Group Housing
- Status on MahaRERA
- Certificate Signed
- Unit types
- 1BHK, 1RK, 2BHK82 units in all
- Address
- Gut No 29 Hissa No 2, ManjarliPIN 421503
- Village
- Badlapur (M Cl), Ambarnath taluka
- Designated bank account
- 76
- Developed in phases
- Yes
Survey, CTS, gat or plot numbers
Boundaries
- North
- Adjoining Gut No 31 Land
- South
- Adjoining Gut No 31 Land
- East
- Adjoining 6 Meter Wide Road
- West
- Adjoining Gut No 31 Land
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking82 units
53 of 82 units booked (65%), as the promoter reported to MahaRERA
| Building | Type | Carpet area | Units | Booked |
|---|---|---|---|---|
| Tanisha Wing A | 1BHK | 37 sq m · 398 sq ft | 1 | 1 |
| Tanisha Wing A | 1BHK | 37.48 sq m · 403 sq ft | 1 | 1 |
| Tanisha Wing A | 1BHK | 39.24 sq m · 422 sq ft | 1 | 1 |
| Tanisha Wing A | 1BHK | 39.73 sq m · 428 sq ft | 1 | 1 |
| Tanisha Wing A | 1BHK | 40.6 sq m · 437 sq ft | 2 | 1 |
| Tanisha Wing A | 1BHK | 40.7 sq m · 438 sq ft | 4 | 3 |
| Tanisha Wing A | 1BHK | 40.78 sq m · 439 sq ft | 2 | 0 |
| Tanisha Wing A | 1BHK | 41.39 sq m · 446 sq ft | 2 | 2 |
Show all 32 unit rowsShow fewer unit rows
| Building | Type | Carpet area | Units | Booked |
|---|---|---|---|---|
| Tanisha Wing A | 1BHK | 42.96 sq m · 462 sq ft | 2 | 1 |
| Tanisha Wing A | 1BHK | 43.04 sq m · 463 sq ft | 2 | 0 |
| Tanisha Wing A | 1BHK | 43.11 sq m · 464 sq ft | 2 | 1 |
| Tanisha Wing A | 1BHK | 43.13 sq m · 464 sq ft | 2 | 1 |
| Tanisha Wing A | 1BHK | 43.44 sq m · 468 sq ft | 2 | 1 |
| Tanisha Wing A | 1BHK | 44.23 sq m · 476 sq ft | 2 | 1 |
| Tanisha Wing A | 1BHK | 44.57 sq m · 480 sq ft | 2 | 2 |
| Tanisha Wing A | 1BHK | 45.39 sq m · 489 sq ft | 2 | 2 |
| Tanisha Wing A | 1BHK | 47.95 sq m · 516 sq ft | 2 | 1 |
| Tanisha Wing B | 1BHK | 39.24 sq m · 422 sq ft | 1 | 0 |
| Tanisha Wing B | 1BHK | 40.78 sq m · 439 sq ft | 8 | 5 |
| Tanisha Wing B | 1BHK | 43.04 sq m · 463 sq ft | 8 | 8 |
| Tanisha Wing B | 1RK | 26.21 sq m · 282 sq ft | 1 | 0 |
| Tanisha Wing C | 1BHK | 36.99 sq m · 398 sq ft | 1 | 0 |
| Tanisha Wing C | 1BHK | 40.78 sq m · 439 sq ft | 6 | 4 |
| Tanisha Wing C | 1BHK | 43.04 sq m · 463 sq ft | 6 | 5 |
| Tanisha Wing C | 1RK | 26.21 sq m · 282 sq ft | 1 | 0 |
| Tanisha Wing C | 2BHK | 58.72 sq m · 632 sq ft | 2 | 2 |
| Tanisha Wing C | 2BHK | 61.32 sq m · 660 sq ft | 2 | 2 |
| Tanisha Wing D | 1BHK | 38.04 sq m · 409 sq ft | 1 | 0 |
| Tanisha Wing D | 1BHK | 40.26 sq m · 433 sq ft | 8 | 3 |
| Tanisha Wing D | 2BHK | 54.82 sq m · 590 sq ft | 1 | 0 |
| Tanisha Wing D | 2BHK | 56.64 sq m · 610 sq ft | 2 | 2 |
| Tanisha Wing D | 2BHK | 59.53 sq m · 641 sq ft | 2 | 2 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Professionals3
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Raj Associates | — |
| Chartered accountant | Ambekar Shelar Karve & Ambardekar Chartered Accountants | — |
| Engineer | Atul Kudtarkar & Associates | — |
Source: MahaRERA project page. Contact details are not shown.