Shreeji Nx
Completion was pushed back 4 months, to Apr 2027; no MahaRERA orders on record; 16% of its units are booked.
Badlapur (M Cl), Thane 421503 · Promoter: Shubh Builders
Completion was pushed back 4 months, to Apr 2027
- This projectRegistered 15 Feb 2024, completion promised 31 Dec 2026, revised to 30 Apr 2027.
No extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales, rentals and mortgages matched to this project · the free view shows a price band
The building
Open a building to see every flat, floor by floor.
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationP51700054882
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P51700054882 | 15 Feb 2024 | 31 Dec 2026 | 30 Apr 2027 | Shubh Builders | Project page |
Documents64
1 document held by Deedo, 63 filings listed on MahaRERA's project page
Legal
Migrated
- 1 PAN Card1 Pancard Shubh Builders.pdf · uploaded 18 Jan 2024Source
- 1 Copy of the legal title reportShubh Builders Title Report FINAL.pdf · uploaded 18 Jan 2024Source
- 1 a Details of encumbrances concerned to FinanceNo Encumbrance Certificate.pdf · uploaded 18 Jan 2024Source
- 1 b Details of encumbrances concerned to LegalNo Encumbrance Certificate.pdf · uploaded 18 Jan 2024Source
- 1 Commencement Certificates / NA Order for plotted developmentCommencement Certificate.pdf · uploaded 18 Jan 2024Source
Show all 64 documentsShow fewer documents
Migrated
- 1 Declaration about Commencement CertificateForm D.pdf · uploaded 18 Jan 2024Source
- 1 Declaration in FORM BFORM B PARTNER.pdf · uploaded 18 Jan 2024Source
- 1 CERSAI detailsCersai Declaration.pdf · uploaded 18 Jan 2024Source
- 1 Disclosure of Interest in Other Real Estate Organizations2 Annexure A Janardan Lahu Dayare.pdf · uploaded 18 Jan 2024Source
- 2 Disclosure of Interest in Other Real Estate Organizations3 Annexure A Nilesh Karale.pdf · uploaded 18 Jan 2024Source
- 3 Disclosure of Interest in Other Real Estate Organizations4 Annexure A Ambrushi kale.pdf · uploaded 18 Jan 2024Source
- 4 Disclosure of Interest in Other Real Estate Organizations5 Annexure A Chandrakant Mhaskar.pdf · uploaded 18 Jan 2024Source
- 1 Proforma of Allotment letterAllotment Letter_11zon.pdf · uploaded 18 Jan 2024Source
- 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameBank Account Declaration.pdf · uploaded 18 Jan 2024Source
- 1 Deviation Report with respect to model copy of AgreementNo Deviation Wrt Agreement.pdf · uploaded 18 Jan 2024Source
- 1 Copy of Layout Approval (in case of layout)LAYOUT.pdf · uploaded 22 Jan 2024Source
- 1 Building Plan Approval / NA Order for plotted developmentLAYOUT.pdf · uploaded 22 Jan 2024Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)shubh builder Architect certificate.pdf · uploaded 22 Jan 2024Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)ENGG CERT.pdf · uploaded 22 Jan 2024Source
- 2 CERSAI detailsCERSAI_Search_Report_200294303553_For_Asset_Based_Search_22_01_2024_14_08_26_110.pdf · uploaded 22 Jan 2024Source
- 5 Disclosure of Interest in Other Real Estate Organizations1 Annexure A Vishnu Kondilkar.pdf · uploaded 22 Jan 2024Source
- 6 Disclosure of Interest in Other Real Estate Organizations6 Annexure A Umesh Sonawane.pdf · uploaded 22 Jan 2024Source
- 7 Disclosure of Interest in Other Real Estate Organizations7 Annexure A Ashish Jamdare.pdf · uploaded 22 Jan 2024Source
- 1 Proforma of Agreement for saleAFS.pdf · uploaded 22 Jan 2024Source
- 1 Deviation Report with respect to Allotment letterNo Deviation Allotment.pdf · uploaded 22 Jan 2024Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 Shubh Builders.pdf · uploaded 23 Jan 2024Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.pdf · uploaded 21 Nov 2024Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2.pdf · uploaded 21 Nov 2024Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)signed-Form 5 Shubh Builders.pdf · uploaded 29 Nov 2024Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 Shubh builders (Manas enterprises) Architech Certificate.pdf · uploaded 9 Jan 2025Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Shubh builders (Manas enterprises) Engineer Certificate.pdf · uploaded 9 Jan 2025Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 Architect Certifiacte Q4.pdf · uploaded 17 Apr 2025Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Engineer Certificate Q4.pdf · uploaded 17 Apr 2025Source
- Withdrawal Update Form 1Form 1.pdf · uploaded 19 Jul 2025Source
- Withdrawal Update Form 2Form 2.pdf · uploaded 19 Jul 2025Source
- Withdrawal Update Form 31 CA Certificate on Project Cost & Fund withdrawal (Form 3) (2).pdf · uploaded 19 Jul 2025Source
- Form 5 (FY 2024-2025)Form Shubh Builders Signed.pdf · uploaded 27 Sep 2025Source
- Withdrawal Update Form 1Form 1 Q2 Shubh Builders.pdf · uploaded 20 Jan 2026Source
- Withdrawal Update Form 2Form 2 Q2 Shubh Builders.pdf · uploaded 20 Jan 2026Source
- Withdrawal Update Form 31 CA Certificate on Project Cost & Fund withdrawal (Form 3) (2).pdf · uploaded 20 Jan 2026Source
- Withdrawal Update Form 1Form 1 Shubh Builders Q3.pdf · uploaded 27 Mar 2026Source
- Withdrawal Update Form 2Form 2 Shubh Builders Q3.pdf · uploaded 27 Mar 2026Source
- Withdrawal Update Form 3Form 3 Shubh Builders.pdf · uploaded 27 Mar 2026Source
- Withdrawal Update Form 1Manas Ent Form 1.pdf · uploaded 20 Apr 2026Source
- Withdrawal Update Form 2Manas Ent Form 2.pdf · uploaded 20 Apr 2026Source
- Withdrawal Update Form 3Form 3 Shubh Builders.pdf · uploaded 20 Apr 2026Source
- Withdrawal Update Form 1Form 1.pdf · uploaded 20 Jul 2026Source
- Withdrawal Update Form 2Form 2.pdf · uploaded 20 Jul 2026Source
- Withdrawal Update Form 3Form 3 Shubh Builders Q1 FY 26-27.pdf · uploaded 20 Jul 2026Source
- Form 5 (FY 2025-2026)Form 5 Signed Shubh Builders.pdf · uploaded 29 Sep 2026Source
- Withdrawal Update Form 1Form 1.pdf · uploaded 7 Oct 2026Source
- Withdrawal Update Form 2Form 2.pdf · uploaded 7 Oct 2026Source
- Withdrawal Update Form 3Form 3 Shubh Builders Q1 FY 26-27.pdf · uploaded 7 Oct 2026Source
Technical (Architect)
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvalsGut No 87, Hissa No 1
As registered with MahaRERA and published on its project page
- Project type
- Others
- Status on MahaRERA
- Certificate Signed
- Unit types
- 1BHK, 2BHK, Shop45 units in all
- Address
- Gut No 87, Hissa No 1, Gut No 87, Hissa No 1, At Village - Valivali, Taluka Ambernath, BadlapurPIN 421503
- Village
- Badlapur (M Cl), Ambarnath taluka
- Location
- 19.18212, 73.23914
- Designated bank account
- 76
- Developed in phases
- No
Survey, CTS, gat or plot numbers
Boundaries
- North
- Sant Birambhai Maharaj Hall
- South
- Gut No 86
- East
- Gut No 95 and 87-2
- West
- Nana Amrita Vaidya Hospital
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking45 units
7 of 45 units booked (16%), as the promoter reported to MahaRERA
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 1BHK | 30.11 sq m · 324 sq ft | 7 | 0 |
| 1BHK | 33 sq m · 355 sq ft | 7 | 1 |
| 1BHK | 36.27 sq m · 390 sq ft | 7 | 0 |
| 2BHK | 45.28 sq m · 487 sq ft | 7 | 0 |
| 2BHK | 50.02 sq m · 538 sq ft | 7 | 0 |
| Shop | 11.27 sq m · 121 sq ft | 1 | 1 |
| Shop | 11.5 sq m · 124 sq ft | 1 | 0 |
| Shop | 11.84 sq m · 127 sq ft | 2 | 2 |
Show all 12 unit rowsShow fewer unit rows
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| Shop | 13.75 sq m · 148 sq ft | 2 | 0 |
| Shop | 13.93 sq m · 150 sq ft | 1 | 0 |
| Shop | 14.16 sq m · 152 sq ft | 2 | 2 |
| Shop | 14.67 sq m · 158 sq ft | 1 | 1 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Professionals1
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | RAJ ASSOCIATES S R Khambayat | — |
Source: MahaRERA project page. Contact details are not shown.