Shivam Complex Wing D And E

Deedo IDDP-THN-RBK0

Its promised completion date, Sep 2018, has passed and MahaRERA does not show it completed; no MahaRERA orders on record; 51% of its units are booked.

Badlapur (M Cl), Thane 421503 · Promoter: Umiya Enterprises

Delivery8 yrs 1 mo past duePromised Sep 2018 · no extension on record · not shown completedRegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales51% booked31 of 61 units · as the promoter reported to MahaRERA
Shivam Complex Wing D And E project report cardPDF: delivery, regulatory orders, people on record, every tower and the registered deals — for your bank or lawyerSee what's inside · from ₹1,499

Its promised completion date, Sep 2018, has passed and MahaRERA does not show it completed

  • This projectRegistered 9 Aug 2017, completion promised 30 Sep 2018, and still not shown completed today.

No extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales, rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

2 buildings

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP51700005023
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P517000050239 Aug 201730 Sep 201830 Sep 2018Umiya EnterprisesProject page
Documents24

1 document held by Deedo, 23 filings listed on MahaRERA's project page

Registration certificate

Legal

  • Declaration Form BForm B.pdf · uploaded 28 Jul 2017Source
  • Legal Title reportTitle cert.pdf · uploaded 28 Jul 2017Source
  • OtherOC.pdf · uploaded 25 Sep 2019Source

Migrated

  • 1 Copy of the legal title reportTitle cert.pdf · uploaded 28 Jul 2017Source
  • 1 Details of encumbrancesEncumbrances.pdf · uploaded 28 Jul 2017Source
  • 1 Copy of Layout Approval (in case of layout)Senction Plan.pdf · uploaded 28 Jul 2017Source
  • 1 Building Plan Approval (IOD)IOD.PDF · uploaded 28 Jul 2017Source
Show all 24 documentsShow fewer documents

Migrated

  • 1 Declaration in FORM BForm B.pdf · uploaded 28 Jul 2017Source
  • 1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Arch Certificate.PDF · uploaded 28 Jul 2017Source
  • 1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Engineer.pdf · uploaded 28 Jul 2017Source
  • 1 Certificates of CA (Form 3)CA Letter comp.pdf · uploaded 28 Jul 2017Source
  • 1 Proforma of Allotment letterUmiya Sales.pdf · uploaded 28 Jul 2017Source
  • 1 Certificates of CA (Form 5)Form 5 CA Letter.pdf · uploaded 12 Oct 2018Source
  • 2 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Architeck Certi.pdf · uploaded 25 Sep 2019Source
  • 1 OtherOC.pdf · uploaded 25 Sep 2019Source
  • 2 Certificates of CA (Form 5)umiya enterprises rara 2019.PDF · uploaded 28 Sep 2019Source
  • 1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentOC-converted.pdf · uploaded 4 Aug 2021Source
  • 2 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentArchiteck Certi.pdf · uploaded 4 Aug 2021Source
  • 2 Architect’s Certificate on Completion of Project (Form 4)Architeck Certi.pdf · uploaded 4 Aug 2021Source

Technical

  • DocumentIOD.PDF · uploaded 28 Jul 2017Source
  • DocumentSenction Plan.pdf · uploaded 28 Jul 2017Source

Technical (Architect)

  • DocumentArchiteck Certi.pdf · uploaded 25 Sep 2019Source

Technical (Engineer)

  • DocumentEngineer.pdf · uploaded 28 Jul 2017Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsS NO 105A H NO 22P

As registered with MahaRERA and published on its project page

Project type
Others
Status on MahaRERA
Certificate Signed
Unit types
1 BHK, 1 RK, 2BHK, 1BHK, 1RK, Shop61 units in all
Address
S No 105a H No 22pPIN 421503
Village
Badlapur (M Cl), Ambarnath taluka
Designated bank account
212
Developed in phases
Yes

Survey, CTS, gat or plot numbers

S NO 105A H NO 22P

Boundaries

North
S No 105a H No 21 Land
South
S No 105a H No 23 Land
East
S No 105a H No 22p Land
West
9 Meter Road

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking61 units

31 of 61 units booked (51%), as the promoter reported to MahaRERA

1 BHK · 14 units1 RK · 1 unit2BHK · 9 units1BHK · 22 units1RK · 6 unitsShop · 9 units
BuildingTypeCarpet areaUnitsBooked
D Wing1 BHK26.93 sq m · 290 sq ft1414
D Wing1 RK18.97 sq m · 204 sq ft11
D Wing2BHK40.21 sq m · 433 sq ft55
E Wing1BHK26.77 sq m · 288 sq ft127
E Wing1BHK27.31 sq m · 294 sq ft40
E Wing1BHK27.83 sq m · 300 sq ft50
E Wing1BHK32.7 sq m · 352 sq ft10
E Wing1RK19.24 sq m · 207 sq ft10
Show all 15 unit rowsShow fewer unit rows
BuildingTypeCarpet areaUnitsBooked
E Wing1RK21.19 sq m · 228 sq ft52
E Wing2BHK41.29 sq m · 444 sq ft42
E WingShop7.97 sq m · 86 sq ft10
E WingShop9.17 sq m · 99 sq ft10
E WingShop9.92 sq m · 107 sq ft20
E WingShop10.17 sq m · 109 sq ft10
E WingShop12.66 sq m · 136 sq ft40

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals1

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectRaj Associates—

Source: MahaRERA project page. Contact details are not shown.