Promised date passed7 floors · 40 flatsRERA P51700050763
Main building, P G Harmony
Deedo IDDP-THN-ER8C-G21 flats have a sale on record, 0 are booked without a sale deed yet and 19 are unsold, per MahaRERA's Oct 2026 disclosure and the registered deeds.
Median saleNot on recordneeds 3 or more sales
Booked53%21 of 40 · Oct 2026
Completion30 Jun 2026as registered
Every flat, floor by floor
Tap a flat to see its record.
- Sale registered
- Unsold
010203040506
Fl 7
Fl 6
Fl 5
Fl 4
Fl 3
Fl 2
Fl 1
Fl G
1 BHK1 BHK1 BHK1 BHK
Sale status from MahaRERA's Oct 2026 disclosure; deeds from IGR Index II, placed on a flat only when the deed names this tower and flat. “Listed by developer” comes from the developer and is labelled as such.
SelectedUnsold
Flat Flat No. 101
1 BHK · 319 sq ft · floor 1
- Deeds
- 0
- Last activity
- None on record
- Last sale
- None registered
Units & parking in Main building
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 1BHK | 29.7 m² (319 sq.ft) | 7 | 1 |
| 1BHK | 32.7 m² (352 sq.ft) | 10 | 4 |
| 1BHK | 34.4 m² (370 sq.ft) | 7 | 3 |
| 1BHK | 35.1 m² (377 sq.ft) | 4 | 2 |
| 1BHK | 35.5 m² (382 sq.ft) | 5 | 1 |
| 1BHK | 36.6 m² (393 sq.ft) | 1 | 0 |
| 2BHK | 47.1 m² (507 sq.ft) | 3 | 0 |
| 3BHK | 66.1 m² (711 sq.ft) | 1 | 0 |
| Library | 84.2 m² (906 sq.ft) | 1 | 0 |
| Town Hall | 86.3 m² (929 sq.ft) | 1 | 0 |
| Town Hall | 176.7 m² (1,902 sq.ft) | 1 | 0 |
As registered with MahaRERA
- RERA registration
- P51700050763 · registered 3 May 2023
- Promised completion
- 30 Jun 2026
- Revised completion
- 30 Jun 2026
- Sanctioned habitable floors
- 7
- Building
- P G HARMONY
- Sanctioned floors (incl. basement, stilt, podium)
- 8
- Units declared
- 41
- Homes
- 38
- Shops and offices
- 3
- Sanctioned FSI area (sq m)
- 7
- MahaRERA status
- Certificate Signed
- Deedo ID
- Deedo IDDP-THN-ER8C-G
Questions about Main building
How many flats in Main building are sold?
21 flats have a sale on record, 0 are booked without a sale deed yet and 19 are unsold, per MahaRERA's Oct 2026 disclosure and the registered deeds.
When is Main building due for completion?
The MahaRERA registration promises 30 Jun 2026.
How many floors does Main building have?
7 sanctioned habitable floors, as registered with MahaRERA.
Data through13 Oct 2026SourcesMahaRERA registration and project page · IGR Maharashtra Index IIFloors and units are as registered; a promoter can revise them in later filings. Party names appear only inside an unlocked Index II.Methodology