Om Aditya
Deedo IDDP-THN-Q3T4Completion was pushed back 10 months to May 2023, and that date has passed too; no MahaRERA orders on record; 49% of its units are booked.
Badlapur (M Cl), Thane 421503 · Promoter: Suresh Keshavrao Yashvantrao
Completion was pushed back 10 months to May 2023, and that date has passed too
- This projectRegistered 4 Jun 2021, completion promised 31 Jul 2022, revised to 31 May 2023, and still not shown completed today.
1 extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales, rentals and mortgages matched to this project · the free view shows a price band
The building
Open a building to see every flat, floor by floor.
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationP51700029570
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P51700029570 | 4 Jun 2021 | 31 Jul 2022 | 31 May 2023 | Suresh Keshavrao Yashvantrao | Project page |
Documents43
2 documents held by Deedo, 41 filings listed on MahaRERA's project page
Finance
- PAN Cardpan card.pdf · uploaded 17 Feb 2020Source
Legal
- Declaration Form BfORM B_compressed.pdf · uploaded 24 Mar 2021Source
- Legal Title reportLegal Tilte Report.pdf · uploaded 2 Apr 2021Source
- OtherPOWER OF ATTORNEY.pdf · uploaded 7 Apr 2021Source
- Legal Title reportLegal Title Report (3).pdf · uploaded 14 May 2021Source
- Legal Title reportDevelopment Agreement.pdf · uploaded 14 May 2021Source
Show all 43 documentsShow fewer documents
Migrated
- 1 PAN Cardpan card.pdf · uploaded 17 Feb 2020Source
- 1 Commencement Certificates / NA Order for plotted developmentCommencement certificate.pdf · uploaded 17 Feb 2020Source
- 1 Details of encumbrancesNON ENCUMBERANCE.pdf · uploaded 24 Mar 2021Source
- 1 Copy of Layout Approval (in case of layout)fLOOR WISE PLAN_compressed.pdf · uploaded 24 Mar 2021Source
- 1 Building Plan Approval / NA Order for plotted developmentBlue Print (1).pdf · uploaded 24 Mar 2021Source
- 1 Declaration in FORM BfORM B_compressed.pdf · uploaded 24 Mar 2021Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)ca fORM b_compressed.pdf · uploaded 24 Mar 2021Source
- 1 Proforma of Allotment letteraLLOTMENT lATTER_compressed.pdf · uploaded 24 Mar 2021Source
- 1 Copy of the legal title reportLegal Tilte Report.pdf · uploaded 2 Apr 2021Source
- 2 Commencement Certificates / NA Order for plotted developmentClarification letter.pdf · uploaded 2 Apr 2021Source
- 3 Commencement Certificates / NA Order for plotted developmentDevelopment Agreement.pdf · uploaded 2 Apr 2021Source
- 2 Proforma of Allotment letterAgreement for Sale.pdf · uploaded 2 Apr 2021Source
- 2 Copy of Layout Approval (in case of layout)Clarification letter.pdf · uploaded 3 Apr 2021Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)ARCHITECT CERTIFICATE.pdf · uploaded 3 Apr 2021Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)ENGINEER CERTIFICATE.pdf · uploaded 3 Apr 2021Source
- 4 Commencement Certificates / NA Order for plotted developmentCopy of CC.pdf · uploaded 7 Apr 2021Source
- 1 OtherPOWER OF ATTORNEY.pdf · uploaded 7 Apr 2021Source
- 2 Copy of the legal title reportLegal Title Report (3).pdf · uploaded 14 May 2021Source
- 3 Copy of the legal title reportDevelopment Agreement.pdf · uploaded 14 May 2021Source
- 1 CERSAI detailsCERSAI REPORT.pdf · uploaded 2 Jun 2022Source
- 1 Declaration about Commencement CertificateDeclaration of CC.pdf · uploaded 19 Jul 2022Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)Form 2A 30 6 21.pdf · uploaded 19 Jul 2022Source
- 2 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)FORM 2A 30 09 21.pdf · uploaded 19 Jul 2022Source
- 3 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)FORM 2A 31 03 22.pdf · uploaded 19 Jul 2022Source
- 4 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)FORM 2A 31 12 2021.pdf · uploaded 19 Jul 2022Source
- 1 Disclosure of sold/ booked inventoryDisclasure of Sold Inventory.pdf · uploaded 19 Jul 2022Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)FORM 5.pdf · uploaded 31 Dec 2022Source
- 1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentOC.pdf · uploaded 7 Jun 2023Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)Om Aditya.pdf · uploaded 29 Sep 2023Source
- 1 Architect’s Certificate on Completion of Project (Form 4)Form 4.pdf · uploaded 25 Jan 2025Source
Technical
Technical (Architect)
- DocumentARCHITECT CERTIFICATE.pdf · uploaded 3 Apr 2021Source
Technical (Engineer)
- DocumentENGINEER CERTIFICATE.pdf · uploaded 3 Apr 2021Source
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvalsS NO 48 H NO 4/2 PLOT NO 2
As registered with MahaRERA and published on its project page
- Project type
- Mixed
- Status on MahaRERA
- Certificate Signed
- Unit types
- 1BHK, 2BHK, 3BHK, Shop41 units in all
- Address
- S No 48 H No 4/2 Plot No 2, Sarodaya Nagar, Badlapur WestPIN 421503
- Village
- Badlapur (M Cl), Ambarnath taluka
- Designated bank account
- 76
- Developed in phases
- No
Survey, CTS, gat or plot numbers
Boundaries
- North
- 12mt D P Road
- South
- S No 48 Hissa No 4 P
- East
- 6mt Wide Road
- West
- S No48 Hissa No 3 P
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking41 units
20 of 41 units booked (49%), as the promoter reported to MahaRERA
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 1BHK | 254.11 sq m · 2,735 sq ft | 7 | 3 |
| 2BHK | 793.31 sq m · 8,539 sq ft | 19 | 5 |
| 3BHK | 145.2 sq m · 1,563 sq ft | 3 | 0 |
| Shop | 11.07 sq m · 119 sq ft | 1 | 1 |
| Shop | 12.3 sq m · 132 sq ft | 1 | 1 |
| Shop | 12.52 sq m · 135 sq ft | 1 | 1 |
| Shop | 14.07 sq m · 151 sq ft | 1 | 1 |
| Shop | 14.33 sq m · 154 sq ft | 1 | 1 |
Show all 15 unit rowsShow fewer unit rows
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| Shop | 14.62 sq m · 157 sq ft | 1 | 1 |
| Shop | 14.67 sq m · 158 sq ft | 1 | 1 |
| Shop | 19.91 sq m · 214 sq ft | 1 | 1 |
| Shop | 21.36 sq m · 230 sq ft | 1 | 1 |
| Shop | 26.1 sq m · 281 sq ft | 1 | 1 |
| Shop | 26.31 sq m · 283 sq ft | 1 | 1 |
| Shop | 26.51 sq m · 285 sq ft | 1 | 1 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.