Skip to content
Extended 36 mo18 floorsRERA P51700000829

B Wing, Mohan Areca

Deedo IDDP-THN-JHR1-B

MahaRERA has not published a flat-by-flat record for this tower, and no registered deed names it yet.

Median saleNot on recordneeds 3 or more sales
Booked100%96 of 96 · MahaRERA
Completion30 Dec 202231 Dec 2019 · revised
Units & parking in B Wing
TypeCarpet areaUnitsBooked
1BHK28 m² (301 sq.ft)88
1BHK28.1 m² (303 sq.ft)88
1BHK29.2 m² (315 sq.ft)88
1BHK29.3 m² (315 sq.ft)88
2BHK35.9 m² (386 sq.ft)88
2BHK36.3 m² (390 sq.ft)88
2BHK36.4 m² (391 sq.ft)88
2BHK36.7 m² (395 sq.ft)88
2BHK38.2 m² (411 sq.ft)1616
2BHK38.6 m² (416 sq.ft)88
2BHK38.6 m² (416 sq.ft)88
As registered with MahaRERA
RERA registration
P51700000829 · registered 23 Jul 2017
Promised completion
31 Dec 2019
Revised completion
30 Dec 2022
Sanctioned habitable floors
18
Sanctioned floors (incl. basement, stilt, podium)
18
Units declared
0
Homes
0
Shops and offices
0
MahaRERA status
Certificate Signed
Deedo ID
Deedo IDDP-THN-JHR1-B
Questions about B Wing

When is B Wing due for completion?

The MahaRERA registration promises 31 Dec 2019, revised to 30 Dec 2022.

How many floors does B Wing have?

18 sanctioned habitable floors, as registered with MahaRERA.