Skip to content
Not yet due8 floors · 35 flatsRERA P51700056288

Wing D, Krishna Nayan Complex Phase I

Deedo IDDP-THN-8YFS-D

1 flat has a sale on record, 0 are booked without a sale deed yet and 17 are unsold, per MahaRERA's Oct 2026 disclosure and the registered deeds.

Median saleNot on recordneeds 3 or more sales
Booked3%1 of 35 · Oct 2026
Completion31 Dec 2027as registered

Every flat, floor by floor

Tap a flat to see its record.

  • Sale registered
  • Unsold
  • Reserved, rehab or other
0102030405
Fl 8
Fl 7
Fl 6
Fl 5
Fl 4
Fl 3
Fl 2
Fl 1
2 BHK2 BHK3 BHK3 BHK2 BHK

Sale status from MahaRERA's Oct 2026 disclosure; deeds from IGR Index II, placed on a flat only when the deed names this tower and flat. “Listed by developer” comes from the developer and is labelled as such.

SelectedUnsold

Flat 705

2 BHK · 547 sq ft · floor 7

Deeds
0
Last activity
None on record
Last sale
None registered
Units & parking in Wing D

MahaRERA's project page with unit types hasn't been imported for this registration.

Parking: Closed/Covered 0 · Open Space 48 (as declared to MahaRERA)

Construction progress (declared)

Work completed, as the promoter reported it to MahaRERA (Form 1). Not verified on site.

  • Excavation0%
  • Basement (if any)0%
  • Podiums (if any)0%
  • Plinth0%
  • Stilt Floor0%
  • Slabs of Super Structure0%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
  • Sanitary Fittings within the flats / premises0%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
As registered with MahaRERA
RERA registration
P51700056288 · registered 25 May 2024
Promised completion
31 Dec 2027
Sanctioned habitable floors
8
Deedo ID
Deedo IDDP-THN-8YFS-D
Questions about Wing D

How many flats in Wing D are sold?

1 flat has a sale on record, 0 are booked without a sale deed yet and 17 are unsold, per MahaRERA's Oct 2026 disclosure and the registered deeds.

When is Wing D due for completion?

The MahaRERA registration promises 31 Dec 2027.

How many floors does Wing D have?

8 sanctioned habitable floors, as registered with MahaRERA.

Data through11 Oct 2026SourcesMahaRERA registration and project page · IGR Maharashtra Index IIFloors and units are as registered; a promoter can revise them in later filings. Party names appear only inside an unlocked Index II.Methodology