Its promised completion date, Dec 2023, has passed and MahaRERA does not show it completed; no MahaRERA orders on record; 100% of its units are booked.

Badlapur (M Cl), Thane 421503 · Promoter: Siddhivinayak Enterprises

Delivery2 yrs 10 mo past duePromised Dec 2023 · no extension on record · not shown completedRegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales100% booked48 of 48 units · as the promoter reported to MahaRERA
Arham Residency project report cardPDF: delivery, regulatory orders, people on record, every tower and the registered deals — for your bank or lawyerSee what's inside · from ₹1,499

Its promised completion date, Dec 2023, has passed and MahaRERA does not show it completed

  • This projectRegistered 20 Feb 2019, completion promised 30 Dec 2023, and still not shown completed today.

No extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales, rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

The building

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP51700019647
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5170001964720 Feb 201930 Dec 202330 Dec 2023Siddhivinayak EnterprisesProject page
Documents30

1 document held by Deedo, 29 filings listed on MahaRERA's project page

Registration certificate

Legal

  • Legal Title reportTITLE REPORT.pdf · uploaded 30 Jan 2019Source
  • Legal Title reportSEARCH REPORT 1.pdf · uploaded 30 Jan 2019Source
  • Legal Title reportSEARCH REPORT 2.pdf · uploaded 30 Jan 2019Source
  • Declaration Form BFORM B.pdf · uploaded 14 Feb 2019Source

Migrated

  • 1 Copy of the legal title reportTITLE REPORT.pdf · uploaded 30 Jan 2019Source
  • 2 Copy of the legal title reportSEARCH REPORT 1.pdf · uploaded 30 Jan 2019Source
  • 3 Copy of the legal title reportSEARCH REPORT 2.pdf · uploaded 30 Jan 2019Source
Show all 30 documentsShow fewer documents

Migrated

  • 1 Details of encumbrancesENCUBRANCES.pdf · uploaded 30 Jan 2019Source
  • 1 Commencement Certificates / NA Order for plotted developmentC C.pdf · uploaded 30 Jan 2019Source
  • 1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)ARCHITECT CERTIFICATE.pdf · uploaded 30 Jan 2019Source
  • 1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)ENGINEER CERTIFICATE.pdf · uploaded 30 Jan 2019Source
  • 1 Certificates of CA (Form 3)CA CERTIFICATE.pdf · uploaded 30 Jan 2019Source
  • 1 Proforma of Allotment letterDRAFT ALLOTMENT LETTER.pdf · uploaded 30 Jan 2019Source
  • 2 Proforma of Allotment letterDRAFT AGREEMENT.pdf · uploaded 30 Jan 2019Source
  • 1 Copy of Layout Approval (in case of layout)LAYOUT PLAN.PDF · uploaded 14 Feb 2019Source
  • 1 Building Plan Approval (IOD)BUILDING PLAN.PDF · uploaded 14 Feb 2019Source
  • 1 Declaration in FORM BFORM B.pdf · uploaded 14 Feb 2019Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)SIDDHIVINAYAK ENTRPRISES.pdf · uploaded 30 Sep 2020Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)SIDDHIVINAYAK ENTERPRISES.pdf · uploaded 30 Sep 2020Source
  • 1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentO C.pdf · uploaded 12 Jun 2021Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)Fom 5 FY 2020-21 Siddhivinayak.pdf · uploaded 25 Feb 2023Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)FORM 5 FY 2021-22 ARHAM RESIDENCY.pdf · uploaded 25 Feb 2023Source
  • 1 Architect’s Certificate on Completion of Project (Form 4)FORM 4 ARCHITECT CERTIFICATE.pdf · uploaded 15 Nov 2024Source
  • 1 Status of Formation of Legal Entity (Society/Co Op etc.)SOCIETY FORMATION CERTIFICATE.pdf · uploaded 15 Nov 2024Source
  • 1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentOCCUPATION CERTIFICATE.pdf · uploaded 15 Nov 2024Source

Technical

  • DocumentBUILDING PLAN.PDF · uploaded 14 Feb 2019Source
  • DocumentLAYOUT PLAN.PDF · uploaded 14 Feb 2019Source

Technical (Architect)

  • DocumentARCHITECT CERTIFICATE.pdf · uploaded 30 Jan 2019Source

Technical (Engineer)

  • DocumentENGINEER CERTIFICATE.pdf · uploaded 30 Jan 2019Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsCTS 525/526

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
Unit types
Commercial shop, Residential flat48 units in all
Address
Cts 525/526, Badlapur, Badlapur GaonPIN 421503
Village
Badlapur (M Cl), Ambarnath taluka
Designated bank account
109
Developed in phases
No

Survey, CTS, gat or plot numbers

CTS 525/526

Boundaries

North
House Of Mr Paranjpe
South
House No 237-1
East
Road To Badlapur Station
West
Lake

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking48 units

48 of 48 units booked (100%), as the promoter reported to MahaRERA

Commercial shop · 12 unitsResidential flat · 36 units
TypeCarpet areaUnitsBooked
Commercial shop9.09 sq m · 98 sq ft11
Commercial shop9.43 sq m · 102 sq ft22
Commercial shop10.86 sq m · 117 sq ft11
Commercial shop11.27 sq m · 121 sq ft33
Commercial shop11.85 sq m · 128 sq ft11
Commercial shop11.96 sq m · 129 sq ft22
Commercial shop14.16 sq m · 152 sq ft11
Commercial shop16.22 sq m · 175 sq ft11
Show all 14 unit rowsShow fewer unit rows
TypeCarpet areaUnitsBooked
Residential flat30.91 sq m · 333 sq ft66
Residential flat34.16 sq m · 368 sq ft66
Residential flat34.24 sq m · 369 sq ft66
Residential flat34.3 sq m · 369 sq ft66
Residential flat39.23 sq m · 422 sq ft66
Residential flat43.98 sq m · 473 sq ft66

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals2

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectAkhil Anil Desai—
EngineerHarsh Desai—

Source: MahaRERA project page. Contact details are not shown.

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Report a problemMethodology