RERA projects in Ambarnath

1,594 projects under 1,679 MahaRERA registrations, registered 2017–2026. 42% have a completion date extended beyond the one promised.

Taluka
1,594RERA projects
1,679Registrationssome projects hold several
585Completion still due993 past their completion date, 22 marked completed
4 monthsMedian extension beyond promised date42% of registrations extended
89Regulatory caseson 24 projects
3,051Buildings on recordfrom registration certificates

Registrations per year

New MahaRERA registrations by registration date.

MahaRERA registrations per year
YearRegistrations
2017341
2018136
2019131
202074
2021138
2022177
2023182
2024126
2025148
2026125

Projects in Ambarnath

1,594 projects registered with MahaRERA in this taluka and the places within it.

ProjectRERARegisteredPromised completionRevised completionTimingCases
Khatri RenovaKhatri DevelopersPM133000260165125 Aug 202631 Dec 203031 Dec 2030Not yet due0
Vishwajeet VantageAbhijeet EmpirePR133000260162924 Aug 202631 Jul 203031 Jul 2030Not yet due0
Raj CornerstoneRaj SuperstructurePR133000260160121 Aug 202631 Dec 202931 Dec 2029Not yet due0
Rosewood Residency 1Vastu Ved DevelopersPR133101260156417 Aug 202630 Oct 203030 Oct 2030Not yet due0
Midtown B And C WingSiddhivinayak Group NxPR133101260154213 Aug 202615 Dec 203015 Dec 2030Not yet due0
Akash Deep CHS LTDMV BuildconPR133000260152011 Aug 202631 Mar 203031 Mar 2030Not yet due0
Greens NXDreamland Developers NXPM133000260149010 Aug 202631 Dec 203031 Dec 2030Not yet due0
Yug ParadiseBharti InfraPR13300026014194 Aug 202631 Oct 202731 Oct 2027Not yet due0
Morivali Ambernath Wembley Park Chs LtdShree Khodiyar BuildconPR133000260137431 Jul 202630 Nov 202830 Mar 2029Extended 4 mo0
Adiyogi Blossom Phase - IIMP Procorp Builders LLPPR133000260135730 Jul 202631 Dec 203030 Apr 2031Extended 4 mo0
Chandrama S ChslS R InfraaPM133000260135529 Jul 202631 Mar 202931 Jul 2029Extended 4 mo0
Sudarshan ViharEeshwar ConstructionPR133000260135429 Jul 202631 Dec 202930 Apr 2030Extended 4 mo0
Sai UniversePinnacle CorporationPR133000260133428 Jul 202631 Dec 202930 Apr 2030Extended 4 mo0
Surval CrownVivikta EnterprisesPR133000260124220 Jul 202631 Mar 202931 Jul 2029Extended 4 mo0
Ganesh HeightsM/s Ganraj ConstructionPR133000260113813 Jul 202630 Jun 202830 Oct 2028Extended 4 mo0
Vishnu Krupa Co operative Housing SocietyKrishna BuildconPM13300026011259 Jul 202631 Dec 202930 Apr 2030Extended 4 mo0
YatigandhSwamini Infra Private LimitedPR13300026010858 Jul 202631 Mar 203131 Jul 2031Extended 4 mo0
Jewel PrrideJewel BuildersPR13300026010396 Jul 202631 Mar 203131 Jul 2031Extended 4 mo0
Tulsi VatsalyaTulsi Builders and DevelopersPR1330002600991, PR133000260117130 Jun 202631 Dec 203230 Apr 2033Extended 4 mo0
Yashoda Vrundavan Complex Phase 2Vardhman RealtyPR133101260096829 Jun 202631 Dec 203030 Apr 2031Extended 4 mo0
R1 And R2 Panvelkar Palash ChsShree Sai EnterprisesPR133000260091224 Jun 202631 Dec 202930 Apr 2030Extended 4 mo0
Innovative PrestigeInnovative RealityPM133000260082517 Jun 202631 Dec 203030 Apr 2031Extended 4 mo0
Iskcon Residency Phase-II Type AIskcon RealtorsPR133202260077715 Jun 202631 Dec 203030 Apr 2031Extended 4 mo0
Sai Prasad ApartmentSai Prasad DevelopersPM133000260076412 Jun 20262 Apr 20292 Aug 2029Extended 4 mo0
City CentreKinikar Multipurpose HospitalPC133000260074311 Jun 202631 Mar 202831 Jul 2028Extended 4 mo0

Other talukas in Thane

Most active promoters

By projects registered here, as named on MahaRERA.

  1. Mohan Lifespaces LLP12 projects
  2. Ishwar Reality9 projects
  3. Mohan Hardasmal Tharwani8 projects
  4. D A Construction7 projects
  5. Gulabrao Baburao Karanjule Patil7 projects
  6. Kgi Realty Private Limited7 projects
  7. Pramukh Developers7 projects
  8. Keyblue Realtors Private Limited6 projects
  9. Panvelkar Infrastructures Private Limited6 projects
  10. Raj Group6 projects
Data through20 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology