Completion was pushed back 4 months, to Apr 2029; no MahaRERA orders on record; 0% of its units are booked.

Ambarnath(M Cl), Thane 421501 · by Ravi Chahu Patil

DeliveryExtended 4 moPromised Dec 2028 · now due Apr 2029RegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales0% booked0 of 47 units · as the promoter reported to MahaRERA

Buying a flat here?

See every deed registered on it.

Completion was pushed back 4 months, to Apr 2029

  • This projectRegistered 23 Dec 2025, completion promised 31 Dec 2028, revised to 30 Apr 2029.

No extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales, rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

The building

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationPM1331012501842
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
PM133101250184223 Dec 202531 Dec 202830 Apr 2029Ravi Chahu PatilProject page
Documents27

1 document held by Deedo, 26 filings listed on MahaRERA's project page

Registration certificate

Finance

  • PAN Cardpan ravi patil (1).pdf · uploaded 18 Nov 2025Source

Legal

  • Declaration Form BLand Ownership Doc.pdf · uploaded 13 Nov 2025Source
  • OthersDisclosure of Interest in other real estate projecdt.pdf · uploaded 18 Nov 2025Source
  • Declaration Form BFinal Form B.pdf · uploaded 18 Nov 2025Source
  • Declaration Form B2 Legal Title 43-2-D,E.pdf · uploaded 9 Dec 2025Source

Migrated

  • Withdrawal Update Form 1Withdrawal Update Form 1 · uploaded 15 May 2026Source
  • Withdrawal Update Form 1Withdrawal Update Form 1 · uploaded 15 May 2026Source
Show all 27 documentsShow fewer documents

Migrated

  • Withdrawal Update Form 1form 1 full.pdf · uploaded 15 May 2026Source
  • Withdrawal Update Form 1form 1 full.pdf · uploaded 15 May 2026Source
  • Withdrawal Update Form 1form 1 full.pdf · uploaded 15 May 2026Source
  • Withdrawal Update Form 2eng certificate.pdf · uploaded 15 May 2026Source
  • Withdrawal Update Form 2eng certificate.pdf · uploaded 15 May 2026Source
  • Withdrawal Update Form 2eng certificate.pdf · uploaded 15 May 2026Source
  • Withdrawal Update Form 2eng certificate.pdf · uploaded 15 May 2026Source
  • Withdrawal Update Form 2eng certificate.pdf · uploaded 15 May 2026Source
  • Withdrawal Update Form 3form 3 rudraraj.pdf · uploaded 15 May 2026Source
  • Withdrawal Update Form 3form 3 rudraraj.pdf · uploaded 15 May 2026Source
  • Withdrawal Update Form 3form 3 rudraraj.pdf · uploaded 15 May 2026Source
  • Withdrawal Update Form 3form 3 rudraraj.pdf · uploaded 15 May 2026Source
  • Withdrawal Update Form 3form 3 rudraraj.pdf · uploaded 15 May 2026Source

Technical

  • DocumentAPPROVAL PLAN.pdf · uploaded 13 Nov 2025Source
  • DocumentAPPROVAL PLAN.pdf · uploaded 13 Nov 2025Source
  • DocumentAnnexure A.pdf · uploaded 18 Nov 2025Source
  • OthersDeclaration regarding Plot area.pdf · uploaded 18 Nov 2025Source

Technical (Architect)

  • Documentform 1 full.pdf · uploaded 15 May 2026Source

Technical (Engineer)

  • Documenteng certificate.pdf · uploaded 15 May 2026Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsLand parcel Hissa No 2 D, Plot No 4

As registered with MahaRERA and published on its project page

Project type
Mixed
Status on MahaRERA
Certificate Signed
Unit types
—47 units in all
Address
Shiv Mandir Road, Pale gaonPIN 421501
Village
Ambarnath(M Cl), Ambarnath taluka
Land area for this project
1,323 sq m (14,240 sq ft)
Approved layout area
2,644 sq m (28,457 sq ft)
Permissible built-up area
3,706 sq m (39,893 sq ft)
Sanctioned built-up area
3,706 sq m (39,893 sq ft)
Recreational open space
145 sq m (1,565 sq ft)
Designated bank account
85
Developed in phases
No

Survey, CTS, gat or plot numbers

Hissa No 2 DPlot No 4Survey No 43

Land as published on MahaRERA's project page

Plot No 4, Village Pale, Hissa No 2 D,E, Survey No 43

Boundaries

North
2400 MT DP Road
South
S No 44
East
S No 43/2, Plot No 5
West
S No 43/2, Plot No 2

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking47 units

47 units registered

— · 47 units
TypeCarpet areaUnits
——47

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals3

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
Chartered accountantSuresh Radhakrishnani—
Chartered accountantWatwani and Associates—
EngineerPramod Kamble—

Source: MahaRERA project page. Contact details are not shown.

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Report a problemMethodology