Ashok Complex
Deedo IDDP-SIN-590SCompletion was pushed back 3 years, to Dec 2026; no MahaRERA orders on record; 16% of its units are booked.
Kudal (Ct), Sindhudurg 416520 · by Sandeep Ashok Gaonkar
Buying a flat here?
See every deed registered on it.
Completion was pushed back 3 years, to Dec 2026
- This projectRegistered 11 Dec 2018, completion promised 30 Dec 2023, revised to 31 Dec 2026.
1 extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales, rentals and mortgages matched to this project · the free view shows a price band
The building
Open a building to see every flat, floor by floor.
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationP52900018890
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P52900018890 | 11 Dec 2018 | 30 Dec 2023 | 31 Dec 2026 | Sandeep Ashok Gaonkar | Project page |
Documents54
2 documents held by Deedo, 52 filings listed on MahaRERA's project page
Finance
- PAN CardSandeep PAN Card.pdf · uploaded 10 Nov 2018Source
Legal
Show all 54 documentsShow fewer documents
Migrated
- 1 Copy of Layout Approval (in case of layout)Plan.pdf · uploaded 13 Nov 2018Source
- 1 Building Plan Approval (IOD)NA Order.pdf · uploaded 13 Nov 2018Source
- 1 Commencement Certificates / NA Order for plotted developmentCommencement Certificate.pdf · uploaded 13 Nov 2018Source
- 1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Architects Certificate.pdf · uploaded 13 Nov 2018Source
- 1 Details of encumbrancesNo Encumbrances.pdf · uploaded 29 Nov 2018Source
- 1 Declaration in FORM BForm_B_ Sandip Gaavkar.pdf · uploaded 29 Nov 2018Source
- 1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Engineers Certificate.pdf · uploaded 5 Dec 2018Source
- 1 Certificates of CA (Form 3)CA Certificate Updated.pdf · uploaded 6 Dec 2018Source
- 1 Proforma of Allotment letterModel Agreement Marathi.pdf · uploaded 6 Dec 2018Source
- 2 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Form 1 - Architect Certificate 31Mar2022.pdf · uploaded 3 Aug 2024Source
- 3 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Form 1 - Architect Certificate 31Mar2023.pdf · uploaded 3 Aug 2024Source
- 4 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Form 1 - Architect Certificate 31Dec2023.pdf · uploaded 3 Aug 2024Source
- 2 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Form 2 - 01 Engineer Certificate 31Mar2022.pdf · uploaded 3 Aug 2024Source
- 3 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Form 2 - 02 Engineer Certificate 31Mar2023.pdf · uploaded 3 Aug 2024Source
- 4 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Form 2 - 03 Engineer Certificate 31Dec2023.pdf · uploaded 3 Aug 2024Source
- 1 Disclosure of sold/ booked inventoryDisclosure of Sold Inventory 31Dec2023.pdf · uploaded 3 Aug 2024Source
- 2 Certificates of CA (Form 3)Form 3 - 01 CA Certificate March 31, 2022.pdf · uploaded 3 Aug 2024Source
- 3 Certificates of CA (Form 3)Form 3 - 02 CA Certificate March 31, 2023.pdf · uploaded 3 Aug 2024Source
- 4 Certificates of CA (Form 3)Form 3 - 03 CA Certificate December 31, 2023.pdf · uploaded 3 Aug 2024Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)Form 5 - 02 Annual Report - CA Certificate Adukia Associate FY 22-23.pdf · uploaded 3 Aug 2024Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)Form 5 - 01 Annual Report - CA Ceritificate Adukia Associate FY 21-22.pdf · uploaded 3 Aug 2024Source
- 2 Declaration in FORM BForm B - Promoter Sandip Ashok Gaonkar.pdf · uploaded 13 Aug 2024Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)Form 2A Quality Assurance 2024.pdf · uploaded 13 Aug 2024Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)Form 2A Quality Assurance 2023.pdf · uploaded 13 Aug 2024Source
- 1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)08 Architect Certificate 31Mar2025.pdf · uploaded 22 Apr 2025Source
- 1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)08 Engineer Certificate 31Mar2025.pdf · uploaded 22 Apr 2025Source
- 1 Certificates of CA (Form 3)08 Form3 CA Certificate 31Mar2025.pdf · uploaded 26 Apr 2025Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)RERA Annual Certificate 2024 Sandip.pdf · uploaded 28 Apr 2025Source
- Withdrawal Update Form 1FORM 1 June25.pdf · uploaded 16 Mar 2026Source
- Withdrawal Update Form 2Form 2 June25.pdf · uploaded 16 Mar 2026Source
- Withdrawal Update Form 3Form 3 June 2025.pdf · uploaded 16 Mar 2026Source
- Withdrawal Update Form 1FORM 1 Sep 25.pdf · uploaded 18 Mar 2026Source
- Withdrawal Update Form 2Form 2 Sep 25.pdf · uploaded 18 Mar 2026Source
- Withdrawal Update Form 3Form 3 Sept 2025.pdf · uploaded 18 Mar 2026Source
- Withdrawal Update Form 1Form 1 Dec 25.pdf · uploaded 21 Mar 2026Source
- Withdrawal Update Form 2Form 2 Dec 25.pdf · uploaded 21 Mar 2026Source
- Withdrawal Update Form 3Form 3 Dec 25.pdf · uploaded 21 Mar 2026Source
- Withdrawal Update Form 1Form 1 Architect Certificate Mar26 Sandeep.pdf · uploaded 24 Jun 2026Source
- Withdrawal Update Form 2Form 2 Engineers Certificate Mar26 Sandeep.pdf · uploaded 24 Jun 2026Source
- Withdrawal Update Form 3Form 3 CA Certificate Mar26 Sandeep.pdf · uploaded 24 Jun 2026Source
Technical
Technical (Architect)
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvalsLand parcel Survey No 260A Hissa No 1A
As registered with MahaRERA and published on its project page
- Project type
- Residential / Group Housing
- Status on MahaRERA
- Certificate Signed
- Unit types
- 1 BHK, 1 RK51 units in all
- Address
- Survey No 260A Hissa No 1A, Near New English School, Ambedkar ChowkPIN 416520
- Village
- Kudal (CT), Kudal taluka
- Land area for this project
- 2,277 sq m (24,509 sq ft)
- Permissible built-up area
- 2,907 sq m (31,295 sq ft)
- Sanctioned built-up area
- 2,382 sq m (25,644 sq ft)
- Designated bank account
- 212
- Developed in phases
- No
Survey, CTS, gat or plot numbers
Land as published on MahaRERA's project page
Survey No 260A Hissa No 1A
Boundaries
- North
- Internal Road
- South
- Remaning Space of Project and Hissa No 1A-1B
- East
- Plot No 3
- West
- Survey No 229-398 and Survey No 227-401
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking51 units
8 of 51 units booked (16%), as the promoter reported to MahaRERA
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 1 BHK | 35.42 sq m · 381 sq ft | 5 | 1 |
| 1 BHK | 35.54 sq m · 383 sq ft | 5 | 0 |
| 1 BHK | 35.62 sq m · 383 sq ft | 5 | 3 |
| 1 BHK | 36 sq m · 388 sq ft | 5 | 1 |
| 1 BHK | 36.12 sq m · 389 sq ft | 8 | 0 |
| 1 BHK | 36.31 sq m · 391 sq ft | 5 | 1 |
| 1 BHK | 37.42 sq m · 403 sq ft | 8 | 0 |
| 1 RK | 21.25 sq m · 229 sq ft | 5 | 2 |
| 1 RK | 23.74 sq m · 256 sq ft | 5 | 0 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Professionals3
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Yogesh Ganpat Sawant | — |
| Chartered accountant | Sagar Gajanan Teli | — |
| Engineer | Yogesh Ganpat Sawant | — |
Source: MahaRERA project page. Contact details are not shown.