Chavan Chorage Complex
Deedo IDDP-SAT-QGCWCompletion was pushed back 6 years and 3 months, to Dec 2029; no MahaRERA orders on record; 0% of its units are booked.
Satara 415002 · by Tarachand Lombaji Tapase
Buying a flat here?
See every deed registered on it.
Completion was pushed back 6 years and 3 months, to Dec 2029
- This projectRegistered 3 Jun 2020, completion promised 30 Sep 2023, revised to 31 Dec 2029.
1 extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales, rentals and mortgages matched to this project · the free view shows a price band
The building
Open a building to see every flat, floor by floor.
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationP52700025456
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P52700025456 | 3 Jun 2020 | 30 Sep 2023 | 31 Dec 2029 | Tarachand Lombaji Tapase | Project page |
Documents42
2 documents held by Deedo, 40 filings listed on MahaRERA's project page
Finance
- PAN CardPAN CARD.pdf · uploaded 14 Mar 2020Source
Legal
Show all 42 documentsShow fewer documents
Migrated
- 1 Copy of Layout Approval (in case of layout)Plot layout Plan Chavan Chorge.pdf · uploaded 14 Mar 2020Source
- 1 Building Plan Approval / NA Order for plotted developmentBuilding Plan Chavan Chorge Complex.pdf · uploaded 14 Mar 2020Source
- 1 Commencement Certificates / NA Order for plotted developmentCERTIFICATE FOR SANCTION Commencement certificate.pdf · uploaded 14 Mar 2020Source
- 1 Declaration in FORM BForm B affidavit cum declaration.pdf · uploaded 14 Mar 2020Source
- 2 Declaration in FORM BPower of Attorney final.pdf · uploaded 14 Mar 2020Source
- 1 Proforma of Allotment letterAgreement o sale.pdf · uploaded 14 Mar 2020Source
- 1 Copy of the legal title reportGOGA BUILDERS AND DEVELOPERS lEGAL sEARCH.pdf · uploaded 19 Mar 2020Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)CHAVAN CHORAGE FORM 3.pdf · uploaded 20 Mar 2020Source
- Withdrawal Update Form 1Chavan Chorage - Form No 1 Jun 2025.pdf · uploaded 19 Jan 2026Source
- Withdrawal Update Form 1Chavan Chorage - Form No 1 Sep 2025.pdf · uploaded 19 Jan 2026Source
- Withdrawal Update Form 1Chavan Chorage - Form No 1 Sep 2025.pdf · uploaded 19 Jan 2026Source
- Withdrawal Update Form 1Chavan Chorage - Form No 1 Dec 2025.pdf · uploaded 19 Jan 2026Source
- Withdrawal Update Form 2Chavan Chorage - Form No 2 Jun 2025.pdf · uploaded 19 Jan 2026Source
- Withdrawal Update Form 2Chavan Chorage - Form No 2 Sep 2025.pdf · uploaded 19 Jan 2026Source
- Withdrawal Update Form 2Chavan Chorage - Form No 2 Dec 2025.pdf · uploaded 19 Jan 2026Source
- Withdrawal Update Form 2Chavan Chorage - Form No 2 Dec 2025.pdf · uploaded 19 Jan 2026Source
- Withdrawal Update Form 3Chavan Chorage - Form No 3 Jun 2025.pdf · uploaded 19 Jan 2026Source
- Withdrawal Update Form 3Chavan Chorage - Form No 3 Sep 2025.pdf · uploaded 19 Jan 2026Source
- Withdrawal Update Form 3Chavan Chorage - Form No 3 DEC 2025.pdf · uploaded 19 Jan 2026Source
- Withdrawal Update Form 3Chavan Chorage - Form No 3 DEC 2025.pdf · uploaded 19 Jan 2026Source
- Form 5 (FY 2024-2025)Chavan Chorage - Form No 5 Mar 2025.pdf · uploaded 19 Jan 2026Source
- Withdrawal Update Form 1Chavan Chorage - Form No 1 Mar 2026.pdf · uploaded 16 Apr 2026Source
- Withdrawal Update Form 1Chavan Chorage - Form No 1 Mar 2026.pdf · uploaded 16 Apr 2026Source
- Withdrawal Update Form 2Chavan Chorage - Form No 2 Mar 2026.pdf · uploaded 16 Apr 2026Source
- Withdrawal Update Form 2Chavan Chorage - Form No 2 Mar 2026.pdf · uploaded 16 Apr 2026Source
- Withdrawal Update Form 3Withdrawal Application Form 3 - Goga Builders..pdf · uploaded 16 Apr 2026Source
- Withdrawal Update Form 3Withdrawal Application Form 3 - Goga Builders..pdf · uploaded 16 Apr 2026Source
- Withdrawal Update Form 1Chavan Chorage - Form No 1 JUN 2026.pdf · uploaded 8 Jul 2026Source
- Withdrawal Update Form 2Chavan Chorage - Form No 2 JUN 2026.pdf · uploaded 8 Jul 2026Source
- Withdrawal Update Form 3Chavan Chorage - Form No 3 JUN 2026_1_11zon.pdf · uploaded 8 Jul 2026Source
Technical
Technical (Architect)
- DocumentChavan Chorage - Form No 1 JUN 2026.pdf · uploaded 8 Jul 2026Source
Technical (Engineer)
- DocumentChavan Chorage - Form No 2 JUN 2026.pdf · uploaded 8 Jul 2026Source
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvalsLand parcel S NO. 11 TO 17
As registered with MahaRERA and published on its project page
- Project type
- Residential / Group Housing
- Status on MahaRERA
- Certificate Signed
- Unit types
- 1BHK, 2BHK, 3BHK, Shop20 units in all
- Address
- S No. 11 To 17, Pratapganj Peth, SataraPIN 415002
- Village
- Satara (M Cl), Satara taluka
- Location
- 17.68577, 73.99042
- Land area for this project
- 1,480 sq m (15,929 sq ft)
- Permissible built-up area
- 1,666 sq m (17,934 sq ft)
- Sanctioned built-up area
- 1,354 sq m (14,571 sq ft)
- Designated bank account
- 213
- Developed in phases
- No
Survey, CTS, gat or plot numbers
Land as published on MahaRERA's project page
S NO. 11 TO 17
Boundaries
- North
- Stream
- South
- Road
- East
- S No 10
- West
- Road
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking20 units
0 of 20 units booked (0%), as the promoter reported to MahaRERA
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 1BHK | 38.29 sq m · 412 sq ft | 2 | 0 |
| 1BHK | 41.06 sq m · 442 sq ft | 2 | 0 |
| 1BHK | 41.86 sq m · 451 sq ft | 1 | 0 |
| 1BHK | 47.91 sq m · 516 sq ft | 2 | 0 |
| 1BHK | 47.96 sq m · 516 sq ft | 2 | 0 |
| 1BHK | 49.41 sq m · 532 sq ft | 2 | 0 |
| 1BHK | 54.63 sq m · 588 sq ft | 1 | 0 |
| 2BHK | 66.25 sq m · 713 sq ft | 1 | 0 |
Show all 14 unit rowsShow fewer unit rows
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 3BHK | 79.35 sq m · 854 sq ft | 2 | 0 |
| Shop | 27.14 sq m · 292 sq ft | 1 | 0 |
| Shop | 27.32 sq m · 294 sq ft | 1 | 0 |
| Shop | 27.96 sq m · 301 sq ft | 1 | 0 |
| Shop | 28.25 sq m · 304 sq ft | 1 | 0 |
| Shop | 29.53 sq m · 318 sq ft | 1 | 0 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Professionals7
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Narendra Roakde | — |
| Chartered accountant | Ca V S Jadhav | — |
| Chartered accountant | samadhan ramdas kadam | — |
| Chartered accountant | Vitthal Shripati Jadhav | — |
| Engineer | Prakash Gujar | — |
| Engineer | Samshuddin M Landge | — |
| Other | Girish Kulkarni | — |
Source: MahaRERA project page. Contact details are not shown.