Deedo IDDP-SAT-5Y4VMahaRERA shows it completed, after its date was pushed back 1 year; no MahaRERA orders on record; 50% of its units are booked.
Malkapur (Np), Satara 415539 · by Dreamworld Builders And Developers
Buying a flat here?
See every deed registered on it.
MahaRERA shows it completed, after its date was pushed back 1 year
- This projectRegistered 8 Feb 2019, completion promised 10 Feb 2023, revised to 10 Feb 2024.
1 extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales, rentals and mortgages matched to this project · the free view shows a price band
2 buildings
Open a building to see every flat, floor by floor.
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationP52700019543
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P52700019543 | 8 Feb 2019 | 10 Feb 2023 | 10 Feb 2024 | DreamWorld Builders And Developers | Project page |
Documents66
3 documents held by Deedo, 63 filings listed on MahaRERA's project page
Show all 66 documentsShow fewer documents
Legal
Migrated
- 1 PAN CardPan card.pdf · uploaded 26 Jan 2019Source
- 1 Copy of the legal title reportsearch.pdf · uploaded 26 Jan 2019Source
- 1 Details of encumbrancesALL FERFAR, 7-12- N43_reduce.pdf · uploaded 26 Jan 2019Source
- 2 Details of encumbrancesDEVELOPMENT AGREEMENT_reduce_reduce-pages-1-12.pdf · uploaded 26 Jan 2019Source
- 3 Details of encumbrancesDEVELOPMENT AGREEMENT_reduce_reduce-pages-13-25.pdf · uploaded 26 Jan 2019Source
- 4 Details of encumbrancesDEVELOPMENT AGREEMENT_reduce_reduce-pages-26-40.pdf · uploaded 26 Jan 2019Source
- 5 Details of encumbrancesDEVELOPMENT AGREEMENT_reduce_reduce-pages-41-55.pdf · uploaded 26 Jan 2019Source
- 6 Details of encumbrancesDEVELOPMENT AGREEMENT_reduce_reduce-pages-56-68.pdf · uploaded 26 Jan 2019Source
- 1 Copy of Layout Approval (in case of layout)PLAN.pdf · uploaded 26 Jan 2019Source
- 1 Building Plan Approval (IOD)PLAN.pdf · uploaded 26 Jan 2019Source
- 1 Commencement Certificates / NA Order for plotted developmentpermission.pdf · uploaded 26 Jan 2019Source
- 1 Certificates of CA (Form 3)CA Form 3 DW-compressed.pdf · uploaded 31 Jan 2019Source
- 7 Details of encumbrancesNA order-compressed.pdf · uploaded 5 Feb 2019Source
- 1 Declaration in FORM BAfdedavit Form B-compressed.pdf · uploaded 5 Feb 2019Source
- 1 Proforma of Allotment letteragreement-Sathekhat-compressed 111.pdf · uploaded 5 Feb 2019Source
- 1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)MAHARERA FORM 5 -Dreamworld-min.pdf · uploaded 11 Jul 2019Source
- 2 Certificates of Architect (Form 1)(Mandatory for only ongoing project)RERA certificate Dreamworld BUILDERS-compressed.pdf · uploaded 11 Jul 2019Source
- 1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)RERA certificate Dreamworld BUILDERS-compressed.pdf · uploaded 11 Jul 2019Source
- 1 Form 2AForm 2A Dream World.pdf · uploaded 11 Jul 2019Source
- 1 Certificates of CA (Form 5)MAHARERA FORM 5 -Dreamworld.pdf · uploaded 11 Jul 2019Source
- 1 Status of ConveyanceForm 2A Dream World.pdf · uploaded 11 Jul 2019Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)FORM 5 20-21_compressed.pdf · uploaded 9 Feb 2023Source
- 2 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)FORM 2A QUALITY ASSURANCE_compressed.pdf · uploaded 9 Feb 2023Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)FORM 5 21-22_compressed (1).pdf · uploaded 9 Feb 2023Source
- 2 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)FORM 2A QUALITY ASSURANCE_compressed.pdf · uploaded 9 Feb 2023Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)FORM 5 18-19.pdf · uploaded 9 Feb 2023Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)FORM 5 19-20 (2)_compressed.pdf · uploaded 9 Feb 2023Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)FORM 5 20-21_compressed.pdf · uploaded 9 Feb 2023Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)FORM 5 21-22_compressed (1).pdf · uploaded 9 Feb 2023Source
- 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameBANK FORM.pdf · uploaded 9 Feb 2023Source
- 1 Deviation Report with respect to Allotment letterDEVIATION.pdf · uploaded 9 Feb 2023Source
- 2 Deviation Report with respect to Allotment letterDEVIATION ALLOTMENT.pdf · uploaded 9 Feb 2023Source
- 1 Deviation Report with respect to model copy of AgreementDEVIATION.pdf · uploaded 9 Feb 2023Source
- 2 Declaration in FORM BFORM B 1.pdf · uploaded 1 Jun 2023Source
- 3 Declaration in FORM BFORM B 2.pdf · uploaded 1 Jun 2023Source
- 3 Certificates of Architect (Form 1)(Mandatory for only ongoing project)FORM 1.pdf · uploaded 1 Jun 2023Source
- 2 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)FORM 2.pdf · uploaded 1 Jun 2023Source
- 4 Declaration in FORM BFORM B 1.pdf · uploaded 17 Jun 2023Source
- 5 Declaration in FORM BFORM B 2.pdf · uploaded 17 Jun 2023Source
- 4 Certificates of Architect (Form 1)(Mandatory for only ongoing project)FORM 1.pdf · uploaded 17 Jun 2023Source
- 3 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)FORM 2.pdf · uploaded 17 Jun 2023Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)FORM 2A.pdf · uploaded 17 Jun 2023Source
- 1 Disclosure of sold/ booked inventorySOLD UNSOLD-signed.pdf · uploaded 17 Jun 2023Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)FORM 5 22-23.pdf · uploaded 17 Jun 2023Source
- 2 Certificates of CA (Form 3)FORM NO 3.pdf · uploaded 19 Jun 2023Source
- 3 Certificates of CA (Form 3)FORM3.pdf · uploaded 19 Jun 2023Source
- 1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentPART COMPLETION.pdf · uploaded 5 Feb 2024Source
- 2 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentCert_FO_339460_35EkZBfSign.pdf · uploaded 9 Feb 2024Source
- 5 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Architects Certificate- Form 1.pdf · uploaded 13 Feb 2024Source
- 4 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Engineers Certificate - Form 2.pdf · uploaded 13 Feb 2024Source
- 2 Disclosure of sold/ booked inventoryBooked inventory Building wise.pdf · uploaded 13 Feb 2024View
- 4 Architect’s Certificate on Completion of Project (Form 4)Scan 14-Feb-2024 (1).pdf · uploaded 14 Feb 2024Source
Technical
Technical (Architect)
- DocumentArchitects Certificate- Form 1.pdf · uploaded 13 Feb 2024Source
Technical (Engineer)
- DocumentEngineers Certificate - Form 2.pdf · uploaded 13 Feb 2024Source
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvalsLand parcel 132/19
As registered with MahaRERA and published on its project page
- Project type
- Others
- Status on MahaRERA
- Certificate Signed
- Unit types
- 1BHK, 2BHK, 3BHK, 4BHK, Office space, Shop28 units in all
- Address
- 132/19, Opp. Old Bharati Vidyapeeth law College, Shivaji Chowk, Anadrao Highschool Road, Malkapur-415539 Tal. Karad Dist. Satara, MalkapurPIN 415539
- Village
- Malkapur (NP), Karad taluka
- Location
- 17.25608, 74.17937
- Land area for this project
- 1,000 sq m (10,764 sq ft)
- Permissible built-up area
- 1,200 sq m (12,917 sq ft)
- Sanctioned built-up area
- 994 sq m (10,699 sq ft)
- Designated bank account
- 76
- Developed in phases
- No
Survey, CTS, gat or plot numbers
Land as published on MahaRERA's project page
132/19
Boundaries
- North
- Somnath Popat Tate Property
- South
- Tarekar And Patil Property
- East
- Road
- West
- Omkar Apartment And Road
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking28 units
14 of 28 units booked (50%), as the promoter reported to MahaRERA
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 1BHK | 171.14 sq m · 1,842 sq ft | 5 | 5 |
| 2BHK | 383.25 sq m · 4,125 sq ft | 8 | 6 |
| 3BHK | 59.06 sq m · 636 sq ft | 1 | 1 |
| 4BHK | 105.88 sq m · 1,140 sq ft | 1 | 0 |
| Office space | 177.99 sq m · 1,916 sq ft | 2 | 0 |
| Shop | 239.28 sq m · 2,576 sq ft | 11 | 2 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Professionals4
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Rahul Shantaram Chavan | — |
| Chartered accountant | Ca Nikhil Indramal Oswal | — |
| Chartered accountant | Mr Sameer Patil | — |
| Other | Rahul Dilip Mane | — |