Skip to content

Goldfields

Deedo IDDP-SAT-AF3Q

MahaRERA shows it completed, after its date was pushed back 1 year; no MahaRERA orders on record.

Asawali, Satara 412802 · by Universal Developers

DeliveryCompletedCompletion / occupancy certificate on MahaRERA · after a 1 yr extensionRegulatoryNo ordersNot in any MahaRERA list or order Deedo has read

Buying a flat here?

See every deed registered on it.

MahaRERA shows it completed, after its date was pushed back 1 year

  • This projectRegistered 17 Aug 2017, completion promised 30 Dec 2020, revised to 30 Dec 2021.

1 extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales, rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.
Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP52700007391
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5270000739117 Aug 201730 Dec 202030 Dec 2021Universal DevelopersProject page
Documents60

2 documents held by Deedo, 58 filings listed on MahaRERA's project page

Registration certificate

Extension certificate

Finance

  • PAN CardPan Card Universal developers.pdf · uploaded 25 Jul 2017Source

Legal

  • Legal Title reportTitle Report- Goldfields 1.pdf · uploaded 25 Jul 2017Source
  • Declaration Form BForm B Affidavit cum Declaration.pdf · uploaded 26 Jul 2017Source
  • Legal Title reportSearch Receipt Report Adv Nadaf 18-12-2015 - Goldfields.pdf · uploaded 26 Jul 2017Source
  • OtherLetters- Consent 14-05-2018.pdf · uploaded 14 May 2018Source
  • OtherSale Deed Draft Goldfield 24122020.pdf · uploaded 25 Dec 2020Source
Show all 60 documentsShow fewer documents

Migrated

  • 1 PAN CardPan Card Universal developers.pdf · uploaded 25 Jul 2017Source
  • 1 Copy of the legal title reportTitle Report- Goldfields 1.pdf · uploaded 25 Jul 2017Source
  • 1 Details of encumbrancesEncumbrances Certificate Goldfield.pdf · uploaded 25 Jul 2017Source
  • 1 Copy of Layout Approval (in case of layout)Sanctioned Layout- Goldfields final.pdf · uploaded 25 Jul 2017Source
  • 1 Commencement Certificates / NA Order for plotted developmentNA ORDER Goldfields.pdf · uploaded 25 Jul 2017Source
  • 2 Copy of the legal title reportSearch Receipt Report Adv Nadaf 18-12-2015 - Goldfields.pdf · uploaded 26 Jul 2017Source
  • 1 Building Plan Approval (IOD)Sanctioned Layout Goldfields Asawali.pdf · uploaded 26 Jul 2017Source
  • 1 Declaration in FORM BForm B Affidavit cum Declaration.pdf · uploaded 26 Jul 2017Source
  • 1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Architect Certificate Arch Thakur fORM 1 25JULY17.pdf · uploaded 26 Jul 2017Source
  • 1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Form 2 Engineers Certificate Sadashiv Byadagi 19 jul 17.pdf · uploaded 26 Jul 2017Source
  • 1 Proforma of Allotment letterAgreement of Sale1.pdf · uploaded 26 Jul 2017Source
  • 1 Certificates of CA (Form 3)Form 3 CA Cert Nilesh Lokhande 27 jul 17.pdf · uploaded 27 Jul 2017Source
  • 2 Certificates of CA (Form 3)Goldfields CA Certificate upto 31DEC2017 F.pdf · uploaded 9 Mar 2018Source
  • 2 Proforma of Allotment letterAgreement of Sale- Goldfields-11-05-2018.pdf · uploaded 14 May 2018Source
  • 1 OtherLetters- Consent 14-05-2018.pdf · uploaded 14 May 2018Source
  • 3 Proforma of Allotment letterAsawali RERA agreement revised draft-Dt 14-8-2018.pdf · uploaded 14 Aug 2018Source
  • 1 Certificates of CA (Form 5)Self Declaration Universal Developers.pdf · uploaded 1 Oct 2018Source
  • 1 Form 2ADec 18 Quality Ass Cer Form 2A Universal Dev Sadashiv Byadagi.pdf · uploaded 4 Mar 2019Source
  • 2 Certificates of Architect (Form 1)(Mandatory for only ongoing project)March 2019 Arch Thakur Cert Form 1 Goldfields.pdf · uploaded 23 Jul 2019Source
  • 2 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)March 2019 Eng Cert U DevSadashiv Byadgi.pdf · uploaded 23 Jul 2019Source
  • 2 Form 2AMarch 2019 Quality Ass Cert U Dev Sadashiv Byadagi.pdf · uploaded 23 Jul 2019Source
  • 3 Certificates of CA (Form 3)Form 3 CA Certificate_Universal Developers_.pdf · uploaded 24 Jul 2019Source
  • 2 OtherSale Deed Draft Goldfield 24122020.pdf · uploaded 25 Dec 2020Source
  • 1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentLetter from Architect -Goldfeild project.pdf · uploaded 14 Jul 2021Source
  • 1 Status of Formation of Legal Entity (Society/Co Op etc.)Goldfields Society Certificate.pdf · uploaded 23 Dec 2021Source
  • 3 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Form 1.pdf · uploaded 26 Apr 2023Source
  • 3 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Engineers Certificate -Universal Developers- March 18.pdf · uploaded 26 Apr 2023Source
  • 4 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Engineers Certificate -Universal Developers- June 18.pdf · uploaded 26 Apr 2023Source
  • 5 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Engineers Certificate -Universal Developers- June 18.pdf · uploaded 26 Apr 2023Source
  • 6 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Dec 18 Eng Cer Form 2 Universal Dev Sadashiv Byadagi.pdf · uploaded 26 Apr 2023Source
  • 4 Certificates of CA (Form 3)Goldfields_CA Certificate.pdf · uploaded 26 Apr 2023Source
  • 5 Certificates of CA (Form 3)Form 3.pdf · uploaded 26 Apr 2023Source
  • 6 Certificates of CA (Form 3)Form 3.pdf · uploaded 26 Apr 2023Source
  • 7 Certificates of CA (Form 3)Form 3.pdf · uploaded 26 Apr 2023Source
  • 1 Proforma of Agreement for saleAgreement Letter.pdf · uploaded 26 Apr 2023Source
  • 1 Status of Conveyance001-050.pdf · uploaded 26 Apr 2023Source
  • 2 Status of Conveyance051-100 (1).pdf · uploaded 26 Apr 2023Source
  • 3 Status of Conveyance101-115.pdf · uploaded 26 Apr 2023Source
  • 2 Certificates of CA (Form 5)17-18.pdf · uploaded 11 May 2023Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)18-19.pdf · uploaded 11 May 2023Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)19-20.pdf · uploaded 11 May 2023Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)20-21.pdf · uploaded 11 May 2023Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)RERA FORM 5 21-22.pdf · uploaded 11 May 2023Source
  • 2 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentOccupation Certificate Goldfields Project.pdf · uploaded 23 Oct 2023Source
  • 3 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentNA ORDER- Goldfields.pdf · uploaded 29 Nov 2023Source
  • 4 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentPlot 208-218 7-12 - Maharashtra Government.pdf · uploaded 8 Apr 2024Source
  • 1 Architect’s Certificate on Completion of Project (Form 4)Form 4 Goldfields Project.pdf · uploaded 4 Nov 2024Source
  • 2 Architect’s Certificate on Completion of Project (Form 4)Form 4 Goldfields Project.pdf · uploaded 7 Nov 2024Source

Technical

  • DocumentSanctioned Layout- Goldfields final.pdf · uploaded 25 Jul 2017Source
  • DocumentSanctioned Layout Goldfields Asawali.pdf · uploaded 26 Jul 2017Source

Technical (Architect)

  • DocumentForm 1.pdf · uploaded 26 Apr 2023Source

Technical (Engineer)

  • DocumentDec 18 Eng Cer Form 2 Universal Dev Sadashiv Byadagi.pdf · uploaded 26 Apr 2023Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsLand parcel 1586, 1587

As registered with MahaRERA and published on its project page

Project type
Plotted
Status on MahaRERA
Certificate Signed
Address
1586, 1587, 1588, 1593, 1900/1PIN 412802
Village
Asawali, Khandala taluka
Designated bank account
179
Developed in phases
No

Survey, CTS, gat or plot numbers

15861587158815931900/1

Boundaries

North
Gat No 1901
South
Road
East
Gat No 1585 1594
West
Gat 1589 1590 1591 1592

Source: registration certificates and MahaRERA's project page, as stated there.

Professionals6

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectAjit V Thakur—
EngineerSadashiv Byadagi—
OtherNana Gorakh Lashkar—
Registered real estate agentGuru Shashikant Keskar—
Registered real estate agentPravin Sakharam Bagade—
Registered real estate agentSujeet Subhash Karnawat—

Source: MahaRERA project page. Contact details are not shown.

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Report a problemMethodology