Skip to content

RERA check · free, always

Is this project on time and in good standing?

Projects: P + 11 digits (or two letters + 13 digits, like PR1260002500851). Agents: A + 11 digits.

RegisteredExtendedMahaRERA status: Certificate Signed

PR1330002502600

Janaki Sadan · Kansai, Thane · Shreeji Developers

Promised for 15 Aug 2027, extended to 15 Dec 2027, which is still ahead.

The revised date is 4 months after the original promise.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Caution: Completion date extended from 15 Aug 2027 to 15 Dec 2027.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 1

Registration certificate4 Mar 2026View

Orders 0

No MahaRERA order or list names this number.

Questions about PR1330002502600

Is Janaki Sadan delayed?

Its completion moved from 15 Aug 2027 to 15 Dec 2027; the revised date has not passed yet.

How many extensions has it had?

Deedo holds 0 extension certificates for PR1330002502600. The completion date moved from 15 Aug 2027 to 15 Dec 2027.

Who is the promoter?

MahaRERA records Shreeji Developers as the promoter of PR1330002502600.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names PR1330002502600.

Answers are generated from the record.

Data through16 Nov 2026, 02:27SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersReport a problemMethodology