Shreeji Developers

Company or firm · 3 projects · 3 MahaRERA registrations

3Projects3 RERA registrations
0Completedas reported on MahaRERA project pages
50%Kept RERA date1 of 2 past their proposed date, not extended
+0 moMedian delayvs RERA proposed date · 1 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Thakare ComplexP51700022578Ambarnath2019Not reported30 Dec 202330 May 2025+17 months
Satyam Sheela Wing FP51700046976Ambarnath (R)2022Not reported31 Jul 2026—On date
Janaki SadanPR1330002502600Kansai2026Not reported15 Aug 2027—On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Thakare Complex+17 mo
  • Satyam Sheela Wing FOn date
  • Janaki SadanOn date

Track record notes

  • 1 of 2 registrations whose RERA proposed completion date has passed was never extended beyond it.
  • Longest extension on record: 17 months, for Thakare Complex (P51700022578).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology