RERA check · free, always
Is this project on time and in good standing?
Projects: P + 11 digits (or two letters + 13 digits, like PR1260002500851). Agents: A + 11 digits.
Registered
PR1260002602423
Avani · Alandi (M Cl), Pune · Akritee Buildcon
Promised for 31 Dec 2027 and not extended so far.
1 year and 1 month to go until the promised date.
What to watch
Facts from the record. A flag is a reason to ask questions, not a verdict.
- ✓Clear: Completion date never extended.
- ✓Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.
Documents 1
Orders 0
No MahaRERA order or list names this number.
Questions about PR1260002602423
Is Avani delayed?
Not so far. MahaRERA records a promised completion of 31 Dec 2027, which has not passed yet.
How many extensions has it had?
Deedo holds 0 extension certificates for PR1260002602423.
Who is the promoter?
MahaRERA records Akritee Buildcon as the promoter of PR1260002602423.
Is it on any MahaRERA regulatory list?
No MahaRERA order or list that Deedo holds names PR1260002602423.
Answers are generated from the record.
Data through4 Nov 2026, 01:40SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersReport a problemMethodology