Company or firm · first RERA registration 2026

Akritee Buildcon

Deedo IDDD-9MH9

None of 1 registration has reached its promised completion date yet.

Projects11 RERA registration
Kept RERA dateNone due yetMaharashtra: 73%
Median delayNone due yetwhen late · Maharashtra: 4 mo
First sales on record0registered first-sale deeds matched so far
Regulatory cases0none on record

Delivery record

None of 1 registration with dates has moved or missed its RERA date

1 registration with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
AvaniPR1260002602423Alandi (M Cl)Not on record31 Dec 2027—On date

Akritee Buildcon, in questions

Does Akritee Buildcon finish projects on time?

None of its 1 MahaRERA registration has reached its promised completion date yet.

How many projects has Akritee Buildcon registered with MahaRERA?

1 project under 1 MahaRERA registration; 0 completed on MahaRERA.

Does Akritee Buildcon have MahaRERA regulatory cases?

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.