P99000052644
Shri Dajiba Heights · Palghar · Shrijee Krupa Developers
Promised for 31 Dec 2027, extended to 30 Apr 2028, which is still ahead.
The revised date is 4 months after the original promise.
What to watch
Facts from the record. A flag is a reason to ask questions, not a verdict.
- !Caution: Completion date extended from 31 Dec 2027 to 30 Apr 2028.
- ✓Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.
Documents 1
Orders 0
No MahaRERA order or list names this number.
Questions about P99000052644
Is Shri Dajiba Heights delayed?
Its completion moved from 31 Dec 2027 to 30 Apr 2028; the revised date has not passed yet.
How many extensions has it had?
Deedo holds 0 extension certificates for P99000052644. The completion date moved from 31 Dec 2027 to 30 Apr 2028.
Who is the promoter?
MahaRERA records Shrijee Krupa Developers as the promoter of P99000052644.
Is it on any MahaRERA regulatory list?
No MahaRERA order or list that Deedo holds names P99000052644.