Deedo IDDD-M8BVOf 3 registrations whose promised date has arrived, 3 kept it (100%).
Delivery record
1 of 4 registrations with dates moved or missed their RERA date · months late against the original promise
4 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Madhav VatikaP99000015110 | Palghar | Certificate Signed | 31 Jan 2021 | 31 Jan 2021 | On date |
| Madhav VatikaP99000017730 | Palghar | Certificate Signed | 30 Dec 2021 | 30 Dec 2021 | On date |
| Madhav Vatika - IVP99000020342 | Palghar | Certificate Signed | 30 Oct 2022 | 30 Oct 2022 | On date |
| Shri Dajiba HeightsP99000052644 | Palghar | Certificate Signed | 31 Dec 2027 | 30 Apr 2028 | +4 mo |
Shrijee Krupa Developers, in questions
Does Shrijee Krupa Developers finish projects on time?
Of 3 MahaRERA registrations whose promised completion date has arrived, 3 kept it (100%). Across Maharashtra, 73% kept their date.
How many projects has Shrijee Krupa Developers registered with MahaRERA?
3 projects under 4 MahaRERA registrations; 3 completed on MahaRERA.
Does Shrijee Krupa Developers have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.