Shrijee Krupa Developers

Deedo IDDD-M8BV

Of 3 registrations whose promised date has arrived, 3 kept it (100%).

Projects34 RERA registrations
Kept RERA date100%Maharashtra: 73%
Median delay4 mowhen late · Maharashtra: 4 mo
First sales on record0registered first-sale deeds matched so far
Regulatory cases0none on record

Delivery record

1 of 4 registrations with dates moved or missed their RERA date · months late against the original promise

4 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Madhav VatikaP99000015110PalgharCertificate Signed31 Jan 202131 Jan 2021On date
Madhav VatikaP99000017730PalgharCertificate Signed30 Dec 202130 Dec 2021On date
Madhav Vatika - IVP99000020342PalgharCertificate Signed30 Oct 202230 Oct 2022On date
Shri Dajiba HeightsP99000052644PalgharCertificate Signed31 Dec 202730 Apr 2028+4 mo

Shrijee Krupa Developers, in questions

Does Shrijee Krupa Developers finish projects on time?

Of 3 MahaRERA registrations whose promised completion date has arrived, 3 kept it (100%). Across Maharashtra, 73% kept their date.

How many projects has Shrijee Krupa Developers registered with MahaRERA?

3 projects under 4 MahaRERA registrations; 3 completed on MahaRERA.

Does Shrijee Krupa Developers have MahaRERA regulatory cases?

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.