RegisteredCompletion date passedMahaRERA status: Certificate Signed

P99000021693

YASHWANT SANKALP- Jasmin Phase 2 · Saravali, Palghar · Mahalaxmi Infra

Promised for 31 Jul 2025 — that date has passed and MahaRERA does not mark the project complete.

1 year and 4 months past the original promise today.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Risk: The latest completion date on record, 31 Jul 2025, has passed.
  • Clear: Completion date never extended.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 1

Registration certificate10 Oct 2023View

Orders 0

No MahaRERA order or list names this number.

Questions about P99000021693

Is YASHWANT SANKALP- Jasmin Phase 2 delayed?

Yes. MahaRERA records a promised completion of 31 Jul 2025, which has passed, and the project is not marked complete.

How many extensions has it had?

Deedo holds 0 extension certificates for P99000021693.

Who is the promoter?

MahaRERA records Mahalaxmi Infra as the promoter of P99000021693.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P99000021693.