Company or firm · first RERA registration 2017
Mahalaxmi Infra
Deedo IDDD-72E9Of 3 registrations whose promised date has arrived, 0 kept it (0%). The rest ran a median 69 mo late.
Projects33 RERA registrations
Kept RERA date0%Maharashtra: 73%
Median delay69 mowhen late
Flats sold, all time0registered sale deeds
Regulatory cases0none on record
3 registrations of 3 ran past the RERA date
Months late against the original RERA promise, per registration
3 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| JasminP99000009167 | Saravali | Certificate Signed | 31 Jan 2021 | 31 Jan 2021 | +69 mo* |
| TulipP99000012111 | Saravali | Certificate Signed | 31 Jul 2019 | 31 Jul 2019 | +87 mo* |
| YASHWANT SANKALP- Jasmin Phase 2P99000021693 | Palghar | Certificate Signed | 31 Jul 2025 | 31 Jul 2025 | +15 mo* |
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology
