Company or firm · first RERA registration 2017

Mahalaxmi Infra

Deedo IDDD-72E9

Of 3 registrations whose promised date has arrived, 0 kept it (0%). The rest ran a median 69 mo late.

Projects33 RERA registrations
Kept RERA date0%Maharashtra: 73%
Median delay69 mowhen late
Flats sold, all time0registered sale deeds
Regulatory cases0none on record

3 registrations of 3 ran past the RERA date

Months late against the original RERA promise, per registration

3 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
JasminP99000009167SaravaliCertificate Signed31 Jan 202131 Jan 2021+69 mo*
TulipP99000012111SaravaliCertificate Signed31 Jul 201931 Jul 2019+87 mo*
YASHWANT SANKALP- Jasmin Phase 2P99000021693PalgharCertificate Signed31 Jul 202531 Jul 2025+15 mo*
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology