RegisteredRevised date passed1 extensionMahaRERA status: Certificate Signed

P99000009297

Nakshatra Ozone · Tivari, Palghar · Jsb Homes Llp

Promised for 30 Dec 2020, extended once to 30 Dec 2021 — and that date has passed without the project marked complete on MahaRERA.

5 years and 10 months past the original promise today.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Caution: Completion date extended from 30 Dec 2020 to 30 Dec 2021 (1 extension certificate on record).
  • Risk: The latest completion date on record, 30 Dec 2021, has passed.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 2

Registration certificate22 Aug 2017View
Extension certificate9 Sep 2021View

Orders 0

No MahaRERA order or list names this number.

Questions about P99000009297

Is Nakshatra Ozone delayed?

Yes. MahaRERA records a promised completion of 30 Dec 2020, revised to 30 Dec 2021, which has passed, and the project is not marked complete.

How many extensions has it had?

Deedo holds 1 extension certificate for P99000009297. The completion date moved from 30 Dec 2020 to 30 Dec 2021.

Who is the promoter?

MahaRERA records Jsb Homes Llp as the promoter of P99000009297.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P99000009297.