Nakshatra Ozone

Certificate Signed

Tivari, Palghar 401208 |Promoter: JSB Homes LLP

Residential / Group HousingRERAP99000009297
22 Aug 2017Registered with MahaRERA
30 Dec 2020Promised completion
30 Dec 2021Revised completionPushed back 1 year
2Buildings
224Units registered123 booked (55%)
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
Buildings
2
Unit types
Residential224 units in all
Address
S.No. 50, Hissa No.7/8, , Tivari, TivariPIN 401208
Designated bank account
85
Developed in phases
Yes

Location

Coordinates as published by MahaRERA

View on OpenStreetMap 19.16304, 72.83930
Nakshatra Ozone is at latitude 19.16304, longitude 72.83930.

Registered transactions

No registered transactions matched to this project yetSales, resales, rentals and mortgages appear here once registered documents are matched to this project by evidence.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion pushed back 1 year

The latest completion date on record passed 4 years and 10 months ago.

Registered
22 Aug 2017
Promised
30 Dec 2020
Revised
30 Dec 2021

RERA registration

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P9900000929722 Aug 201730 Dec 202030 Dec 2021JSB Homes LLPProject page

2 buildings

Buildings and wings named in the registration

BuildingSanctioned floorsUnits
12a16112
12b16112

Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.

Units and parking

123 of 224 units booked (55%), as the promoter reported to MahaRERA

Residential · 224 units
BuildingTypeCarpet areaUnitsBooked
12aResidential23.41 sq m · 252 sq ft11261
12bResidential23.41 sq m · 252 sq ft11262

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Documents

2 documents held by Deedo, 47 filings listed on MahaRERA's project page

Registration certificate

Extension certificate

Finance

  • PAN CardJSB Homes LLP PAN Card.pdf · uploaded 30 Jul 2017Source

Legal

  • Declaration Form BFormB- JSb Homes LLP-Ozone.pdf · uploaded 30 Jul 2017Source
  • Legal Title reportIndex II - Nakshatra Ozone.pdf · uploaded 31 Jul 2017Source
  • Legal Title reportCertificate of title 50-7-8{2}.pdf · uploaded 31 Jul 2017Source
  • Legal Title reportCertificate of title 50- 8.pdf · uploaded 31 Jul 2017Source
  • Declaration Form BOzone_Form B (1).pdf · uploaded 18 Jun 2019Source
Show all 49 documentsShow fewer documents

Migrated

  • 1 PAN CardJSB Homes LLP PAN Card.pdf · uploaded 30 Jul 2017Source
  • 1 Building Plan Approval (IOD)Self attested CC - Ozone .pdf · uploaded 30 Jul 2017Source
  • 1 Commencement Certificates / NA Order for plotted developmentSelf attested CC - Ozone .pdf · uploaded 30 Jul 2017Source
  • 1 Declaration in FORM BFormB- JSb Homes LLP-Ozone.pdf · uploaded 30 Jul 2017Source
  • 1 Certificates of CA (Form 3)CA certificate07302017 new.pdf · uploaded 30 Jul 2017Source
  • 1 Proforma of Allotment letterDeclaration for Sale agreement - Nakshatra Ozone.pdf · uploaded 30 Jul 2017Source
  • 1 Copy of the legal title reportIndex II - Nakshatra Ozone.pdf · uploaded 31 Jul 2017Source
  • 2 Copy of the legal title reportCertificate of title 50-7-8{2}.pdf · uploaded 31 Jul 2017Source
  • 3 Copy of the legal title reportCertificate of title 50- 8.pdf · uploaded 31 Jul 2017Source
  • 1 Details of encumbrancesjsb LLP encumbrances.pdf · uploaded 31 Jul 2017Source
  • 1 Copy of Layout Approval (in case of layout)Nakshtra-Ozone Plans Layout.pdf · uploaded 31 Jul 2017Source
  • 1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Arch Cet - Nakshatra Ozone.pdf · uploaded 31 Jul 2017Source
  • 1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Engg Cert - Nakshatra Ozone.pdf · uploaded 31 Jul 2017Source
  • 2 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Ozone_Q1.pdf · uploaded 13 Dec 2018Source
  • 3 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Ozone_Q2.pdf · uploaded 13 Dec 2018Source
  • 4 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Ozone_Q3.pdf · uploaded 13 Dec 2018Source
  • 5 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Ozone_Q4.pdf · uploaded 13 Dec 2018Source
  • 6 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Ozone_Q5.pdf · uploaded 13 Dec 2018Source
  • 7 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Nakshatra Primus RERA Architect_Certificate Q-6.pdf · uploaded 31 May 2019Source
  • 8 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Nakshatra Primus - RERA Architect_Certificate Q-7.pdf · uploaded 31 May 2019Source
  • 2 Details of encumbrancesOzone - Encumbrance Certificate.pdf · uploaded 1 Jun 2019Source
  • 2 Declaration in FORM BOzone_Form B (1).pdf · uploaded 18 Jun 2019Source
  • 2 Proforma of Allotment letterOzone Draft Agreement.pdf · uploaded 4 Jul 2019Source
  • 9 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Revised_Architect Certificate Ozone_Q8-min.pdf · uploaded 19 Dec 2019Source
  • 10 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Revised_Architect Certificate Ozone_Q8-min.pdf · uploaded 19 Dec 2019Source
  • 11 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Architect Certificate Ozone_Q9-min.pdf · uploaded 19 Dec 2019Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)Nakshatra Ozone_Form5_2017-2018.pdf · uploaded 3 Jan 2020Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)Nakshatra Ozone_Form5_2018-2019 (2)_New.pdf · uploaded 3 Jan 2020Source
  • 12 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Nakshatra Ozone Form 1 12-02-2020_compressed.pdf · uploaded 25 Feb 2020Source
  • 1 Details of Restarting of Construction work post lockdownOzone-Details of Restarting Construction Post Lockdown.pdf · uploaded 16 Jul 2020Source
  • 13 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Architect Certificate of Nakshatra OZONE Q11.pdf · uploaded 23 Jul 2020Source
  • 14 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Nakshatra Ozone Q12 RERA Certificate-compressed.pdf · uploaded 14 Oct 2020Source
  • 1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentNakshatra Ozone Occupancy Certificate.pdf · uploaded 17 Dec 2020Source
  • 1 Architect’s Certificate on Completion of Project (Form 4)Form 4 Architect_s certificate to be issued on completion of each wing.pdf · uploaded 11 Jan 2021Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)Form5_Ozone_2020_compressed.pdf · uploaded 18 Aug 2021Source
  • 1 Status of Formation of Legal Entity (Society/Co Op etc.)Nakshatra Ozone_A wing (1).pdf · uploaded 2 Oct 2021Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)form 5 ozone.pdf · uploaded 11 Oct 2021Source

Technical

  • DocumentSelf attested CC - Ozone .pdf · uploaded 30 Jul 2017Source
  • DocumentNakshtra-Ozone Plans Layout.pdf · uploaded 31 Jul 2017Source

Technical (Architect)

  • DocumentNakshatra Ozone Q12 RERA Certificate-compressed.pdf · uploaded 14 Oct 2020Source

Technical (Engineer)

  • DocumentEngg Cert - Nakshatra Ozone.pdf · uploaded 31 Jul 2017Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Tivari, Vasai taluka

Survey, CTS, gat or plot numbers

Hissa No.7/8S.No. 50

Boundaries

North
12 M Wide Internal Road
South
Nalla to the South
East
Sr no 57 H No 10 to the East
West
Adjoining Wing C to the West

Source: registration certificates and MahaRERA's project page, as stated there.

Professionals

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectAjay Wade & Associates—
ArchitectVivek Bhole Architects Pvt. Ltd.—
Chartered accountantK B Mistry & Associates—
Chartered accountantKetan Kataria & Associates—
EngineerDeepak Kumar Singh—
Registered real estate agentNimesh Anandkumar Jalan—
Registered real estate agentPatel Deepak Ishwarlal—
Registered real estate agentVimal Gopiram Agrawal—

Source: MahaRERA project page. Contact details are not shown.

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Methodology