Jsb Homes Llp

Company or firm · 2 projects · 2 MahaRERA registrations

Projects22 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date50%1 of 2 past their proposed date, not extended
Median delay+6 movs RERA proposed date · 1 extended
Regulatory cases0MahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Nakshatra OzoneP99000009297Tivari2017Not reported30 Dec 202030 Dec 2021+12 months
Nakshatra Pride-IP99000017763Tivari2018Not reported30 Sep 2023—On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Nakshatra Ozone+12 mo
  • Nakshatra Pride-IOn date

Track record notes

  • 1 of 2 registrations whose RERA proposed completion date has passed was never extended beyond it.
  • Longest extension on record: 12 months, for Nakshatra Ozone (P99000009297).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology