Nine Star Residency Rohini Building · Makane, Palghar · Trinity Concrete Structures Private Limited
Promised for 31 Jul 2018, extended once to 31 Jul 2022 — and that date has passed without the project marked complete on MahaRERA.
8 years and 4 months past the original promise today.
What to watch
Facts from the record. A flag is a reason to ask questions, not a verdict.
- !Caution: Completion date extended from 31 Jul 2018 to 31 Jul 2022 (1 extension certificate on record).
- !Risk: The latest completion date on record, 31 Jul 2022, has passed.
- ✓Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.
Documents 2
Orders 0
No MahaRERA order or list names this number.
Questions about P99000005167
Is Nine Star Residency Rohini Building delayed?
Yes. MahaRERA records a promised completion of 31 Jul 2018, revised to 31 Jul 2022, which has passed, and the project is not marked complete.
How many extensions has it had?
Deedo holds 1 extension certificate for P99000005167. The completion date moved from 31 Jul 2018 to 31 Jul 2022.
Who is the promoter?
MahaRERA records Trinity Concrete Structures Private Limited as the promoter of P99000005167.
Is it on any MahaRERA regulatory list?
No MahaRERA order or list that Deedo holds names P99000005167.