Trinity Concrete Structures Private Limited

Of 1 registration whose promised date has arrived, 0 kept it (0%). The rest ran a median 48 mo late — longer than Maharashtra's 4 mo.

Projects22 RERA registrations
Kept RERA date0%Maharashtra: 73%
Median delay48 mowhen late · Maharashtra: 4 mo
Flats sold, all time0registered sale deeds
Regulatory cases0none on record

1 registration of 2 ran past the RERA date

Months late against the original RERA promise, per registration

2 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Nine Star Residency Rohini BuildingP99000005167MakaneCertificate Signed31 Jul 201831 Jul 2022+48 mo
Trinity Vista Building No 3PR1240002601523KapaseCertificate Signed31 Dec 203131 Dec 2031On date
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology