Promised for 30 Nov 2024, extended once to 30 Nov 2025 — and that date has passed without the project marked complete on MahaRERA.
2 years past the original promise today.
What to watch
Facts from the record. A flag is a reason to ask questions, not a verdict.
- !Caution: Completion date extended from 30 Nov 2024 to 30 Nov 2025 (1 extension certificate on record).
- !Risk: The latest completion date on record, 30 Nov 2025, has passed.
- ✓Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.
Documents 3
Orders 0
No MahaRERA order or list names this number.
Questions about P53100054015
Is Royal Residency delayed?
Yes. MahaRERA records a promised completion of 30 Nov 2024, revised to 30 Nov 2025, which has passed, and the project is not marked complete.
How many extensions has it had?
Deedo holds 1 extension certificate for P53100054015. The completion date moved from 30 Nov 2024 to 30 Nov 2025.
Who is the promoter?
MahaRERA records Swapn Purti Builders And Developers as the promoter of P53100054015.
Is it on any MahaRERA regulatory list?
No MahaRERA order or list that Deedo holds names P53100054015.