Is this project on time and in good standing?

Projects: P + 11 digits (or two letters + 13 digits, like PR1260002500851). Agents: A + 11 digits.

RegisteredRevised date passed1 extensionMahaRERA status: Certificate Signed

P53100003847

Oriental Plaza · Jaysingpur (M Cl), Kolhapur · Mark Construction

Promised for 26 Jul 2019, extended once to 30 Dec 2021 — and that date has passed without the project marked complete on MahaRERA.

7 years and 4 months past the original promise today.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Caution: Completion date extended from 26 Jul 2019 to 30 Dec 2021 (1 extension certificate on record).
  • Risk: The latest completion date on record, 30 Dec 2021, has passed.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 2

Registration certificate6 Aug 2017View
Extension certificate9 Sep 2021View

Orders 0

No MahaRERA order or list names this number.

Questions about P53100003847

Is Oriental Plaza delayed?

Yes. MahaRERA records a promised completion of 26 Jul 2019, revised to 30 Dec 2021, which has passed, and the project is not marked complete.

How many extensions has it had?

Deedo holds 1 extension certificate for P53100003847. The completion date moved from 26 Jul 2019 to 30 Dec 2021.

Who is the promoter?

MahaRERA records Mark Construction as the promoter of P53100003847.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P53100003847.

Answers are generated from the record.

Data through23 Nov 2026, 01:37SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersReport a problemMethodology