RegisteredMahaRERA status: Certificate Signed

P52800078696

Akar Vanaju Estate · Zadgaon Ct, Ratnagiri · Akar Infrastructure

Promised for 27 Dec 2040 and not extended so far.

14 years and 1 month to go until the promised date.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Clear: Completion date never extended.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 1

Registration certificate7 Jan 2025View

Orders 0

No MahaRERA order or list names this number.

Questions about P52800078696

Is Akar Vanaju Estate delayed?

Not so far. MahaRERA records a promised completion of 27 Dec 2040, which has not passed yet.

How many extensions has it had?

Deedo holds 0 extension certificates for P52800078696.

Who is the promoter?

MahaRERA records Akar Infrastructure as the promoter of P52800078696.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P52800078696.

Answers are generated from the record.

Data through3 Nov 2026, 02:25SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersReport a problemMethodology