Akar Infrastructure
Of 3 registrations whose promised date has arrived, 3 were never extended past it (100%).
Projects67 RERA registrations
Kept RERA date100%Maharashtra: 73%
Median delay4 mowhen extended · Maharashtra: 4 mo
Completed0as reported on MahaRERA
Regulatory cases0none on record
2 registrations of 7 moved past the RERA date
Months late against the original RERA promise, per registration
7 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Akar VishwaP52800011556 | Nachane (Ct) | Certificate Signed | 8 Oct 2020 | 8 Oct 2020 | On date |
| Akar VishwaP52800016360 | Nachane (Ct) | Certificate Signed | 10 May 2024 | 10 May 2024 | On date |
| Akar SwaroopP52800018675 | Nachane (Ct) | Certificate Signed | 10 Jan 2024 | 10 Jan 2024 | On date |
| Akar Rajashri SankulP52800034762 | Nachane (Ct) | Certificate Signed | 28 Sep 2028 | 28 Sep 2028 | On date |
| Akar-Anand ViharP52800035144 | Zadgaon Ct | Certificate Signed | 23 Apr 2030 | 23 Aug 2030 | +4 mo |
| Akar Shere PlazaP52800076898 | Zadgaon Ct | Certificate Signed | 30 Nov 2028 | 30 Mar 2029 | +4 mo |
| Akar Vanaju EstateP52800078696 | Ratnagiri | Certificate Signed | 27 Dec 2040 | 27 Dec 2040 | On date |
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology