RegisteredExtendedMahaRERA status: Certificate Signed

P52100080336

Aventis · Tathwade, Pune · Devsia Infracon LLP

Promised for 21 Jun 2030, extended to 21 Oct 2030, which is still ahead.

The revised date is 4 months after the original promise.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Caution: Completion date extended from 21 Jun 2030 to 21 Oct 2030.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 1

Registration certificate20 Aug 2026View

Orders 0

No MahaRERA order or list names this number.

Questions about P52100080336

Is Aventis delayed?

Its completion moved from 21 Jun 2030 to 21 Oct 2030; the revised date has not passed yet.

How many extensions has it had?

Deedo holds 0 extension certificates for P52100080336. The completion date moved from 21 Jun 2030 to 21 Oct 2030.

Who is the promoter?

MahaRERA records Devsia Infracon LLP as the promoter of P52100080336.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P52100080336.