Devsia Infracon LLP
Deedo IDDD-0J7XNone of 3 registrations has reached its promised completion date yet.
Delivery record
3 of 3 registrations with dates moved or missed their RERA date · months late against the original promise
3 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| AventisP52100080336 | Tathwade | Certificate Signed | 21 Jun 2030 | 21 Oct 2030 | +4 mo |
| AventisPR1261012600924 | Tathwade | Certificate Signed | 31 May 2031 | 30 Sep 2031 | +4 mo |
| AventisPR1261012600932 | Tathwade | Certificate Signed | 31 May 2031 | 30 Sep 2031 | +4 mo |
Devsia Infracon LLP, in questions
Does Devsia Infracon LLP finish projects on time?
None of its 3 MahaRERA registrations has reached its promised completion date yet.
How many projects has Devsia Infracon LLP registered with MahaRERA?
1 project under 3 MahaRERA registrations; 0 completed on MahaRERA.
Does Devsia Infracon LLP have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.