RegisteredExtendedMahaRERA status: Certificate Signed

P52100055795

Ashapuri Tulsivan Phase I · Pirangut, Pune · Ashapuri Developers

Promised for 31 Dec 2027, extended to 30 Apr 2028, which is still ahead.

The revised date is 4 months after the original promise.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Caution: Completion date extended from 31 Dec 2027 to 30 Apr 2028.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 1

Registration certificate18 Aug 2026View

Orders 0

No MahaRERA order or list names this number.

Questions about P52100055795

Is Ashapuri Tulsivan Phase I delayed?

Its completion moved from 31 Dec 2027 to 30 Apr 2028; the revised date has not passed yet.

How many extensions has it had?

Deedo holds 0 extension certificates for P52100055795. The completion date moved from 31 Dec 2027 to 30 Apr 2028.

Who is the promoter?

MahaRERA records Ashapuri Developers as the promoter of P52100055795.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P52100055795.