Balaji Residency · Baner, Pune · Balaji Developers

Promised for 31 Dec 2023, extended once to 30 Jun 2024 — and that date has passed without the project marked complete on MahaRERA.

2 years and 11 months past the original promise today.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Caution: Completion date extended from 31 Dec 2023 to 30 Jun 2024 (1 extension certificate on record).
  • Risk: The latest completion date on record, 30 Jun 2024, has passed.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 14

Commencement certificate15 Jun 2022View
Form B15 Jun 2022View
Form 515 Jun 2022View
Registration certificate22 Jun 2022View
Form 2A22 Dec 2023View
Form 522 Dec 2023View
Allotment letter22 Dec 2023View
Extension certificate3 Jan 2024View
Show all 14 documents
OtherView
Layout planView
Building planView
OtherView
OtherView
OtherView

Orders 0

No MahaRERA order or list names this number.

Questions about P52100046332

Is Balaji Residency delayed?

Yes. MahaRERA records a promised completion of 31 Dec 2023, revised to 30 Jun 2024, which has passed, and the project is not marked complete.

How many extensions has it had?

Deedo holds 1 extension certificate for P52100046332. The completion date moved from 31 Dec 2023 to 30 Jun 2024.

Who is the promoter?

MahaRERA records Balaji Developers as the promoter of P52100046332.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P52100046332.