RERA check · free, always
Is this project on time and in good standing?
Projects: P + 11 digits (or two letters + 13 digits, like PR1260002500851). Agents: A + 11 digits.
P52100012713
Ved Vihar Phase II - Building No. 4 · Kothrud, Pune · Rohan Pate Group Of Constructions Llp
Promised for 31 Dec 2021, extended once to 16 Jan 2025 — and that date has passed without the project marked complete on MahaRERA.
4 years and 11 months past the original promise today.
What to watch
Facts from the record. A flag is a reason to ask questions, not a verdict.
- !Caution: Completion date extended from 31 Dec 2021 to 16 Jan 2025 (1 extension certificate on record).
- !Risk: The latest completion date on record, 16 Jan 2025, has passed.
- ✓Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.
Documents 3
Orders 0
No MahaRERA order or list names this number.
Questions about P52100012713
Is Ved Vihar Phase II - Building No. 4 delayed?
Yes. MahaRERA records a promised completion of 31 Dec 2021, revised to 16 Jan 2025, which has passed, and the project is not marked complete.
How many extensions has it had?
Deedo holds 1 extension certificate for P52100012713. The completion date moved from 31 Dec 2021 to 16 Jan 2025.
Who is the promoter?
MahaRERA records Rohan Pate Group Of Constructions Llp as the promoter of P52100012713.
Is it on any MahaRERA regulatory list?
No MahaRERA order or list that Deedo holds names P52100012713.
Answers are generated from the record.